The Moonlight Project - BFS Updates

2 May 2014 12:30

RNS Number : 1900G
Ferrum Crescent Ltd
02 May 2014
 

2 May 2014

 

Ferrum Crescent Limited

("Ferrum Crescent", the "Company" or the "Group") (ASX: FCR, AIM: FCR, JSE: FCR)

 

The Moonlight Project - BFS Updates

 

 

Ferrum Crescent, the ASX, AIM and JSE quoted iron ore developer, today announces a project update on the Bankable Feasibility Study ("BFS") underway at the Moonlight Iron Ore Project ("Moonlight Project" or "the Project"). The purpose of this announcement is to summarise recent work and outline the future work schedule in order to progress the Moonlight Project towards BFS close and construction financing.

 

Project overview

 

Various key components of the Moonlight Project BFS have already been concluded including:

· 30 year Mining Right granted

· Environmental licence (EIA) in place for the Moonlight Project mining area (approved 4 April 2013)

· Metallurgical test work - indicates high quality pellets in excess of 69% iron and low deleterious elements possible

 

In order to advance the BFS economic model, the Moonlight Project Resource has recently been made compliant with JORC code 2012. The completion of this work allows the Company to progress with final stage BFS work such as engineering design, connection to local infrastructure and permitting for the pelletising operation.

 

 

Moonlight Iron Ore Project BFS- Key components for completion

 

Process

The Moonlight Project has already had significant amounts of metallurgical process work undertaken on it and the next stage BFS stage for process represents the critical path for the whole Project. As a potential producer of a high-grade iron ore project, final assessment of Moonlight's capability to operate at an industrial scale is all important.

 

Metallurgists will work with geologists to identify key areas for representative sample selection for advanced testing including a pilot test work programme. Immediate test work will focus on financially optimising grind size vs iron recovery.

 

Future work will also focus on optimising the pelletising technology process undertaking activity such as temperature profiling and treatment times.

 

 

Mining

Plan the contract mining model for site development, overburden removal and general open pit mining activities; and

Low stripping ratio expected: 1:1.5 during the early years of operations (relatively shallow dips with occurrence of up to 4 magnetite-bearing zones).

Feasibility requirements to be completed:

• geotechnical drilling, mine design, mine reserve estimation based on certain cut-off estimates and economic criteria; and

• final estimate of mining costs from an adjudicated tender process for a contract mining will be concluded.

 

Infrastructure

Future pipeline work: 

• pipeline route EIA completion; and

• optimise pipeline design and costing (finalising rheology / density and particle size distribution)

Future power related work (ESKOM connection):

• finalise negotiations with Eskom for capital costs and tariffs once mining/process demand/schedules are finalised for the anticipated 110-120MW needed.

Future rail work (Transnet connection):

• Planning & costing loading / unloading facilities, wagon and locomotive requirements; and

• Transnet to review Project infrastructure needs as part of feasibility component - finalise commercial arrangements.

Future port work: (Richards Bay, connection)

• Secure area at the Richards Bay port and complete negotiations on handling and storage costs, post a more detailed understanding of the Project development schedule.

 

Environment

EIAs are currently being prepared for the other areas of the Project including the pellet plant site and pipeline route.

 

Geology and Mineral Resources

The Mineral Resources are currently located entirely on the farm Moonlight 111LR, with significant potential to expand the resource base within the Project area once all current work is financed and complete.

 

Community

A baseline socio-economic impact study of the areas occupied by both the Ga-Seleka and Ga-Shongoane communities situated within a 50km radius of the mining right area is well advanced.

Monthly meetings are held with the Royal Council and Traditional Council of both communities as well as updating the Lephalale Municipality on findings and proposed initiatives. Once the study is included an announcement will be made on findings relating to current local skills identification, futureemployment terms and training needs.

 

Project Schedule

 

• Feasibility study can be completed within 18 months work-time;

• 30 to 36 month construction period expected;

• Schedule coincides with Government infrastructure development plans; and

• Completion of the feasibility is expected to cost approximately A$10-13m.

 

 

Commenting today Tom Revy, Managing Director, said: "Since joining the Company earlier this year my focus has been on conducting a thorough review of all BFS work completed to date. I am extremely encouraged by what I have found with many key components such as metallurgy, mining right and infrastructure pathways completed or well underway. Getting the JORC Resource compliant with 2012 standards has been very important with all mineral assumptions now completely current with the international code. We shall now be focusing on moving forward and process work into trial mining and working on final infrastructure agreements to feed into the existing power, rail and port amenities."

