Liqhobong Commences Production Ramp-up

21 Oct 2016 07:00

RNS Number : 1118N
Firestone Diamonds PLC
21 October 2016
 

21 October 2016

 

Firestone Diamonds plc

("Firestone", the "Group" or the "Company") (AIM: FDI)

 

Liqhobong Diamond Mine Commences Production Ramp-up

 

Firestone Diamonds plc, the AIM-quoted diamond company, is pleased to provide its quarterly update on activities at its Liqhobong Diamond Mine ("Liqhobong" or the "Project") as at the end of September 2016 and to also announce the recovery of the first diamonds as the Project moves into the production ramp-up phase. Liqhobong is owned 75% by Firestone and 25% by the Government of Lesotho.

 

Post period: Ramp-up production highlights as at 20 October 2016

· Recovery of first diamonds

- First ore treated through plant as scheduled with diamonds reporting to the sort house

- Initial recoveries are as expected and confirm presence of fancy yellow diamonds

· Commissioning at 96% complete

· First ore blast in the main pit successfully completed

· Waste stripping on target

· Ramp-up to commercial production now commenced

- Production guidance for financial year ending June 2017 remains as announced in July 2016, with 1.8 to 2 million tonnes ("Mt") treated and between 380,000 and 450,000 carats recovered

- Full production rates expected to take at least six months

 

Construction highlights as at the end of September 2016

· All major construction activities complete

· Plant 91% commissioned, ahead of revised target of 50%

· Revised capital budget of ZAR2.1 billion, remains within the original project budget of US$185.4 million

· Zero lost time injury record maintained, with approximately 3.2 million man hours worked

 

Stuart Brown, Chief Executive Officer, commented:

 

"It is extremely exciting to have reached the end of the construction phase and to start the next chapter of the Liqhobong Diamond Mine, as we ramp-up production to become a one million carat per annum producer.

 

Discovered in the 1950's this exciting diamond deposit is on the cusp of entering commercial production and I commend the team for completing construction ahead of revised schedule and achieving over three million man hours without a lost time injury - a truly exceptional accomplishment."

 

Project Update

 

Liqhobong has completed all major construction activities and at the end of September 2016 the Project was 98% complete and well ahead of schedule. The teamwork and cooperation of all staff and contractors has allowed the Project to achieve commissioning well ahead of plan. The commissioning phase was 91% complete at the end of the quarter and we have been able to commence the ramp-up to commercial production.

 

The remaining 2% of the Project construction relates to minor construction activities, such as cladding and final non-essential items, which will all be completed before the end of 2016.

 

 

Health & Safety

 

At the end of the quarter, the Project had maintained its remarkable safety record, having reached 3.2 million man hours worked without a single Lost Time Injury.

 

Financial

 

The Project continues to remain within the original US$185.4 million budget and as at 30 September 2016, ZAR1.8 billion (US$157 million) or 83% had been spent on the Project against the revised capital budget of ZAR2.1 billion. The cash on hand at the end of September 2016 was US$4.6 million and the Company also had US$29.0 million available pursuant to the ABSA debt facility, resulting in forecast headroom available to the Company of approximately US$9.0 million as at the end of December 2016. This does not include the US$15.0 million standby facility available to the Company.

 

Production Guidance

 

Following the completion of all major construction and commissioning stages, the production ramp-up phase has now successfully started. As per the announcement of 20 July 2016, Firestone anticipates that the ramp up process to full nameplate capacity, being 3.6 million tonnes per annum or 500 tonnes per hour to recover up to 1 million carats per annum, will take at least six months.

 

As set out previously, during the initial ramp-up phase, ore from mixed low grade stockpiles and diluted ore from the main pit will be processed through the plant. The variability of this ore will therefore influence the recovery of run of mine carats and it is difficult at this stage to predict the average dollar per carat that will be achieved from the early diamond sales. The Company expects to treat between 1.8 and 2.0 Mt of ore, recovering between 380,000 and 450,000 carats, during the financial year ending June 2017. Costs are projected to be in the region of US$12 to US$14 per tonne processed.

 

Diamond Recovery

 

Diamonds recovered to date are in line with the low grade stockpiles and diluted ore that has been fed through the plant. Pleasingly the first fancy yellow diamond has been recovered. As the Company continues with the ramp-up of production and begins treatment of run of mine ore from the main pit, Firestone expects that the quality and size of the diamonds recovered will improve.

 

Diamond Sales

 

Firestone has scheduled its first diamond sale to take place in Antwerp in January 2017. The sale will complete early in February 2017. Thereafter the Company expects to host two sales per quarter. As the Company increases production through the ramp-up phase and begins to treat larger volumes of kimberlite from the main pit, it will obtain an enhanced understanding of the occurrence and value of large stones over time.

