28 Jan 2010 07:32
ο»Ώ
Norseman Gold plc / Epic: NGL / Index: AIM / Sector: Mining & Exploration
NORSEMAN GOLD PLC
('Norseman Gold'Β orΒ 'the Company')
Three Month Report On ActivitiesΒ For The Period Ended 31 DecemberΒ 2009
Β
Norseman Gold, the AIM-listedΒ and ASX-listedΒ Australian gold productionΒ and explorationΒ companyΒ is pleased to announce a three month progress report on its activities for the period to 31Β DecemberΒ 2009.
|
Overview |
3 Months to 31/12/09 |
3 Months to 30/09/09 |
|
|
Production |
oz |
15,721 |
16,160 |
|
Average Realised Gold Price |
A$/oz |
1,203 |
1,150 |
|
Operating Cash CostΒ |
A$/oz |
933 |
900 |
|
Project EBIT |
A$(m) |
1.2 |
0.3 |
|
Capital Investment |
A$(m) |
11.5 |
6.6 |
|
Cash at Quarter End (incl. bullion) |
A$(m) |
24.9 |
31.8 |
Gold production from the Norseman Gold Project during the three monthsΒ to 31 December 2009 totalled 15,721Β ounces at a cash operating cost of A$933Β per ounce gold, generating a profit of A$1.2m. Production is expected to increase steadily in the second half of the financial year.
The ProjectΒ commenced developmentΒ at its third mine, OK Decline, during the quarter. The firstΒ developmentΒ ore has been delivered to the surface stockpileΒ andΒ wasΒ treated in January 2010.Β Β This is the first gold to be recovered from the Company's third mineΒ under itsΒ fill the mill strategy andΒ demonstrates the Company's ability to find and develop gold assets within the project area.
Dewatering at North Royal Open Pit hasΒ commencedΒ andΒ over 21% of the water volumeΒ was pumpedΒ by the end of the quarter.Β Β The first stage drilling programme hasΒ beenΒ completed at the southern end of the open pit.
The preliminary resource estimate for the Perch ReefΒ at the Harlequin Decline returnsΒ an Inferred Resource of 48,000 tonnes at 41.0 g/t gold for 63,000 ounces. It is expected that the confidence level of the resource will improve once further drilling and development is undertaken.
The Company'sΒ capital investmentΒ increasedΒ during the quarterΒ with the development of the OK Decline resulting in the expenditure ofΒ A$11.5MΒ on exploration, capitalised mine development and equipment.
The CompanyΒ hasΒ revised guidance forΒ its full year forecastΒ toΒ between 75,000 to 80,000 ouncesΒ of goldΒ at a cash operating costΒ of between A$800 and A$850Β per ounce in the 2009/10 financial year.
Β
Operating Review
Gold production from the Norseman Gold ProjectΒ during the three month period to 31 December 2009 totalled 15,721Β ounces.Β Β The quarterly production continued in lower grade areas, with the focus remaining on capitalΒ developmentΒ to open up areas for future stoping.Β Β ForΒ theΒ quarter,Β theΒ BullenΒ mine contributed 7,442Β ounces,Β andΒ the Harlequin mineΒ contributedΒ 8,251Β ouncesΒ with 28 ounces from low grade stocks.Β Β The project has now produced over 200,000 ounces of gold for the Company sinceΒ controlΒ was assumedΒ in April 2007.
The gold price received during theΒ quarterΒ rangedΒ fromΒ A$1,136Β toΒ A$1,308Β perΒ ounces, with an average price achieved of A$1,203Β perΒ ounce.Β Β The operations remain un-hedged with a gold price of A$1,210Β perΒ ounceΒ at the date hereof.
