Jolly Ranch Q1 2011 Production & Operations Update

18 May 2011 07:00

RNS Number : 7891G
Nighthawk Energy plc
18 May 2011
 



 

NIGHTHAWK ENERGY PLC

("Nighthawk" or "the Company")

Jolly Ranch Q1 2011 Production and Operations Update

Nighthawk, the US focused oil development and production company (AIM: HAWK and OTCQX: NHEGY) gives its second quarterly production update covering the quarter ended 31 March 2011 and provides an update on the ongoing recompletion and completion activity.

Highlights

·; Number of wells now on test production following the completions/recompletions undertaken since January increased by 5 to 12

·; Production anticipated to be higher in Q2 2011

·; Focus remains on finishing the current series of completions and recompletions in line with the previously announced programme

Update on Production

In the Q4 2010 production update we stated that Q1 production was expected to be broadly in line with the Q4 figures. However, Q1 2011 production totalled 2,062 barrels of oil net to Nighthawk, a reduction on Q4 due to well decline and worse than average winter weather which curtailed production operations.

The production figures below are presented net of applicable Colorado State Taxes and Royalty payments to the landowners. The figures for the quarter ended 31 December 2010 are presented for comparison.

Q4 2010

Q1 2011

October

1,021

January

624

November

1,076

February

751

December

989

March

687

Total

3,086

Total

2,062

 

These figures should not be used to calculate a bopd figure as the wells, which are predominantly on test, are intermittently taken offline for routine maintenance, modifications to pumping equipment, weather related conditions, workovers, recompletions or completion in new zones. As the number of wells increases, the effect of individual wells being taken offline will have less effect on the overall production figures.

As reported on 8 March, the Craig 16-32 was on pump and, after maintenance, had come back on at a rate of around 85 bopd. The production from this well continues to vary considerably on a day-to-day basis and is currently averaging approximately 30 bopd, with up to 60 bopd on certain days.

Production in Q2 is currently anticipated to be higher as a number of wells come on stream following the completion and recompletion exercises.

Drilling Programme

As announced on 8 March, it was expected that the drilling of four development wells in the core area around the Craig Ranch field, all focusing on the Pennsylvanian Atoka and Cherokee shales, and up to a further three wells in the Middle Mist area, to test the 'J' sands and the Cretaceous-aged Niobrara shale formation, were to be drilled in Q2. Due to tight rig availability, in particular extension options being taken up by other operators in the area, the commencement of this programme has been delayed.

The Company will update the market when the programme is expected to commence. In the interim, the programme of recompletion and completion will continue.

Update on Completion Operations

The previously announced completion and recompletion work continues with the ongoing initial six well programme. This programme has now been expanded and a number of other wells are now connected to the water disposal wells and further well sites are being electrified, enabling more efficient pumping and water disposal.

Jolly Ranch 2-1

The 2-1 has been added to the current programme and has been completed in the Cherokee A. Early swab testing of this zone resulted in 50% oil cut from 40 barrels of fluid recovered in a 12-hour interval. The well has been placed on pump to increase the fluid recovery rates.

 

Jolly Ranch 16-1

Electric and water disposal lines have been commissioned at the 16-1, which has been recompleted and production is being comingled from Cherokee and Atoka formations.

 

Craig 8-1

As announced on 8 March, the well had been placed on pump and was producing in a range between 10-30 bopd gross. The well experienced mechanical problems in early April but has subsequently been placed back on pump and is currently producing 15-35 bopd.

Williams 10-27

The Williams 10-27 was recently completed in the Atoka. The well has been placed on pump and is currently seeing an increased oil cut around 5% as the well continues to flow back fraccing fluid. The overall fluid level produced is decreasing, but the oil cut is expected to improve.

Further activities intended to enhance production from the following wells are now planned and being undertaken.

