Charles Jillings, CEO of Utilico, energized by strong economic momentum across Latin America. Watch the video here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksHorizonte Minerals Regulatory News (HZM)

Share Price Information for Horizonte Minerals (HZM)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 0.425
Bid: 0.40
Ask: 0.45
Change: -0.025 (-5.26%)
Spread: 0.05 (12.50%)
Open: 0.475
High: 0.45
Low: 0.45
Prev. Close: 0.475
HZM Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Araguaia Line2 Feasibility Study Contracts Awarded

6 Mar 2023 07:00

RNS Number : 9241R
Horizonte Minerals PLC
06 March 2023
 

NEWS RELEASE

6 March 2023

 

LINE 2 FEASIBILITY STUDY CONTRACTS AWARDED TO DOUBLE PRODUCTION AT ARAGUAIA

 

 

HIGHLIGHTS:

 

· Awarded Araguaia Line 2 Feasibility Study, aiming to double nickel production to 29,000 tpa;

· Anticipated low capital intensity through leveraging the shared infrastructure and services from Line 1;

· AACEI Class 3 standard cost estimate;

· Line 2 process plant sits within the existing industrial area;

· Trade off to allow a percentage of production to be converted to nickel matte; and

· Targeting 2H 2023 publication of Line 2 Feasibility Study.

 

 

Horizonte Minerals Plc (AIM/TSX: HZM) ("Horizonte" or the "Company") a nickel company developing two Tier 1 assets in Brazil, reports that it has awarded contracts for the Line 2 Feasibility Study ("FS") at its Araguaia Nickel Project ("Araguaia" or "the Project"). The second line at Araguaia is expected to increase production by 100% to 29,000 tonnes of nickel per year through the construction of a duplicate RKEF processing facility ("Line 2").

 

The aim of the FS is to produce a NI 43-101 Feasibility Report supported by a AACEI Class 3-quality cost estimate, and project execution plan. The Company is targeting publication of the results of the study in 2H 2023. The principal contractors for this work are:

 

·  Snowden - geology, mine design, mine planning and NI 43-101 reporting;

·  Environment Resources Management (ERM)- environmental permitting outline planning;

·  Reta Engineering - cost estimation, execution scheduling and planning services;

·  Draft Solutions - lead engineer, basic engineering design and documentation; and

·  Afry Poyry - Process engineering support.

 

These groups are all key contributors to the engineering, costing and construction work currently underway on Line 1 at Araguaia and have extensive knowledge and understanding of the Project.

 

The Line 2 FS is expected to demonstrate a mine life of over 25 years with a production capacity of approximately 29,000 tonnes of nickel per year at Araguaia. Line 2 will deliver greater production flexibility, lower capital intensity and increased operating margins. As part of the FS, an option will be designed into the flow sheet to allow a portion of the furnace product from Line 2 to be converted to nickel matte allowing Araguaia not only to produce high-grade low impurity ferronickel but also matte that can be upgraded to feed directly into the electric vehicle battery chemistry supply chain.

 

The Araguaia Plant has been designed and optimised to allow for the build out of Line 2 with key fixed infrastructure sized to support both lines, reducing the overall cost of developing Line 2.

 

 

 

Jeremy Martin, CEO of Horizonte, commented:

 

"The award of the Line 2 FS is an important step in achieving our goal of Araguaia becoming a scalable, low-cost nickel operation. Line 1 and Line 2 together are designed to produce 29,000 tpa of nickel with the overall resource of 119 million tonnes able to support this scenario with the potential to increase the mine life in the future. We are also excited about the potential of having the option to produce nickel matte giving us the ability to participate in different parts of the nickel market.

 

"We are making solid progress on the construction of Araguaia Line 1, which remains on-budget and on-schedule to produce first nickel in 1Q 2024, whilst simultaneously preparing for our next growth phase with Vermelho's Feasibility Study expected to be finalised in 2024."

