Third FlexGen Funding & 7 MW Site Update

19 Feb 2026 07:00

RNS Number : 5602T
Quantum Data Energy PLC
19 February 2026
 

Quantum Data Energy PLC

(Incorporated in England and Wales)

(Registration Number: 12886458)

LEI :213800HFVHGJ9YGO9F71

Share code on the LSE: MAST

ISIN: GB00BNG90H86

 

Dated: 19 February 2026

 

Quantum Data Energy PLC

("Quantum", "QDE" or the "Company")

 

QDE Third FlexGen Asset Funding & Construction Progress Update,

and Acquisition of 7 MW FlexGen Brownfield Site Update

 

London, UK - Quantum Data Energy PLC (LSE: MAST) is pleased to announce, further to its RNS announcements dated 3 February 2026 and 9 February 2026 respectively, that the Company is continuing to make significant progress to get its third flexible generation power project to financial close and into construction and commercial operations. QDE is in advanced discussions with Power Balancing Services ("PBS"), regarding QDE's 100% owned Bordersley 5 MW flexible generation project, as previously announced.

 

QDE has agreed in principle with PBS to co-fund the capex of its Bordesley 5 MW flexgen project, and the capex funding will be structured at project SPV level. QDE and PBS are busy finalising the investment agreement which is in near final agreed form, and expected to be executed and completed shortly at which time the key terms of the transaction will be announced.

 

The rationale of partnering with PBS to co-fund the project's capex is mainly because QDE currently owns 100% of the shovel-ready project, which does not generate any income yet. In order for the project to go into commercial production and generate income, it requires construction and associated capex funding. The capex funding for a typical new-build 5 MW flexible generation project is around £3.5m. In order to limit dilution for QDE's existing shareholders, the Company chooses to apply capital discipline and efficiency and to partner with an experienced and reputable investor such as PBS to co-fund the capex of its development projects. The end result is that QDE will own a significant equity stake in an asset that is generating income, increase QDE's portfolio of MW's in production, increase QDE's revenues, with limited capital investment required from QDE.

 

Further, in tandem with finalising the investment agreement with PBS, full preparations are underway for the construction of the site. Comprehensive engineering, procurement, and construction ("EPC") proposals have been received from leading EPC contractors, and availability of key equipment confirmed. The site's grid- and gas connection construction are also underway. It is expected that the construction of the site will be completed and the site in full commercial production and income generating in Q4 2026. As a reminder, QDE's Pyebridge flexgen asset that is in production, currently generates total revenues of c. £290,000 per MW per annum (see RNS announcement dated 3 February 2026).

 

Progress Update on Acquisition of 7 MW Brownfield FlexGen Site:

QDE is pleased to announce, further to its RNS announcement dated 6 November 2025, that it has made significant progress towards the completion of the acquisition of the 7 MW 11kV flexible generation power brownfield site located in England (the "FlexGen Site"). All technical and legal due diligence have essentially been successfully completed, and the purchase contract is near final agreed form. QDE is awaiting final official confirmation from the DNO regarding the FlexGen Site's grid connection date under NESO's grid connection reform, which is expected around end March 2026. Once the aforementioned final official confirmation is received, it is expected that the purchase of the FlexGen Site will be completed shortly thereafter.

 

Pieter Krügel, CEO at Quantum Data Energy PLC, said: "We are delighted with the ongoing positive progress made to get our third flexgen asset constructed and into production. By applying capital discipline and efficiency, we limit QDE's capital requirements and dilution of existing shareholders. We are also working on a number of additional near term growth opportunities, and we look forward to providing the market with further positive progress updates over the coming weeks and months."

 

Issue of Broker Warrants:

Further to the Company's RNS announcement dated 9 February 2026, as part of the acceleration capital funding (the "Acceleration Capital") which was arranged by Fortified Securities ("Fortified"), the Company's sole corporate broker, the Company will grant to Fortified or associates, broker warrants valid for three years from the issue date which shall give Fortified the right to subscribe for one ordinary share for each warrant issued. The number of warrants to be issued is calculated as warrants equivalent to 6% of the gross aggregate value of the Acceleration Capital consideration at the Placing Price.

 

Stay up to date with QDE's latest news and updates by joining our emailing list and social media channels, as follows:

 

Website

https://quantumdata.energy

General enquires

https://quantumdata.energy/contact

RNS email alerts

https://quantumdata.energy/news

LinkedIn

https://www.linkedin.com/company/quantum-data-energy-plc/

X (formerly Twitter)

@mastplc

 

About Quantum Data Energy PLC:

Quantum Data Energy PLC (LSE: MAST) is a UK-based developer, operator and owner of flexible generation power assets. The Company delivers flexible, modular power solutions to the UK grid and AI datacentres worldwide, enabling scalable, reliable energy for next-generation digital infrastructure. The Company has deep expertise in infrastructure planning, grid access, gas access, and efficient power supply. Its new AI power supply strategy is intended to position Quantum as a leading AI infrastructure platform on the London Stock Exchange.