 

 

 

 

For more information, please visit www.ferrumcrescent.comor contact:

 

Australia and Company enquiries:

UK enquiries:

Ferrum Crescent Limited

Ed Nealon T: +61 8 9380 9653

Executive Chairman

 

Tom Revy T: +61 8 9380 9653

Managing Director

Pareto Securities Ltd (Broker)

Guy Wilkes T: +44 (0) 20 7786 4370

 

RFC Ambrian Limited (Nominated Adviser)

Sarah Wharry/Stuart Laing

T: +44 (0) 20 3440 6800

 

Ferrum Crescent Limited

Laurence Read (UK representative)

T: +44 7557672432

 

South Africa enquiries:

Sasfin Capital

Leonard Eiser T: +27 11 809 7500

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLLLFILELIFIIS
Date   Source Headline
2nd Feb 20267:00 amRNSCancellation - EUROPA METALS LTD
30th Jan 20267:00 amRNSEuropa Metals: Cancellation of admission to AIM
20th Jan 202612:45 pmRNSLSE Timetable regarding Return of Capital
19th Jan 202611:00 amRNSReturn of Capital Finalisation
16th Jan 202612:54 pmRNSResult of AGM
15th Dec 20257:00 amRNSNotice of AGM and Proposed Return of Capital
26th Nov 20257:00 amRNSPostponement of 2025 Annual General Meeting
6th Nov 20257:00 amRNSProposed Acquisition of Marula Africa Mining Ltd
31st Oct 20251:15 pmRNSAnnual Financial Report
14th May 20257:30 amRNSSuspension - Europa Metals Ltd
14th May 20257:00 amRNSSuspension of trading on AIM
7th May 20257:00 amRNSFee Conversions and Issue of Equity
23rd Apr 20257:00 amRNSPartial disposal of Denarius Metals shares
28th Mar 20259:30 amRNSHalf-year Report
21st Feb 20257:00 amRNSCorporate Update
17th Feb 20257:00 amRNSViridian Metals Transaction Update
22nd Jan 20257:00 amRNSViridian Metals Transaction Update
6th Dec 20249:00 amRNSViridian Metals Transaction Update
29th Nov 20241:00 pmRNSResult of AGM
26th Nov 20247:00 amRNSConvertible loan note issuance
13th Nov 20249:00 amRNSCompletion of Disposal of Toral Project
6th Nov 202410:00 amRNSNotice of AGM
31st Oct 20249:00 amRNSFinal Results
28th Oct 20242:00 pmRNSViridian Metals Transaction Update
25th Oct 20242:00 pmRNSResults of General Meeting
1st Oct 202411:00 amRNSNotice of General Meeting
17th Sep 20247:30 amRNSSuspension - Europa Metals Ltd
17th Sep 20247:30 amRNSProposed Disposal of Toral Project to Denarius
17th Sep 20247:00 amRNSProposed Company Acquisition, RTO & AIM suspension
16th Sep 202410:00 amRNSHolding(s) in Company
30th Aug 20248:45 amRNSHolding(s) in Company
13th Aug 20241:00 pmRNSHolding(s) in Company
26th Jul 20249:00 amRNSHolding(s) in Company
2nd Jul 202411:00 amRNSHolding(s) in Company
26th Jun 20241:00 pmRNSHolding(s) in Company
14th May 202412:00 pmRNSChange of Auditor
28th Mar 20247:28 amRNSHalf-year Report
11th Dec 20237:00 amRNSConversion of Performance Rights
30th Nov 202311:30 amRNSResult of AGM
1st Nov 20237:00 amRNSFinal Results and Notice of AGM
23rd Oct 20237:00 amRNSToral Mining Licence Application process completed
9th Oct 20237:00 amRNSAppointment of Nominated Adviser and Broker
4th Aug 20237:00 amRNSDrilling Results and Mining Licence Update
25th Jul 20238:00 amRNSDrawdown of Final Tranche of CDTI Loan
19th May 20237:00 amRNSDrilling Results
5th Apr 202310:00 amRNSOperational Update
31st Mar 20237:00 amRNSHalf-year Report
22nd Mar 20232:00 pmRNSToral JV Update: Initial budget agreed w/Denarius
24th Jan 20231:00 pmRNSDirectors’ Dealings and Issue of Equity
30th Dec 202212:00 pmRNSResult of General Meeting

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.