Islandmagee Project Update

3 Jul 2019 07:00

RNS Number : 2792E
Infrastrata PLC
03 July 2019
 

 

 

3 July 2019

 

InfraStrata plc

("InfraStrata" or the "Company")

 

Islandmagee Project Update

 

InfraStrata plc (AIM: INFA), the UK quoted company focused on the development of natural gas storage capacity, is pleased to provide an update on recent progress with the Company's Islandmagee Gas Storage Project (the "Project").

 

Project Funding Partners & Final Investment Decision (FID)

 

The Company achieved a transformational milestone for the Project on 11 June 2019 when it entered into a Binding Term Sheet with Vitol SA for the proposed offtake of the entire storage capacity of the Project for 12 years. The Company announced that it had agreed a term sheet with Vitol SA that, once converted into a full gas storage agreement in due course, will underpin cumulative Project revenues for the first 12 years of operation of the gas storage facility, expected to be approximately £600 million to £780 million before costs at full operating capacity. Over the 40 year lifetime of the facility operations, cumulative revenues are expected to be between £2 billion and £2.60 billion before costs at full operating capacity. The directors of InfraStrata believe that not only does this outline agreement validate the need for gas storage for the whole of the UK, but in due course will also provide an invaluable contribution to the local Northern Ireland economy in terms of direct and indirect employment. The Company has now proceeded to the next stage of this process to draft and agree the Gas Storage Agreement (GSA) with Vitol SA, based on the binding pricing and capacity terms agreed in the Term Sheet, and that will cover the entire capacity of the Project, being 500 million cubic metres across all seven caverns once constructed and fully operational.

 

The signing of the Term Sheet has enabled InfraStrata to continue to progress detailed discussions with potential equity and debt partners in the UK and Europe for the funding of the construction of the Project and pre-construction works, and this is a key priority for the Board. Discussions include proposals for a convertible debt facility that can be converted to equity at the Project level. Since the announcement of the Term Sheet, the Company has been able to provide the potential funding partners with additional financial modelling, that includes revenue sensitivities, construction costs and the contracting methodology, all of which demonstrate the Project's technical and economic viability.

 

After receiving and fully analysing all Project construction offers, InfraStrata has now refined its main construction strategy. The main focus is to de-risk the Project, as much as possible, during construction and to better integrate the various construction services as well as centralise the common requirements of the selected contractors. This is expected to lead to increased cost savings, operational efficiencies and ultimately reduce the impact on the local area within Islandmagee.

 

The Company remains committed to obtaining a FID to fund the construction of the Project by the end of 2019, which can then lead to first injection of gas in 2022 and full commercial gas storage operations in 2023. This is subject to agreement with the Company's chosen funding partner. Further details will be announced as soon as possible.

 

Marine Licence

 

The Company continues to make significant progress on the marine licence and confirms that it has submitted all the reports that were last formally requested by the Department for Agriculture, Environment and Rural Affairs in Northern Ireland (DAERA) as follows:

 

· Shadow Habitats Assessment

· Updated Brine Model

· Independent Verification of Brine Model

· Environmental Monitoring Plan

InfraStrata expects feedback on these reports from DAERA in due course, which is a normal step in the process of being granted a full marine licence. Further, as an EU Project of Common Interest (PCI), the Project is entitled to receive expedited processing timeframes in relation to licencing and permitting. InfraStrata is working closely with DAERA so that the full and proper process required for the issuance of a full marine licence can be completed as soon as possible.

 

As the Project moves towards the construction phase, the Company has awarded minor contracts to update environmental baseline surveys that will be required prior to the construction process commencing. This piece of work will be completed in due course and kept ready before construction activities commence. As the Company has previously stated, it sees no reason why the full marine licence will not be issued once due process has been adhered to and been completed.

 

EU Grants

 

The final EU application to receive the remaining grant monies of EUR1.6m for the FEED work that was completed last year continues to be progressed and the funds are now expected to be received from the EU later this year after all final audits have been completed. This is currently an ongoing process and InfraStrata expects to receive this already-approved grant (which was subject to completion of the FEED to the satisfaction of the EU and according to set milestones that the Company believes it has met) once all the external audit formalities have been duly completed. The Company is confident of receiving the monies in due course but is subject to the due process and timetable of the EU.

 

As announced on the 14 June 2019, an application was made to the EU for a sum of EUR9,299,446.00 to enable the FEED study in order to facilitate the reverse flow of the Scottish Northern Ireland Pipeline (SNIP). The Company expects to hear of the outcome of this application by the end of 2019. A reversal of the SNIP will enable the full capacity of the Project to be utilised once all proposed seven caverns are constructed and ready for operation, expected by 2024/5. Additionally, the Company is considering other strategies including virtual trading of gas between Northern Ireland and mainland Britain in order to fully maximise the storage capacity made available by 2024/25. This will not only increase trading optionality but will also help in balancing of the two networks during peak demand days.

 

 

John Wood, Chief Executive Officer, commented: "We are now at a very exciting stage of the Islandmagee Gas Storage Project. Having underpinned our future revenues with an innovative offtake structure, we have been able to fully model the future income streams for the next 12 years. This has assisted in our negotiations with potential project funding partners. As we did with the Term Sheet with Vitol, we will take the required time to negotiate the best long term deal we can so as to ensure our long term interests and those of our shareholders are protected."