Production
|
Β |
Β |
3 months to 31/03/09 |
3 months to 30/06/09 |
3 months to 30/09/09 |
3 months to 31/12/09 |
|
Capital Development |
metres |
590 |
555 |
663 |
767 |
|
OreΒ Development |
metres |
1,212 |
1,279 |
1,617 |
1,152 |
|
Development |
tonnes |
39,876 |
36,620 |
55,327 |
41,210 |
|
Grade |
gAu/t |
2.50 |
3.40 |
2.26 |
2.98 |
|
Mechanised Stoping |
tonnes |
15,174 |
18,114 |
8,018 |
15,967 |
|
Grade |
gAu/t |
4.19 |
4.66 |
2.70 |
2.61 |
|
Airleg Stoping |
tonnes |
48,665 |
44,481 |
42,924 |
38,082 |
|
Grade |
gAu/t |
9.63 |
10.73 |
8.61 |
8.75 |
|
U/G Production |
tonnesΒ |
103,715 |
99,215 |
106,269 |
95,259 |
|
Treated Tonnes |
tonnes |
102,217 |
105,025 |
106,010 |
96,043 |
|
Grade |
gAu/t |
6.12 |
6.66 |
4.86 |
5.21 |
|
Recovery |
% |
98.9% |
98.0% |
97.5% |
97.7% |
|
Recovered Ounces |
ozs |
19,902 |
22,013 |
16,160 |
15,721 |
Β Β During the December 2009 quarter, the Company continued with its capital development programmeΒ to access new ore levels to provide development and stoping blocks for future production.Β Β The access to higher grade stoping blocks did not proceed as anticipated and the increase in grade to normal levels is moving at a slower rate than expected.Β Β However the Company expects the production profile to improve steadily for the next two quarters until the end of the current financial year in June 2010.Β Β It is expected that after this time the production profile at the Bullen and Harlequin Declines will be at the planned levels and will proceed in steady state from there.
In October 2009, the Company approved the commencement of the OK Decline. The two year mine life is based on an initial reserve of 57,000 ounces of goldΒ from the OKΒ MainΒ and the O2 Reef. However current drilling of the Star of Erin orebody is expected to result in a favourable revision of the mine life during the March 2010 quarter.
The first OK Decline development ore, mined from the Star of Erin orebody, was delivered to the surface stockpile and treated in January 2010. The initial schedule forecasts 5,000 ounces being mined in the current 2009/10 financial year and 30,000 ounces being mined in the 2010/11 financial year.
The CompanyΒ expects that the OK Decline will be ramped up and operating in steady state, as planned, by June 2010, so that the company willΒ thenΒ have three mines feeding into the Phoenix treatment plant which will offset some of the production fluctuations that have been experienced when operating only two mines.Β Β Furthermore,Β progress on the fourth mine at the North Royal Open Pit willΒ alsoΒ be more advanced and when this mineΒ starts it will further de-risk the operations production profile. This is theΒ result the Company has spent the last two plus years working towards.
Production forΒ the quarter was 15,721Β ouncesΒ of gold recovered, below the Company's target production from the Bullen and Harlequin Declines. TheΒ Company as a consequence has revised its guidance for theΒ 2009/10 financialΒ year to between 75,000 to 80,000 ounces recoveredΒ (previously 80,000 to 85,000 ounces of gold)Β at aΒ cash cost of A$800 to A$850 per ounceΒ (previously A$720 to A$780 per ounce) fromΒ the Bullen, OKΒ and Harlequin Declines.
The Company forecastΒ for the 2010/11 financialΒ year remains unchanged at 105,000 to 110,000 ounces recovered at cash costs of between A$670 to A$730 per ounce of gold.Β
Operating Costs
Β
As a result of the lower production profile,Β theΒ net directΒ cashΒ operatingΒ costs per ounceΒ for the quarter haveΒ increasedΒ to A$933Β per ounce of gold recovered,Β above theΒ previousΒ forecast range of between A$720 to A$780 per ounce. However,Β as indicated above,Β the Company expects that itsΒ full year forecast costsΒ for the Bullen, OKΒ and Harlequin DeclinesΒ will reduce to the A$800 to A$850 per ounce markΒ as the production profile returnsΒ to the required levels. Total operating costs have been maintained at close to budgeted levels.
From an accounting profit and loss point of view,Β the Norseman Project generatedΒ estimatedΒ EarningsΒ Before Interest and Tax ('EBIT') ofΒ A$1.2Β millionΒ forΒ the quarter.
Cash Balances
Cash balancesΒ at the end of the period totalledΒ A$24.9Β million (A$23.5Β millionΒ excluding bullion).Β Β Approximately A$5.5Β millionΒ of this cash balance is committed toΒ cash-backedΒ environmental bonds.
The Company paid its first income tax payment of A$2.9 million during the quarter.
Capital ExpenditureΒ
The major part of the capital expenditure for the month was on the equipment and infrastructure for the OK Decline.Β Β The new mine took delivery of most of the items needed to start and at the end of the quarter had only installation work to complete.