Well

Completion Activity

John Craig 7-2

Upper Atoka - multiple new perforations and acidisations

Cherokee C - reperforation and acidisation

Cherokee A - new perforation and acidisation

Fort Scott - multiple new perforations and acidisations

Jolly Ranch 4-13

Atoka - multiple recompletions

Craig 12-33

Lower Atoka - acidise existing perforations

Cherokee A - new perforation and acidisation

Craig 15-34

Cherokee A - new perforation and acidisation

Craig 10-28

Upper Atoka - multiple new perforations and acidisations

Fort Scott - multiple new perforations and acidisations

 

Craig 7-34

Cherokee A - new perforation and acidisation

Potential Morrow - new perforations and acidisations

 

Jolly Ranch Well Status

The current status of the wells on Jolly Ranch is as follows

Well

Current Status

John Craig 7-2

In current completion programme

Craig 4-4

Test production

Craig 4-33

Test production

Craig 6-4

Test production

Craig 6-4 SWD

Salt water disposal

Craig 7-34

In current completion programme

Craig 8-1

Test production

Craig 10-28

Test production

Craig 12-28

Test production

Craig 12-33

In current completion programme

Craig 15-32H

Test production

Craig 15-34

In current completion programme

Craig 16-32

Test production

Jolly Ranch 2-1

Test production

Jolly Ranch 4-13

In current completion programme

Jolly Ranch 10-1 SWD

Salt water disposal

Jolly Ranch 10-5

Test production

Jolly Ranch 16-1

Test production

Williams 10-27

Test production

 

Tim Heeley B.Eng (Hons) a member of the Society of Petroleum Engineers, Fellow of the Geological Society of London and a Chartered Energy Engineer, who is CEO of Nighthawk and has over 15 years of experience in the hydrocarbons industry, has approved the technical information contained in this announcement.

Enquiries:

Nighthawk Energy plc

Tim Heeley, Chief Executive

Mike Thomsen, Executive Chairman

 

020 3405 1982

+1 720 344 5154

Westhouse Securities Limited

Tim Feather

Matthew Johnson

020 7601 6100

tim.feather@westhousesecurities.com

matthew.johnson@westhousesecurities.com

Matrix Corporate Capital LLP

James Pope

020 3206 7000

james.pope@matrixgroup.co.uk

Financial Dynamics

Ben Brewerton

Ed Westropp

020 7831 3113

ben.brewerton@fd.com

edward.westropp@fd.com

Notes to editors

Nighthawk is a focused oil and gas production and development business with assets onshore USA.

The Company holds a 50% working interest in a shale oil project in Colorado called the Jolly Ranch Group project ("Jolly Ranch"). Running Foxes Petroleum Inc. ("Running Foxes"), holds the remaining working interest and is the operator of the project; comprising the Jolly Ranch, Middle Mist and Mustang Creek areas, covering approximately 410,000 gross acres of Lincoln, Elbert and Washington Counties, Colorado.

Jolly Ranch lies within the southeast flank of the Denver-Julesburg Basin, a major mid-continent hydrocarbon producing basin. The source of the produced hydrocarbons is the black organic shales that are interbedded with siliclastic and carbonate rocks. The shales at Jolly Ranch are within the oil generation window and there is reasonable certainty of reservoir and source rock continuity throughout the project area.

To date, 19 wells of 7,500-8,000 feet have been drilled on a core 50,000 acre area by Nighthawk and Running Foxes, all of which have encountered multiple pay horizons.

The current work programme involves various testing and fraccing procedures on numerous shale target formations to determine the optimum production plan and also gain a greater understanding of this non-conventional play. In addition to testing, Nighthawk's main efforts have been focused on proving up the extent of the asset to help establish the wider project value.

In January 2011 Schlumberger Data & Consulting Services ("Schlumberger"), completed an independent reservoir simualtion model of the core Craig Ranch area. The model consisted of detailed areas of the Craig Ranch project area, totalling approximately 3,200 gross surface acres, and assessed the likely long-term production behaviour of the Marmaton, Cherokee and Atoka horizons. The simulation concluded that there were approximately 30,000 barrels of oil in place per acre in the Cherokee and Atoka shale horizons and the average model area recovery rate was 7.5% on 40-acre spacings with vertical wells. Schlumberger has previously stated that the regional continuity of the formations is such that the resources in place are likely to be laterally continuous across the total acreage.