 

ENDS

 

This announcement contains inside information for the purposes of the UK version of the Market Abuse Regulation (EU No. 596/2014) as it forms part of United Kingdom domestic law by virtue of the European Union (Withdrawal) Act 2018 ('UK MAR'). Upon the publication of this announcement, this inside information is now considered to be in the public domain.

 

Pieter Krügel

contact@quantumdata.energy

Quantum Data Energy PLC

CEO

Guy Wheatley, CFA

+44 (0)203 4117773

Fortified Securities

Corporate Broker

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
FUREAKAPFLPKEFA
Date   Source Headline
19th Feb 20267:00 amRNSThird FlexGen Funding & 7 MW Site Update
9th Feb 20267:00 amRNSBusiness Growth Update and Capital Funding
3rd Feb 20267:00 amRNSNew Record High Generation and Revenues
30th Jan 20267:11 amRNS-RQ1 2026 Business Update & CEO Interview
13th Jan 20267:00 amRNSHindlip Makes Significant Construction Progress
6th Jan 20267:00 amRNSRecord Generation and Revenues For 2025
18th Dec 202510:00 amRNS-RQDE CEO Interview & Publication of Business Video
16th Dec 20257:00 amRNS2025 A Remarkable Year in Review
9th Dec 20257:00 amRNSElectricity Generation and Revenues Surge
2nd Dec 20257:00 amRNSSignificant Progress with Funding at Project Level
25th Nov 20257:00 amRNS10 MW CHP Project Significant Progress
18th Nov 20257:00 amRNSRecord High Electricity Sales
11th Nov 20257:00 amRNS1GW AI Datacentre Power Strategy Update
6th Nov 20257:00 amRNSHindlip breaks ground and update on 7 MW purchase
4th Nov 20254:30 pmRNSHolding(s) in Company
3rd Nov 20253:00 pmRNSChange of Name
22nd Oct 20254:30 pmRNSHolding(s) in Company
21st Oct 20257:00 amRNS25 MW Portfolio Makes Signif. Development Progress
20th Oct 20254:30 pmRNSHolding(s) in Company
14th Oct 20257:00 amRNSPyebridge FlexGen Power Asset Revenues Surge
7th Oct 20253:30 pmRNSHindlip Project Significant Construction Progress
30th Sep 20257:00 amRNSAI Datacentre Power Supply JVA Completed
23rd Sep 20257:00 amRNSPyebridge Income Boost -15-yr. Cap. Mkt. Contract
17th Sep 20253:30 pmRNSAI Investment Surge Validates MAST’s AI Vision
16th Sep 20257:00 amRNSAI Datacentre Power Supply Strategy Target of 1 GW
9th Sep 20252:01 pmRNS-RWarning Regarding Unsolicited Articles
9th Sep 20257:00 amRNSHoliday Parks Power Supply Exclusive Joint Venture
4th Sep 20257:00 amRNSAcquisition of 7 MW Constructed FlexGen Site
1st Sep 20253:30 pmRNSExercise of Warrants, Issue of Equity & TVR
28th Aug 20257:00 amRNSHalf-year Report
26th Aug 202512:30 pmRNSExercise of Warrants, Issue of Equity & TVR
20th Aug 20257:00 amRNSHindlip Construction Progress Update
6th Aug 20257:00 amRNSAI Datacentre Power Supply JV
31st Jul 20257:00 amRNSRevenues Update
25th Jul 20257:00 amRNSBroker Warrant Exercise
22nd Jul 20257:00 amRNSAcquisition of 25 MW of New Sites
15th Jul 20254:30 pmRNSPDMR Dealing Notifications
11th Jul 20252:30 pmRNSCompletion of Equity Fundraise
9th Jul 202511:45 amRNSApproval & Publication of Prospectus
8th Jul 202512:19 pmRNSNotice of General Meeting Results
26th Jun 202512:19 pmRNSResult of AGM
16th Jun 202512:00 pmRNSNotice of GM
4th Jun 20257:00 amRNSNotice of AGM
27th May 20254:30 pmRNSHolding(s) in Company Update (TR-1)
23rd May 20253:59 pmRNSLoan, Proposed Equity Fundraise, and Share Consol.
20th May 20254:30 pmRNSHolding(s) in Company
6th May 20257:00 amRNSDefinitive Invest. Agmt. Complete & Revenue Update
30th Apr 20257:00 amRNSAnnual Financial Report
17th Apr 20254:00 pmRNSHolding(s) in Company
20th Mar 20257:00 amRNS£5m Definitive Investment Agreement Signed

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.