The CompanyΒ completed the camp expansion during the quarter.Β Β Forty new self contained rooms have been placed on-site in the main accommodation camp and were being occupied by the end of the quarter.Β
A total of A$11.5Β million in capital was invested during the quarter.Β Β Significant capital expendituresΒ were made onΒ mobile equipment (A$6.8 million),Β exploration (A$2.0Β million) andΒ capitalised mineΒ development (A$2.7Β million).
Mine Production
TheΒ capitalΒ development atΒ theΒ HarlequinΒ DeclineΒ progressed towardsΒ the next levelsΒ at the Redfin/PerchΒ and HV1Β Reefs.Β Β At the commencement of the March 2010 quarter the two boom jumbo had reached the -312 Level on the Redfin/Perch and was to complete one more level before going to the Bullen Decline.Β Β OreΒ development rates were excellent,Β with the Harlequin ore development focussing on the Redfin/PerchΒ ReefΒ and the HV1 Reef.Β Β Stoping focused on increasing the mechanised tonnes stoped and on moving airleg miners into higher grade areas in the Perch Reef.Β
The Bullen capitalΒ development focussed on theΒ Bullen,Β Norseman andΒ St Patrick's Reefs.Β At the end of the quarter the two boom jumbo went to OK Decline to commence refurbishment of the decline as planned.Β Β The jumbo is expectedΒ to relocateΒ from Harlequin Decline early in the quarter to continue development on the Norseman and Bullen Reef.
The Company's objectiveΒ at bothΒ Bullen and HarlequinΒ isΒ to maintain the production at a consistent level whileΒ continuing to seek more efficiencies.Β Β To this end, the manning at Bullen was adjusted downward during the quarter to reflect its production profile, with a number of personnel moved to fill vacancies at theΒ Harlequin and OK Declines.
Mine Exploration
Diamond drillingΒ at HarlequinΒ has been focussed on the Perch Reef from the diamond drillΒ cuddy on the RedfinΒ -285m Level. Drilling has continued to produce excellent results and the orebody has still not been closed off by the drilling.Β Β The next stage of the drilling of this orebody will be to move higher up the mine to a diamond drill cuddy at the -154m Level and to continue to test the extent of the reef. Drilling from the new cuddy is expected to commence in the March 2010 quarter.
The preliminaryΒ resource estimate for the Perch Reef was also completed in December returning an Inferred Resource of 48,000 tonnes at 41.0 g/t goldΒ for 63,000 ounces using a high grade cut of 300 g/t and a low grade cut of 5.0 g/t.Β Β It is expected that the confidence levelΒ of the resource will improve once further drilling and development is undertaken.
Perch Reef significantΒ drillingΒ results have been received as follows;
1.7m @ 4.0 g/t gold from 30.0m and
1.0m @ 21.2 g/t gold including
0.2m @ 42.3 g/t gold in drill-hole HD1776
0.7m @ 63.9 g/t gold from 85.7mΒ including
0.2m @ 298.9 g/t gold and
2.2m @ 20.0 g/t gold from 91.8m including
0.6m @ 54.7 g/t gold and
2.7m @ 2.7 g/t gold from 95.8m and
1.0mΒ @ 13.5 g/t gold from 100.4m and
2.9m @ 3.6 g/t gold from 103.8m and
2.0m @ 6.6 g/t gold from 115.2 m in drill-hole HD1778
0.3m @ 192.6 g/t gold from 184.0mΒ and
1.8m @ 53.8 g/t gold from 188.3m including
0.4m @ 92.9 g/t gold from 189.3m and
0.2m @ 113.5 g/t gold from 190.6mΒ in drill-hole HD1779
0.5m @ 44.5 g/t gold from 162.6m in drill-hole HD1784
1.3m @ 18.2 g/t gold from 134.8m including
0.2m @ 102.0 g/t gold in drill-hole HD1787
1.1m @ 36.4 g/t gold from 50.8m in drill-hole HD1793
2.2m @ 59.3 g/t gold from 55.8m including
0.3m @ 342.0 g/t gold and
0.5m @ 70.9 g/t gold andΒ
1.2m @ 28.6 g/t gold from 64.7m including
0.3m @ 85.0 g/t gold in drill-hole HD1794Β
Diamond drilling at Bullen hasΒ continued withΒ the new diamond drill rig fromΒ the first week of October.Β Β The rig has made good progress and significant results are outlined below.