Gaffney Cline and Associates reported on reserves in April 2011 and whislt stating that there was not enough of a production track record to fully develop a type curve which could be applied with good statistical confidence across the wider project area, the 2P reserves associated with the wells that have each cumulatively produced 20,000 bbls or more, for the best well to date on a Estimated Ultimate Recovery basis is 64,000 bbls gross on a 40 acre drainage basis.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCARMRTMBMBBJB
Date   Source Headline
19th Jul 20187:00 amRNSUpdate on Chapter 11 cases
29th Jun 20187:00 amRNSChapter 11 update and resignation of Nomad
26th Jun 20187:00 amRNSUpdate on Chapter 11 cases
11th Jun 20187:00 amRNSCancellation of GM and Chapter 11 Update
31st May 20183:06 pmRNSNotice of General Meeting
16th May 20187:00 amRNSChapter 11 update
14th May 20185:48 pmRNSUpdate on Chapter 11 proceedings
10th May 20187:00 amRNSRequisition of general meeting
4th May 20185:17 pmRNSDirectorate Change
1st May 20187:30 amRNSSuspension - Nighthawk Energy Plc
1st May 20187:00 amRNSNotice of Chapter 11 and Suspension
20th Apr 20187:00 amRNSUpdate on CBA Loan
11th Apr 20187:00 amRNSProduction update
23rd Mar 20187:00 amRNSProduction update
28th Feb 201810:22 amRNSSenior management appointment
20th Feb 20187:00 amRNSProduction Update
14th Feb 20187:00 amRNSSenior management change
25th Jan 20187:00 amRNSAppointment of US Investment Bank
12th Jan 20187:00 amRNSProduction Update
5th Jan 20185:19 pmRNSHolding(s) in Company
28th Dec 20177:00 amRNSAmendment to Existing Bank Agreement
28th Nov 20178:30 amRNSProduction update
22nd Nov 20177:00 amRNSResource Update
7th Nov 20177:00 amRNSDirectorate Change
1st Nov 20177:00 amRNSFarmout Option Agreement
25th Oct 20177:00 amRNSCompany Update
3rd Oct 20177:00 amRNSReserves Based Loan Covenant Compliance
26th Sep 20177:00 amRNSHalf-year Report
14th Sep 20177:00 amRNSCompany Update
30th Aug 20177:00 amRNSAmendment of Loan Notes
3rd Aug 20177:00 amRNSCompany Presentation and Operational Update
3rd Jul 20177:00 amRNSBanking Agreement
23rd Jun 201710:36 amRNSProduction Update and Result of AGM
31st May 20179:36 amRNSReserves Based Loan Covenant Compliance
26th May 20174:03 pmRNSFinal Results
2nd May 20177:00 amRNSReserves Based Loan Covenant Compliance
26th Apr 20177:00 amRNSProduction update
5th Apr 20174:16 pmRNSResults of General Meeting
15th Mar 20177:00 amRNSNotice of GM - Rule 9 Waiver
15th Feb 20177:00 amRNSUpdate re Operations and Year-end Reserves
26th Jan 20177:00 amRNSCorrection - Production Update
24th Jan 20177:00 amRNSProduction Update
18th Jan 20174:35 pmRNSPrice Monitoring Extension
12th Jan 20177:00 amRNSOperations Update
3rd Jan 20177:00 amRNSCompany Update
21st Dec 20164:35 pmRNSPrice Monitoring Extension
16th Dec 20167:00 amRNSMonarch JDA Settlement Agreement
12th Dec 20164:35 pmRNSPrice Monitoring Extension
7th Dec 20164:35 pmRNSPrice Monitoring Extension
2nd Dec 20164:35 pmRNSPrice Monitoring Extension

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.