Ncondezi Project Timetable Update

15 Apr 2020 07:00

RNS Number : 6535J
Ncondezi Energy Limited
15 April 2020
 

 

News Release  

 

 

Ncondezi Project Timetable Update

 

15 April 2020: Ncondezi Energy Limited ("Ncondezi" or the "Company") (AIM: NCCL) is pleased to provide a general update on the planned steps to progress the proposed integrated Ncondezi 300MW coal-fired power project and coal mine in Tete, Mozambique (the "Project").

 

Highlights:

 

· Updated Project timetable agreed by Ncondezi and its partners following submission of updated tariff proposal to Electricidade de Moçambique ("EDM")

 

· Key target milestones for Q2 2020:

o Tariff negotiation concluded with EDM

o Shareholders agreement term sheet concluded

o Engineering, Procurement and Construction ("EPC") contract in agreed form

o Ncondezi historical costs audit completed

 

· Key target milestones for H2 2020:

o Power Purchase Agreement ("PPA") in agreed form with EDM

o Power Concession Agreement ("PCA") in agreed form with Ministry of Mineral Resources and Energy ("MIREME")

o Shareholder agreement entered into

 

· Project Financial Close is targeted for H1 2021

 

Note: Timetable subject to change due to developing impact of COVID-19

Ncondezi Chief Executive Officer, Hanno Pengilly said: "The successful submission of the updated Project power tariff has opened up the next phase of key development work to further de-risk the project and firm up the underlying Project value.

A key priority between now and the end of June will be finalising the power tariff negotiations with EDM. I believe the Project is uniquely positioned with a competitive tariff offering and world class partners. At this stage the full impact of COVID-19 is unknown however it is clear that large scale infrastructure projects, such as the Ncondezi Project, can play a major role in giving economies a critical boost in the short term whilst supporting long term growth in the future. As an advanced stage project, the Ncondezi Project has significant potential to mobilise quickly, create much needed jobs and provide access to a reliable and affordable source of power, helping to close the regional infrastructure gap and serving as a catalyst for economic development.

In addition to the tariff negotiations, today's announcement highlights the workstreams that will be run in parallel over the remainder of the year. Finalisation of the EPC contract, PPA and PCA are cornerstone milestones to finalise debt and equity financing, whilst the shareholders agreement term sheet and full form agreement and historical costs audit will crystallise the Project value to shareholders.

Further updates will be made to shareholders as Project milestones are progressed."

 

Enquiries

 

For further information please visit www.ncondezienergy.com or contact:

 

Ncondezi Energy

Hanno Pengilly

+27 (0) 71 362 3566

 

Liberum Capital LimitedNOMAD & Joint Broker

 

Andrew Godber, Edward Thomas, Kane Collings

+44 (0) 20 3100 2000

Novum Securities Limited

Joint Broker

Colin Rowbury

+44 (0) 20 7399 9427

 

Pimlico Advisory Ltd

Investor Relations

Elizabeth Johnson

+44 (0) 777 56 55 927

 

 

About Ncondezi Energy

 

Ncondezi is an African power development company with an advanced staged, integrated 300MW thermal coal power plant and mine project located in the Tete Province, Northern Mozambique.

 

The Company is focused on providing reliable, affordable and accessible baseload energy to Mozambique and secure against the effects of water drought and intermittency of new renewables. This project supports Mozambique's energy strategy of universal electricity access by 2030. According to the World Bank, only 30% of the Mozambican population had access to energy in 2017. The Ncondezi Project would provide 300MW of reliable and available power helping to close the infrastructure gap of the region and serving as a catalyst for economic development.

 

The power plant will be designed to be equipped with state-of-the-art emissions controls technologies that will reduce local air pollutants, minimizing the plant's impact on the environment and ensuring its compliance with the most stringent emission standards

 

In April 2019 the Company announced a proposed Joint Venture with GridX Africa Power Development to enter into the Commercial and Industrial ("C&I") renewable and battery storage sector and in October 2019 announced their first investment in an off grid solar battery project. The move into the C&I solar and battery storage sector offers a significant opportunity for the Company to complement the existing large-scale baseload power project and access near-term low-risk annuity income streams which have significant growth potential.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDKKQBDDBKBBQD
Date   Source Headline
24th Jan 20197:00 amRNSShareholder Loan Conversion
16th Jan 20197:00 amRNSIssue of Equity
28th Dec 20187:00 amRNSProject Update
21st Dec 20187:00 amRNSUpdated Project Presentation
10th Dec 201812:01 pmRNSHolding(s) in Company
5th Dec 20187:00 amRNSIssue of Equity
26th Nov 20187:00 amRNSProject Update
16th Nov 20187:01 amRNSShareholder Loan Restructuring Complete
5th Nov 201812:30 pmRNSResult of AGM
5th Nov 20187:00 amRNSGeneral Update
12th Oct 20187:00 amRNSNotice of AGM
3rd Oct 20188:07 amRNSHolding(s) in Company
28th Sep 20187:00 amRNSInterim Results and Directorate Change
30th Aug 201810:45 amRNSGeneral Update
10th Aug 20187:00 amRNSShareholder Loan Update
26th Jul 20187:00 amRNSProject Update
6th Jul 201811:49 amRNSHolding(s) in Company
6th Jul 201810:38 amRNSHolding(s) in Company
29th Jun 20187:00 amRNSAnnual Financial Report
11th Jun 20187:00 amRNSFinancial Model Update
30th May 20182:30 pmRNSIssue of Equity
29th May 20187:00 amRNSShare Option Grants
4th May 20187:00 amRNSPlacing to Raise £950,000
3rd May 20187:00 amRNSProject Update
30th Apr 20184:40 pmRNSSecond Price Monitoring Extn
30th Apr 20184:35 pmRNSPrice Monitoring Extension
27th Apr 201811:05 amRNSSecond Price Monitoring Extn
27th Apr 201811:00 amRNSPrice Monitoring Extension
25th Apr 20187:00 amRNSProject Update
18th Apr 20187:00 amRNSProject Update
27th Dec 20177:00 amRNSProject Update
28th Nov 20173:45 pmRNSResult of AGM
9th Nov 20177:09 amRNSNcondezi signs NBO with GE and CMEC
30th Oct 20172:30 pmRNSDirector/PDMR Shareholding
30th Oct 20177:00 amRNSNotice of AGM
20th Oct 20177:00 amRNSNcondezi Agrees Non-Binding Offer with GE and CMEC
18th Oct 20177:00 amRNSPlacing to Raise £750,000
29th Sep 20177:00 amRNSHalf-year Report
27th Sep 20172:05 pmRNSSecond Price Monitoring Extn
27th Sep 20172:00 pmRNSPrice Monitoring Extension
13th Sep 20174:00 pmRNSChange of Registered Office
4th Sep 20177:00 amRNSShareholder Loan Extension
25th Aug 20177:00 amRNSProject and Financing Update
20th Jul 20177:00 amRNSProject Update
30th Jun 20177:00 amRNSFinal Results
23rd Jun 20175:15 pmRNSUS$582,000 Loan Facility Agreed - Amend
23rd Jun 20177:00 amRNSUS$582,000 Loan Facility Agreed
26th May 20177:24 amRNSExclusive Discussions with SEP Suspended
11th May 20177:00 amRNSShareholder Loan Extension
10th May 20177:00 amRNSProject and Funding Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.