Mararoa Reef Drilling
2.5m @ 2.6 g/t gold from 106.7m in drill-hole BN467
St Patrick's South Drilling
1.4m @ 3.9 g/t gold from 323.3m in drill-holeΒ BN659
Norseman (Mt Barker) Drilling
1.25m @ 8.5 g/t gold from 11.8m in drill-hole BN700
Regional Exploration and Third Mine Development
The CompanyΒ has continued with its programmeΒ of third mine development.Β Β The start-up of OK Decline progressed during the quarter as did the dewatering at North Royal Open Pit. The Company currently has three underground diamond rigs drilling atΒ theΒ Bullen, OK and Harlequin DeclinesΒ and has approved the purchase of a fourth drill rig to commence drilling medium term exploration targets from underground.Β
OK Decline
Mobilisation of surface infrastructure, mobile equipment and personnel proceeded during the quarter.Β Β At the end of the quarter surface earthworks had been completed and construction of surface facilities had commenced with the laying of concrete for pads for theΒ workshops,Β offices and refuelling facilities.Β Β Construction of buildings is expected to be complete by the end of theΒ MarchΒ 2010 quarter.
Personnel and mobile equipment had also commenced arriving on site.Β Β Refurbishment of the existing decline had commenced with the new two boom jumbo and ore development had commenced on the Star of Erin orebodyΒ with first ore processed by theΒ PhoenixΒ treatment plant by the end of January 2010.Β Β This first gold poured from OK Decline is a significant milestone for the Company.
The drilling underground into the Star of Erin orebody continued during the quarter. Results continued to be positive and it is expected that there will be a new resource, initial preliminary reserve and consequently first pass mining schedule for the mining of this orebody during the March 2010 quarter.Β Β The significant results from the Star of Erin drilling received during the quarter are as follows;
0.6m @ 25.4 g/t gold from 174.9m and
0.4m @ 41.0 g/t gold from 182.0m and
2.0m @ 2.7 g/ gold from 185.0m in drill-hole OKD196
3.6m @ 12.0 g/t gold from 137.6m including
0.8m @ 26.0 g/t gold from 137.6m and
0.9m @ 22.3 g/ gold from 138.4m in drill-hole OKD201
1.2m @ 10.4 g/t gold from 148.2m including
0.4m @ 18.8 g/t gold from 148.2m in drill-holeΒ OKD245
3.0m @ 14.7 g/t gold from 68.4m including
1.0m @ 33.5 g/t gold from 68.4m and
1.0m @ 7.8 g/t gold from 69.4m in drill-hole OKD246
1.0m @ 151.0 g/t gold from 159.0m including
0.7m @ 215.0 g/t gold from 159.3m and
0.7m @ 10.7 g/t gold from 182.3m in drill-hole OKD248
1.0m @ 28.9 g/t gold from 107.2m in drill-hole OKD249
3.0m @ 2.8Β g/t gold from 73.0m including
1.0m @ 5.2 g/t gold from 75.0m in drill-hole OKD252
2.0m @ 8.4 g/t gold from 83.0m including
1.0m @ 15.0 g/t gold from 83.0m and
4.0m @ 2.2 g/t gold from 86.0m in drill-hole OKD258
0.3m @ 28.0 g/t gold from 32.3m in drill-hole OKD285
The original schedule for theΒ OK Decline was to provideΒ mainly lower grade ore from development in the first six months of production with full stoping and development operations not being achieved until the 2010/11 financial year. The resultsΒ from the Star of Erin orebody haveΒ given encouragement to the mine being able to stope from this area sooner than when expected from the OK Main and O2 Reef. The result of this potential is twofold, in that higher grade stope ore may be treated sooner than expected,Β and it will beΒ at a lower cost base than the scheduled development ore.
North Royal Open Pit
The dewatering of the North Royal Open Pit gathered momentum during the quarter with the commissioning of both pumps and the pipe-work to dewater the pit.Β Β Pumping rates of over 400 litres per secondΒ have been achieved during the quarter.Β Β The dewatering at the end of the quarter had removed over 21%Β ofΒ the volume ofΒ water from the open pit.
To continue to advance the project surface drilling was undertaken on the southern end of the pit to test the resources that are located under the pit floorΒ in that area.Β Β At quarter end theΒ drillΒ programmeΒ had been completed andΒ logging and assaying of the drill-holes was being undertaken.Β Β Β Β Significant results that have been received so far for theΒ North Royal South drillingΒ are listed below:
1.0m @ 5.2 g/t gold from 154.0m and
0.8m @ 7.4 g/t gold from 156.8m in drill-hole NRD014
1.0m @ 9.3 g/t gold from 63.0m in drill-hole NRD030
2.0m @ 2.9 g/t gold from 12.0m in drill-hole NRD036
Once the remainderΒ of the results are received, the dataΒ will be analysed and a new resource generated.Β Β On the current rate of progress, with the dewatering and the drilling required to improve the confidence level of the resources to be mined, it is anticipated that mining will now potentially commenceΒ at North Royal in the December 2010 quarter.
