Corihuarmi Production June Quarter, 2010

14 Jul 2010 07:00

RNS Number : 2849P
Minera IRL Limited
14 July 2010
 



 

 

 

 

 

Minera IRL Limited - Corihuarmi Gold Mine Production June Quarter, 2010

 

 

London, 14 July 2010: Minera IRL Limited ("Minera IRL" or the "Company"), (TSX:IRL) (AIM:MIRL) (BVL:MIRL) the Latin American focused gold mining, development and exploration company, announces production results from its Corihuarmi Gold Mine for the quarter ending June 2010.

Highlights:

·; Gold production of 8,098 ounces, 10% above budget

·; Quarterly cash operating costs of $365 per ounce

·; Gold sales prices for the quarter averaged $1,201 per ounce

·; Permitting to increase treatment rate by 35% in 2011

 

Corihuarmi production results are summarized in the table below:

June Quarter

2010

March Quarter

2010

June Quarter

2009

Ore mined and stacked on heap - tonnes

351,952

371,963

389,162

Ore grade, mined and stacked - g/t Au

0.81

1.02

0.81

Production - Gold, fine ounces

8,098

7,071

7,753

Shipments - Gold, fine ounces

8,253

7,541

7,117

Sale price received - Gold, US$/ounce

1,201

1,110

941

Cash operating cost - US$/ounce

365

432

393

 

Minera IRL Limited Executive Chairman, Courtney Chamberlain, comments "Corihuarmi has, once again, performed beyond our expectations. Gold production was 10% above budget and spot gold sales achieved a price of over US$1,200 per ounce. The net effect was that revenue from Corihuami for the quarter of US$9.9 million exceeded the previous quarter by US$1.5 million and the corresponding quarter of 2009 by US$3.2 million, close to a 50% increase. The margin also improved with costs decreasing to US$365/oz providing increased cash to apply to our project development and exploration activities."

An amended Environmental Impact Assessment will be lodged in the next quarter with the authorities to allow ore production to be increased by 35% to 2 million tonnes per annum in 2011. This will allow economies of scale to be applied toward profitably treating lower grade ore which will be particularly attractive at high gold prices. The extra capacity will also allow large scale production trials on broken scree material with an inferred resource of 3,765,000 tonnes grading 0.45g/t containing 54,600 ounces of gold.

Production and cost statistics from Corihuarmi have been internally generated by Minera IRL and are unaudited.

This press release was reviewed by Courtney Chamberlain, Executive Chairman of the Company, BSc and MSc Metallurgical Engineering, a Fellow of the Australian Institute of Mining and Metallurgy (AUSIMM), who is the designated Qualified Person for the purposes of National Instrument 43-101 and has approved the technical information in this press release.

 

For more information please contact:

 

Minera IRL Limited

Trish Kent, Vice President, Corporate Relations

+511 4181230

 

Arbuthnot Securities (Nominated Adviser & Broker, London)

+ 44 (0)20 7012 2000

Hugh Field/Richard Johnson

The Equicom Group Inc. (Investor Relations, Canada)

James Kitchen, Account Executive

+1 416 815 0700

(ext 267)

 

Bankside Consultants (Financial PR, London)

+ 44 (0)20 7367 8888

Simon Rothschild

Louise Mason

 

 

Minera IRL Limited is the AIM traded, TSX and BVL listed holding company of precious metals mining and exploration companies focused in Latin America. Minera IRL is led by an experienced senior management team with extensive industry experience, particularly in operating in South America. The Group operates the Corihuarmi Gold Mine and is developing the Ollachea Gold Project in Peru and Don Nicolas Project in Argentina.

 

 

The Toronto Stock Exchange neither approves nor disapproves the information contained in this News Release.

 

Some of the statements contained in this release are forward-looking statements, such as estimates and statements that describe the Company's future plans, objectives or goals, including words to the effect that the Company or management expects a stated condition or result to occur. Since forward-looking statements address future events and conditions, by their very nature, they involve inherent risks and uncertainties.