 

 

For further information, please contact:

 

InfraStrata plc

John Wood, Chief Executive

 

c/o Yellow Jersey

+44 (0)20 3735 8825

Allenby Capital Limited (AIM Nominated Adviser & Joint Broker)

Jeremy Porter / Liz Kirchner 

+44 (0)20 3328 5656

Yellow Jersey

Tim Thompson  

+44 (0)20 3735 8825

 

 

-ENDS-

 

Notes to editors:

 

InfraStrata is an independent gas storage company focused on the UK and Ireland. Further information is available on the Company's website: www.infrastrataplc.com 

 

Background on the Islandmagee Storage Project

 

The Islandmagee gas storage project is a proposed salt cavern gas storage facility located on Islandmagee in County Antrim, Northern Ireland. The Board of InfraStrata believes that the proposed 500 million cubic metres natural gas cavern storage facility will provide over 25% of the UK's natural gas storage once constructed. The facility will be situated adjacent to the Scotland Northern Ireland (gas) Pipeline (SNIP) and the Moyle 500 megawatt electricity interconnector. Work commenced in 2007 with the acquisition of 3D seismic data to image the Permian salt in the Larne Lough area. During 2012, planning permission was granted for the project and a gas storage licence was issued by the Utility Regulator. In 2015 a well was drilled to core the salt and confirm the technical feasibility of the project, supported in part by the European Commission. The Front End Engineering and Design (FEED) element of the project was completed in November 2018 and the FEED report was submitted to the European Union in December 2018 in accordance with the Company's grant conditions. To date approximately £14.5m has been invested in the project.

 

Further information is available on the company's website: www.infrastrataplc.com 

 

 

 

The Front End Engineering & Design (FEED) and Insitu Downhole Testing programme for the Islandmagee gas storage project is co-financed by the European Union's Connecting Europe Facility.

 

Disclaimer releasing the European Union from any liability in terms of the content of the dissemination materials:

 

"The sole responsibility of this publication lies with the author. The European Union is not responsible for any use that may be made of the information contained therein."

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDSSEEEEFUSELW
Date   Source Headline
30th Jun 201611:50 amRNSIslandmagee signs new EU Grant Agreement
16th Jun 20163:45 pmRNSWoodburn Forest-1 well - completion of drilling
25th May 20162:45 pmRNSIslandmagee-receipt of final EUR1.75m grant monies
16th May 20167:00 amRNSWoodburn Forest-1 well - commencement of drilling
13th May 20161:00 pmRNSRe Press Comment on Woodburn Forest
22nd Mar 20167:00 amRNSHalf Yearly Report
16th Mar 20167:00 amRNSNotice of Interim Results
11th Mar 20167:00 amRNSWoodburn Forest-1 well-site construction commenced
2nd Mar 20167:01 amRNSAdvisers' appointment for Islandmagee monetisation
2nd Mar 20167:00 amRNSChange of Broker
1st Feb 201612:43 pmRNSData sharing agreement signed
29th Jan 20165:00 pmRNSTotal Voting Rights
29th Jan 201610:11 amRNSHolding(s) in Company
28th Jan 20163:56 pmRNSHolding(s) in Company
27th Jan 20169:19 amRNSHolding(s) in Company
26th Jan 201612:45 pmRNSResult of AGM, Placing update, total voting rights
22nd Jan 20163:05 pmRNSIslandmagee receives further EU Grant Funding
19th Jan 20167:00 amRNSUpdate on Woodburn Forest-1 well and its funding
31st Dec 201512:33 pmRNSTotal Voting Rights
23rd Dec 20154:40 pmRNSSecond Price Monitoring Extn
23rd Dec 20154:35 pmRNSPrice Monitoring Extension
18th Dec 20157:37 amRNSProposed placing to raise up to £450,000
17th Dec 201511:12 amRNSPosting of annual report
8th Dec 20157:00 amRNSFinal Results
30th Nov 20157:00 amRNSNotice of Final Results
27th Nov 20157:00 amRNSUpdate on Islandmagee gas storage project
16th Nov 20157:00 amRNSDivestment of Exploration Assets
10th Nov 20154:13 pmRNSDirectorate Change
4th Sep 20157:00 amRNSUpdate on the post Islandmagee-1 well
27th Aug 20158:00 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
25th Aug 20157:00 amRNSNorthern Ireland Exploration Update
18th Jun 20157:30 amRNSResults of Islandmagee-1 Well
18th Jun 20157:05 amRNSResults of Islandmagee-1 well
18th Jun 20157:00 amRNSLicence P1918 Update
17th Jun 20157:00 amRNSAppointment of Nominated Adviser and Joint Broker
15th Jun 20158:00 amRNSNotification of Major Interest in Shares
22nd May 20158:00 amRNSNOTIFICATION OF MAJOR INTEREST IN SHARES
18th May 20157:00 amRNSCommencement of drilling: Islandmagee-1
1st May 20157:00 amRNSConvertible Loan Facility with Baron Oil Plc
28th Apr 20157:00 amRNSInterim Results
24th Apr 20153:27 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
2nd Apr 20157:00 amRNSNotification of Interim Results
5th Mar 20152:43 pmRNSNOTIFICATION OF MAJOR INTEREST IN SHARES
3rd Mar 20155:21 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
27th Feb 20154:36 pmRNSTotal Voting Rights
25th Feb 20153:06 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
23rd Feb 201511:46 amRNSResult of GM and Completion of Placing
5th Feb 20157:00 amRNSPlacing to raise £2.1million
30th Jan 20157:00 amRNSData release agreement signed
21st Jan 201512:46 pmRNSBoard Changes

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.