Corporate Review
The Company has remained focused on the strategy to fill theΒ PhoenixΒ treatment plantΒ via the commencement at the OK Decline and the dewatering and drilling at the North Royal Open Pit. As a consequence other projects such as Norseman IronΒ OreΒ and the Tailings Retreatment project have not advanced during the quarter. Once the OK Decline is operating as a producing mine the resources will become available to advance these projects at a quicker rate.
The plan for current MarchΒ 2010 quarterΒ is to complete the mobilisation and construction at OK Decline, continue the dewatering at North Royal Open Pit andΒ surface drilling for ongoing resource delineation, including a portion of the Crown Reef closer to the surface.
Β Β Competent Persons - Consent for Release
The information in this report that relates to Exploration Results, Mineral Resources and Ore Reserves is based on data generated by employees of Central Norseman Gold CorporationΒ LimitedΒ who have the relevant experience and qualifications to qualify as competent persons.
Β
The parts of this report that relate to Exploration Results, Mineral Resources and Ore Reserves were compiled by Barry Cahill using that data.Β Β He is a Member of the Australasian Institute of Mining and Metallurgy and has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which they are undertaking to qualify as a Competent Person as defined in the 2004 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves". He has consented to the inclusion in the report of the matters based on this information in the form and context in which it appears.
Forward-Looking Statements
This regulatory news release contains certain forward looking statements, which include assumptions with respect to future plans, results and capital expenditures.Β Β The reader is cautioned that assumptions used in the preparation of such information may prove to be incorrect.Β Β All such forward looking statements involve substantial known and unknown risks and uncertainties, certain of which are beyond the Company's control.Β Β Please refer to the Company's Admission Document available from the Company's web site for a list of risk factors. Β The Company's actual results could differ materially from those expressed in, or implied by, these forward-looking statements and, accordingly, no assurances can be given that any of the events anticipated by the forward-looking statements will transpire or occur, or if any of them do so, what benefits the Company will deriveΒ there from.Β Β All subsequent forward-looking statements, whether written or oral, attributable to the Company or persons acting on its behalf are expressly qualified in their entirety by these cautionary statements.Β Β Furthermore, the forward-looking statements contained in this news release are made as at the date of this news release.
* * ENDS * *
For further information visitΒ www.norsemangoldplc.comΒ or contact:
Barry Cahill Norseman Gold Plc Tel: +61 (0) 8 9473 2200
Guy Wilkes Ocean Equities Ltd Tel: 020 7786 4370
William Vandyk Astaire Securities Plc Tel: 020 7448 4400
Hugo de Salis StΒ Brides Media & Finance Ltd Tel: 020Β 7236 1177
E-mail investors@ngold.com.au
Note to editors:
Norseman Gold plc is an AIM listedΒ and ASX listedΒ Australian gold production company, which acquired the Norseman Gold Project in May 2007,Β Australia's longest continually running gold operation.Β Β The Norseman Gold Project is located in the Eastern Goldfields of Western Australia in the highly prospective Norseman-Wiluna greenstone belt, 725km east ofΒ PerthΒ and 186km fromΒ Kalgoorlie.
Gold was first found on the Norseman field in 1894 and over the last 65 years it has produced over 5.5 millionΒ ozΒ of gold. The mine is currently producing from two high-grade narrow-vein underground mines - the Bullen and the Harlequin. Currently, it has a total resource inventory ofΒ 3.7Β millionΒ ozΒ of gold at an average grade ofΒ 5.5Β g/t.
The tenements cover a 1,614Β sq km area centred on theΒ NorsemanΒ Township. The landholding comprises 179 contiguous tenements consisting of 13 Exploration Licences, 106 Mining Licences, 45 Prospecting Licences, 15 Miscellaneous Licences and 29 Mining Lease Applications.
The Company's strategy is focused on extending the mine life through the conversion of resources into reserves and identifying additional resources and obtaining additional ore for the operating mill through the development of a thirdΒ and subsequent mines. The Company has fifteen advanced resource projects under review of which three have pre-development work being undertaken on them.Β Β It is anticipated that at least one if not all the pre-development projects will develop into mining propositions.
Follow the stocks