 

 

 

For further information, visit www.horizonteminerals.com or contact:

 

Horizonte Minerals plc

Jeremy Martin (CEO)

Simon Retter (CFO)

Patrick Chambers (Head of IR)

 

info@horizonteminerals.com

+44 (0) 203 356 2901

Peel Hunt LLP (Nominated Adviser & Joint Broker)

Ross Allister

David McKeown

 

+44 (0)20 7418 8900

 

BMO (Joint Broker)

Thomas Rider

Pascal Lussier Duquette

Andrew Cameron

 

+44 (0) 20 7236 1010

 

Tavistock (Financial PR)

Emily Moss

Cath Drummond

 

+44 (0) 20 7920 3150

 

 

ABOUT HORIZONTE MINERALS

Horizonte Minerals plc (AIM & TSX: HZM) is developing two 100%-owned, Tier 1 projects in Pará state, Brazil, the Araguaia Nickel Project and the Vermelho Nickel-Cobalt Project. Both projects are large scale, high-grade, low-cost, low-carbon and scalable. Araguaia is under construction with first metal scheduled for early 2024, when fully ramped up with Line 1 and Line 2, is forecast to produce 29,000 tonnes of nickel per year. Vermelho is at feasibility study stage and is expected to produce 25,000 tonnes of nickel and 1,250 tonnes of cobalt to supply the EV battery market. Horizonte's combined near-term production profile of over 60,000 tonnes of nickel per year positions the Company as a globally significant nickel producer. Horizonte's top three shareholders are La Mancha Investments S.à r.l., Glencore plc and Orion Resource Partners LLP.

 

 

 