 

While these forward-looking statements, and any assumptions upon which they are based, are made in good faith and reflect our current judgment regarding the direction of our business, actual results will almost always vary, sometimes materially, from any estimates, predictions, projections, assumptions or other future performance suggestions herein. Except as required by applicable law, Minera IRL Limited does not intend to update any forward-looking statements to conform these statements to actual results.

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCGGURAMUPUGWW
Date   Source Headline
21st Sep 20151:50 pmRNSSuspension - Minera IRL Limited
12th Nov 20144:40 pmRNSSecond Price Monitoring Extn
12th Nov 20144:35 pmRNSPrice Monitoring Extension
18th Sep 20142:56 pmRNSChairman to Present at Proactive Investor Forum
21st Feb 20147:00 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
17th Feb 20145:33 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
17th Feb 20145:29 pmRNSNOTIFICATION OF INTEREST IN SHARES
7th Feb 20149:41 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
5th Feb 20145:07 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
29th Jan 20147:00 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
3rd Jan 20145:07 pmRNSHolding(s) in Company
1st Nov 20137:00 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
18th Oct 20135:32 pmRNSTR-1: NOTIFICATION OF INTEREST IN SHARES
16th Oct 20135:52 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
11th Oct 20135:07 pmRNSForm 8.3 - [Minera]
11th Oct 201312:42 pmRNSForm 8.5 (EPT/RI)
11th Oct 201311:12 amRNSForm 8.5 (EPT/RI)
11th Oct 201310:03 amRNSForm 8.3 - Minera IRL Limited
11th Oct 20137:00 amRNSTermination of discussions with Minera IRL Ltd
10th Oct 20134:40 pmRNSSecond Price Monitoring Extn
10th Oct 20134:35 pmRNSPrice Monitoring Extension
9th Oct 201311:13 amRNSForm 8.3 - Minera IRL Limited
9th Oct 201311:12 amRNSForm 8.5 (EPT/RI)
9th Oct 201310:50 amRNSForm 8.5 (EPT/RI)
8th Oct 20131:51 pmRNSForm 8.3 - Minera IRL Limited
8th Oct 201310:48 amRNSForm 8.5 (EPT/RI)
8th Oct 201310:03 amRNSForm 8.5 (EPT/RI)
7th Oct 20133:46 pmRNSPublic Dealing Disclosure under Rule 8 DD
7th Oct 20133:44 pmRNSPublic Dealing Disclosure under Rule 8 DD
7th Oct 201312:37 pmRNSForm 8.3 - Minera IRL Limited
7th Oct 201312:22 pmRNSForm 8.3 - Minera IRL Ltd
7th Oct 201312:01 pmRNSForm 8.5 (EPT/RI)
7th Oct 201311:16 amRNSForm 8.5 (EPT/RI)
4th Oct 20134:40 pmRNSSecond Price Monitoring Extn
4th Oct 20134:35 pmRNSPrice Monitoring Extension
4th Oct 20134:21 pmRNSStatement re: Possible Offer
2nd Oct 20134:35 pmRNSPrice Monitoring Extension
25th Sep 20137:20 amRNSNOTIFICATION OF INTEREST IN SHARES
23rd Aug 20137:00 amRNSHolding(s) in Company
23rd Aug 20137:00 amRNSHolding(s) in Company
12th Jun 20137:00 amRNSNotice of Annual General and Special Meeting
22nd May 20137:00 amRNSOllachea Community Endorsement of ESIA
14th May 20137:08 amRNSInterim Financial Accounts
14th May 20137:01 amRNSManagement's Discussion and Analysis
14th May 20137:00 amRNSFirst Quarter 2013 Financial Results
9th May 20134:32 pmRNSNOTIFICATION OF INTEREST IN SHARES
9th May 20137:00 amRNSPatagonia Exploration Results
4th Apr 20136:19 pmRNSAnnual Report & Accounts
2nd Apr 20137:00 amRNSOllachea Exploration Results
2nd Apr 20137:00 amRNSNEW CONFERENCE CALL NUMBERS FOR FULL YEAR RESULTS

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.