Otakikpo Operational Update

29 Jul 2015 07:01

RNS Number : 3706U
Lekoil Limited
29 July 2015
 

 

29 July 2015

 

Lekoil Limited

("Lekoil" or the "Company")

 

Otakikpo Operational Update

Project on schedule for first oil by end of Q3 2015

 

Lekoil (AIM: LEK), the oil and gas exploration and development company with a focus on Nigeria and West Africa more generally, announces the following update regarding operational activity at the Otakikpo Marginal Field ("Otakikpo").

 

Re-entry activities on Otakikpo-002 commenced with the successful drilling-out of the cement plugs in the 9⅝'' casing. While attempting to drill-out the cement plugs in the 7'' liner, the rig crew noticed a potential critical safety issue around the crown block of the rig which has forced temporary suspension of re-entry activities, for safety reasons, pending repairs and replacement of equipment. No injuries were incurred due to the proactive actions of the trained rig crew. Safety remains the highest priority to Lekoil and its partner Green Energy International Limited (GEIL). Replacement parts may be sourced from outside the country and costs relating to the replacement of the rig equipment will be carried entirely by the drilling company, not Lekoil.

 

As a consequence of this interruption, first oil is now expected to flow from the Otakikpo-002 to the Early Production Facility ("EPF") by the end of Q3 2015.

 

Lekoil has made significant progress to date at Otakikpo:

 

· All necessary approvals for the well re-entry plan were secured during 2014;

 

· The contracts for the Phase-1 Field Development Plan, which included a rig, well services and an EPF, were tendered and awarded during the first half of 2015;

 

· The Company had to overcome a series of significant logistical challenges related to road remediation and the building of a temporary bridge in order to bring the equipment to site. As a result of the work the surrounding local community have gained a significant socio-economic advantage.

 

· Prior to rig mobilisation large tracts of swamp land were reclaimed by sand-filling and land consolidation.

 

· Mobilisation of the rig equipment was completed and the rig mast was erected in preparation for well completion and production operations.

 

 

Lekan Akinyanmi, Lekoil's CEO, said, "Phase 1 operation from Otakikpo is underway and we look forward to announcing first oil by end of Q3 2015. Safety remains our key priority and we will continue applying the highest standard to our operations. The Company would like to thank Shareholders for their continued support."

 

 

Background to Otakikpo

Otakikpo is sited in a coastal swamp location in oil mining lease (OML) 11, adjacent to the shoreline in the south-eastern part of the Niger Delta. Lekoil exercises the rights and benefits of its 40 per cent. economic interest in Otakikpo via the Farm-in Agreement and Joint Operating Agreement signed on 17 May 2014 with Green Energy International Limited. Ministerial consent was granted by the Honourable Minister of Petroleum Resources of Nigeria in June 2015.

 

The Field Development Plan consists of two phases: Phase 1 comprises the recompletions of two wells, Otakikpo-002 and Otakikpo-003 with the installation of an Early Production Facility of 6,000 bbls/d capacity and export via shuttle tanker. Phase 2 covers the subsequent incremental development of the rest of the field with a new Central Processing Facility and seven new wells coming on stream during 2017.

 

 

For further information, please visit www.lekoil.com or contact:

 

Lekoil Limited

Hamilton Esi, Corporate Communications

 

+44 20 7920 3150

 

Strand Hanson Limited (Financial & Nominated Adviser)

James Harris / James Spinney / Ritchie Balmer

 

+44 20 7409 3494

 

Mirabaud Securities LLP (Joint Broker)

+44 20 7878 3362

Peter Krens / Edward Haig-Thomas

+44 20 7878 3447

BMO Capital Markets (Joint Broker)

+44 20 7236 1010

Rupert Newall / Neil Haycock / Thomas Rider

Ladenburg Thalmann & Co. Inc. (US Placing Agent)

Jim Hansen / Barry Steiner

+1 713 353 8914

+1 305 572 4200

Tavistock Communications (Financial PR)

Simon Hudson / Ed Portman

+44 20 7920 3150

 

-ends-

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUWUARVSABUUR
Date   Source Headline
5th Jun 20141:12 pmRNSHolding(s) in Company
2nd Jun 20141:01 pmRNSHolding(s) in Company
2nd Jun 20141:00 pmRNSHolding(s) in Company
28th May 20141:18 pmRNSNotice of AGM
27th May 20148:00 amRNSTVR and Directors' Holdings
21st May 20147:00 amRNSCompletion of Placing
20th May 20147:01 amRNSPlacing to fund acquisition of interest
20th May 20147:00 amRNSFinal Results
16th May 201411:30 amRNSHolding(s) in Company
12th May 201412:55 pmRNSHolding(s) in Company
9th Apr 20144:27 pmRNSHolding(s) in Company
27th Mar 20147:00 amRNSOPL 310 Operations Update
19th Mar 20149:15 amRNSHolding(s) in Company
17th Dec 20135:15 pmRNSHolding(s) in Company
17th Dec 201311:00 amRNSHolding(s) in Company
16th Dec 20136:00 pmRNSHolding(s) in Company
27th Nov 20139:30 amRNSHolding(s) in Company
26th Nov 201310:00 amRNSHolding(s) in Company
22nd Nov 20138:00 amRNSTotal Voting Rights & Directors' Holdings Update
21st Nov 20133:50 pmRNSHolding(s) in Company
21st Nov 201311:31 amRNSResult of EGM
19th Nov 20137:03 amRNSAppointment of Adviser
19th Nov 20137:02 amRNSUpdate on OML113
19th Nov 20137:01 amRNSOPL310 Drilling and Resources Update
8th Nov 201311:58 amRNSHolding(s) in Company
7th Nov 20137:00 amRNSProposed Acquisition of Interest in OML113
5th Nov 20137:00 amRNSPosting of Circular & Notice of EGM
1st Nov 20137:41 amRNSUS$100M Placing Completed
31st Oct 20134:54 pmRNSIntention to raise approximately US$100 million
31st Oct 20137:02 amRNSOPL310 Drilling Update
30th Sep 20137:01 amRNSHalf Yearly Report
30th Sep 20137:00 amRNSOgo-1 Sidetrack Drilling Update
18th Sep 20132:00 pmRNSDisclosure of Holdings
16th Sep 20131:03 pmRNSReplacement: Update on OML113
16th Sep 20138:03 amRNSUpdate on OML113
10th Sep 20134:30 pmRNSHolding(s) in Company
4th Sep 20137:00 amRNSHolding(s) in Company
4th Sep 20137:00 amRNSHolding(s) in Company
3rd Sep 20134:45 pmRNSHolding(s) in Company
3rd Sep 20134:40 pmRNSHolding(s) in Company
29th Aug 20131:30 pmRNSDrilling Update
7th Aug 201312:15 pmRNSResult of EGM
19th Jul 20134:30 pmRNSPosting of Circular and Notice of EGM
17th Jul 20137:39 amRNSIssue of Equity
26th Jun 20137:00 amRNSSignificant oil discovery offshore Nigeria
18th Jun 20137:10 amRNSProposed Acquisition of Interest in OML113 - Amend
18th Jun 20137:00 amRNSProposed Acquisition of Interest in OML113
17th May 20137:00 amRNSPlacing and Admission to AIM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.