 

Image Gallery

 

Each month the Company updates its media gallery to include images to illustrate the Project's progress and these can be found on Firestone's website: www.firestonediamonds.com/media.

 

For more information contact:

 

Firestone Diamonds plc

+44 (0)20 8741 7810

Stuart Brown

Strand Hanson Limited (Nomad)

+44 (0)20 7409 3494

Stuart Faulkner

Richard Tulloch

James Dance

Macquarie Capital (Europe) Limited (Joint Broker)

Raj Khatri

+44(0)20 3037 2000

Nick Stamp

Mirabaud Securities LLP (Joint Broker)

Rory Scott

+44 (0)20 7878 3360

Ed Haig-Thomas

+44 (0)20 7878 3447

Tavistock (Public and Investor Relations)

+44 (0)20 7920 3150

Emily Fenton

Jos Simson

+44 (0)7788 554 035

Barney Hayward

 

Background information on Firestone

 

Firestone is an international diamond mining company with operations focused on Lesotho. Firestone is currently in the process of commencing production at the Liqhobong Diamond Mine in Lesotho to become a one million carat per annum producer.

 

Lesotho is emerging as one of Africa's significant new diamond producers, hosting Gem Diamonds' Letseng Mine, Firestone's Liqhobong Mine and Namakwa Diamonds' Kao Mine.

 

For more information please visit: www.firestonediamonds.com.

 

**ENDS**

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
UPDBLBDGDXDBGLG
Date   Source Headline
28th Jan 20107:00 amRNSOrapa joint venture update
14th Jan 20107:00 amRNSEmployee Incentive Scheme Share Issue
21st Dec 20097:00 amRNSBotswana Joint Venture Agreement Signed
15th Dec 20095:53 pmRNSAGM Statement
10th Dec 20097:00 amRNSBotswana Operations Update
13th Nov 20097:00 amRNSPreliminary Results
21st Oct 200911:59 amRNSHolding(s) in Company
25th Sep 20097:00 amRNSBotswana Operations Update
31st Jul 20092:53 pmRNSHolding(s) in Company
30th Jul 20092:34 pmRNSHolding(s) in Company
24th Jul 200911:14 amRNSResult of General Meeting
8th Jul 200910:36 amRNSIssue of Equity
2nd Jun 20097:00 amRNSAppointment of Joint Brokers
31st Mar 20097:00 amRNSInterim Results
30th Mar 20097:00 amRNSBK11 Update
27th Mar 20097:00 amRNSTsabong Project Update
19th Feb 20097:00 amRNSFirestone selected as preferred bidder
16th Feb 20093:15 pmRNSHolding(s) in Company
9th Feb 20097:00 amRNSBuffels River Toll Treatment Update
29th Jan 200912:56 pmRNSResult of AGM
29th Dec 20089:26 amRNSAnnual Report and Accounts
10th Dec 20087:00 amRNSPreliminary Results
6th Oct 20087:00 amRNSBotswana Operations Update
16th Jul 20087:00 amRNSIssue of Equity
26th Jun 20087:00 amRNSBulk Sampling Results
19th Jun 20087:00 amRNSJoint broker appointment
18th Jun 20087:00 amRNSAdditional Listing
20th May 20085:33 pmRNSHolding(s) in Company
22nd Apr 20089:45 amRNSDoc re. Interim Results
31st Mar 20087:02 amRNSInterim Results
25th Feb 20087:00 amRNSEncouraging Results from MK1
18th Feb 20087:00 amRNSTsabong Evaluation Update
27th Dec 20079:32 amRNSAnnual Report and Accounts
18th Dec 20077:01 amRNSPreliminary Results
29th Oct 20077:01 amRNSUpdate on Tsabong evaluation
16th Oct 200711:01 amRNSHolding(s) in Company
8th Oct 20077:00 amRNSJoint Broker Appointment
17th Aug 20075:20 pmRNSHolding(s) in Company
16th Aug 20079:48 amRNSAIM Rule 26
31st Jul 20079:06 amRNSTotal Voting Rights
30th Jul 20077:01 amRNSEvaluation Programme Update
27th Jun 20072:51 pmRNSAdditional Listing
16th Apr 20077:01 amRNSUpdate on Tsabong project
2nd Apr 20071:09 pmRNSInterim Results - Replacement
30th Mar 20077:02 amRNSInterim Results
23rd Mar 20075:05 pmRNSHolding(s) in Company
22nd Mar 20075:03 pmRNSHolding(s) in Company
6th Mar 20077:02 amRNSProspecting Licence Award
26th Feb 20075:17 pmRNSHolding(s) in Company
21st Feb 20074:04 pmRNSHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.