CAUTIONARY STATEMENT REGARDING FORWARD-LOOKING INFORMATION

Except for statements of historical fact relating to the Company, certain information contained in this press release may constitute "forward-looking information" under Canadian securities legislation. Generally, forward-looking information can be identified by the use of forward-looking terminology such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". Forward-looking information is based on the reasonable assumptions, estimates, analysis and opinions of management made in light of its experience and its perception of trends, current conditions and expected developments, as well as other factors that management believes to be relevant and reasonable in the circumstances at the date that such statements are made, and are inherently subject to known and unknown risks, uncertainties and other factors that may cause the actual results, level of activity, performance or achievements of the Company to be materially different from those expressed or implied by such forward-looking information, including but not limited to risks related to: the ability of the Company to complete the acquisition of required equipment, on time or at all, the costs and timing for delivery of the necessary equipment to be purchased, the estimation of mineral resources and reserves and the ability of the Company to achieve its goals in respect of growing its mineral resources; the realization of mineral resource and reserve estimates and achieving production in accordance with the Company's potential production profile or at all, the success of exploration and mining activities; cost and timing of future exploration, production and development, the ability of the Company to expand production lines on the timeline contemplated or at all, exploration and mining risks, competition from competitors with greater capital; the Company's lack of experience with respect to development-stage mining operations; fluctuations in metal prices; uninsured risks; environmental and other regulatory requirements; exploration, mining and other licences; the Company's future payment obligations; potential disputes with respect to the Company's title to, and the area of, its mining concessions; the Company's dependence on its ability to obtain sufficient financing in the future; the Company's dependence on its relationships with third parties; the potential of currency fluctuations and political or economic instability in countries in which the Company operates; currency exchange fluctuations; the Company's ability to manage its growth effectively; the trading market for the ordinary shares of the Company; uncertainty with respect to the Company's plans to continue to develop its operations and new projects; the Company's dependence on key personnel; possible conflicts of interest of directors and officers of the Company, and various risks associated with the legal and regulatory framework within which the Company operates, together with the risks identified and disclosed in the Company's disclosure record available on the Company's profile on SEDAR at www.sedar.com, including without limitation, the annual information form of the Company for the year ended December 31, 2021, the Araguaia Report and the Vermelho Report. Although management of the Company has attempted to identify important factors that could cause actual results to differ materially from those contained in forward-looking information, there may be other factors that cause results not to be as anticipated, estimated or intended. There can be no assurance that such statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
CNTUPUAGWUPWGQA
Date   Source Headline
15th Apr 20247:00 amRNSCorporate Update
2nd Apr 20247:00 amRNSCorporate Update
28th Mar 20241:39 pmRNSCorporate Update
14th Mar 20244:40 pmRNSAraguaia Project Update
1st Mar 20247:00 amRNSCorporate Update
23rd Feb 202410:52 amRNSHolding(s) in Company
19th Feb 20244:53 pmRNSUpdated Capex and Schedule Estimate
18th Jan 20244:57 pmRNSAPPOINTMENT OF NICHOLAS MICHAEL TO THE BOARD
10th Jan 20245:35 pmRNSTR-1: Standard notification of major holdings
27th Dec 20237:00 amRNSINTERIM US$20M FUNDING PACKAGE SIGNED
19th Dec 20232:32 pmRNSARAGUAIA PROJECT UPDATE
18th Dec 20235:55 pmRNSAPPOINTMENT OF BOARD MEMBERS
27th Nov 20237:00 amRNSBOARD AND MANAGEMENT CHANGES
14th Nov 20238:02 amRNSARAGUAIA PROJECT UPDATE
23rd Oct 20237:00 amRNSQ3 2023 Construction Update
12th Oct 20237:00 amRNSHolding(s) in Company
5th Oct 20237:00 amRNSHolding(s) in Company
2nd Oct 20237:00 amRNSUpdate on Araguaia Nickel Project Construction
14th Sep 20231:00 pmRNSEXERCISE OF OPTIONS AND TOTAL VOTING RIGHTS
12th Sep 20237:00 amRNSPASSING OF FORMER CHAIR AND CO-FOUNDER
24th Aug 20237:00 amRNSOperations Director Appointed for Araguaia Project
17th Aug 20237:00 amRNSInterim Financial Results
3rd Aug 20237:00 amRNSQ2 2023 Araguaia Construction Update
2nd Aug 20237:00 amRNSNotice of Investor Presentation
27th Jul 20233:00 pmRNSExercise of Options and Total Voting Rights
25th Jul 20237:00 amRNSAPPOINTMENT OF JOINT CORPORATE BROKER
13th Jul 20237:00 amRNSAward of Options
11th Jul 20237:00 amRNSBoard Appointments
7th Jul 202311:03 amRNSHolding(s) in Company
6th Jul 20237:00 amRNSMINING APPROVAL RECEIVED FOR ARAGUAIA
29th Jun 20237:00 amRNSDELIVERY OF ROTARY KILN
15th Jun 20237:00 amRNSAraguaia Nickel Project Pictorial Update
24th May 20234:37 pmRNSResult of AGM
24th May 20237:00 amRNSHORIZONTE MINERALS PLC 2022 SUSTAINABILITY REPORT
23rd May 20234:05 pmRNSTR-1: Notification of Major Holdings
23rd May 20234:01 pmRNSTR-1: Notification of Major Holdings
28th Apr 20237:00 amRNSNotice of AGM
24th Apr 20237:00 amRNSAraguaia Construction Update
19th Apr 20237:00 amRNSNotice of Investor Presentation
31st Mar 20234:07 pmRNSExercise of Options and Total Voting Rights
29th Mar 20237:00 amRNSFINAL RESULTS FOR THE YEAR ENDED 31 DECEMBER 2022
6th Mar 20237:00 amRNSAraguaia Line2 Feasibility Study Contracts Awarded
27th Feb 20237:00 amRNSSecond drawdown complete
24th Feb 20239:04 amRNSTR-1: Notification of Major Holdings
16th Feb 20237:00 amRNSHORIZONTE MINERALS PICTORIAL UPDATE
9th Feb 20237:00 amRNSMining Services Contract Awarded for Araguaia
8th Feb 20234:31 pmRNSTR-1: Notification of Major Holdings
24th Jan 20237:00 amRNSVermelho Nickel Cobalt Project EIA Submitted
21st Dec 20227:00 amRNSDirector/PDMR Shareholding
15th Dec 20227:00 amRNSAraguaia remains on Schedule and on Budget

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.