Operational Summary 2012

19 Dec 2012 07:00

RNS Number : 7750T
Ferrum Crescent Ltd
19 December 2012
 

19 December 2012

 

Ferrum Crescent Limited

("Ferrum Crescent", the "Company" or the "Group") (ASX: FCR, AIM: FCR, JSE: FCR)

Operational Summary 2012

 

Ferrum Crescent Limited, the ASX, AIM and JSE quoted iron ore developer in northern South Africa, today announces an operational summary of work during 2012 progressing component parts of the Bankable Feasibility Study ("BFS") being carried at out the Company's Moonlight Iron Ore Project.

 

2012 - key milestones

Ø New JORC compliant resource at Moonlight Iron Ore Project of 307.8 million tonnes @ 26.9% Fe.

Ø 2,827 line km on 50m line spacing was completed with Interpretation of the results of a high resolution airborne magnetic survey at Moonlight.

Ø Survey enhanced assumptions at existing exploration area and also identified new prospective areas to the south, east and west of the Moonlight Deposit.

Ø Moonlight granted Mining Right with licence covering the farms Moonlight, Julietta and Gouda Fontein, having met all criteria under South African law including environmental and social and labour plans.

Ø Negotiations with Transnet and other infrastructure suppliers progressed.

Moonlight project overview

The Moonlight Project is currently undertaking a bankable feasibility study ("BFS") in relation to the potential development of a deliverable, low cost magnetite ore project that produces a high grade, low contaminant iron pellet, product following beneficiation. The current established JORC compliant resource is 307.8 million tonnes Resource, a magnetite ore with metallurgy that demonstrates capability for high grade product up to 69.7% Fe grade. Metallurgical testing phases have also shown that the product is likely to contain extremely low contaminants-2.05% SiO2, and 0.40% Al2O3, and 0.01% P.

 

It is anticipated that Moonlight will be developed as a contract, open-pit mine with onsite concentrate production. A slurry concentrate pipeline to pelletising plant near railhead will be created, with return water to Moonlight (100 - 220km); current preferred sites are at Lephalale and Thabazimbi. A pelletising plant to produce iron ore pellets (68.5% Fe) for international and domestic markets is planned with production at 6Mtpa DRI and BF pellets. With a high grade, pure product near existing rail infrastructure and producing steel mills an offtake agreement for initial production has already been signed with Duferco. It is expected that production will be a mix of direct reduction iron ("DRI") grade and blast furnace grade iron pellets.

Strategic rationale for 2012 work programme

With extensive exploration already complete at Moonlight, Ferrum has prioritised increasing economic understanding of the existing mineralisation in order to provide the data need to complete a BFS study for development of the project into near-term production. Focussed work was also undertaken to examine the expansion potential of Moonlight outside of existing JORC delineation. With long lead times often involved in procuring relevant licensing for development the Company also made it a clear objective to secure a full, granted, mining licence over all the Moonlight area.

 

 

 

2013

Ferrum Crescent will continue to progress the Moonlight Iron Ore Project, with the intention of having a BFS completed by the end of 2013.

Commenting today Ed Nealon, Chairman, said, "2012 saw the conclusion of an exploration campaign that established our JORC resource to higher levels of economic certainty and also identified additional areas for exploration expansion. Securing our mining licences over all areas of Moonlight was a significant milestone achieved during 2012. I look forward to progressing our infrastructure analysis and process testing working alongside our initial offtake partners and other parties interested in the near term viability of a potentially high grade, low impurity magnetite iron ore product."

Australia and Company enquiries:

UK enquiries:

Ferrum Crescent Limited

Ed Nealon T: +61 8 9380 9653

Executive Chairman

 

Bob Hair T: +61 414 926 302

Managing Director

Ocean Equities Limited (Broker)

Guy Wilkes T: +44 (0) 20 7786 4370

 

RFC Ambrian Limited (Nominated Adviser)

Richard Morrison T: +44 (0) 20 3440 6800

Jen Boorer T: +44 (0) 20 3440 6800

 

Laurence Read (UK representative)

T: +44 7557672432

 

South Africa enquiries:

Sasfin Capital

Leonard Eiser T: +27 11 809 7500

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCFFESAAFESEDE
Date   Source Headline
2nd Feb 20267:00 amRNSCancellation - EUROPA METALS LTD
30th Jan 20267:00 amRNSEuropa Metals: Cancellation of admission to AIM
20th Jan 202612:45 pmRNSLSE Timetable regarding Return of Capital
19th Jan 202611:00 amRNSReturn of Capital Finalisation
16th Jan 202612:54 pmRNSResult of AGM
15th Dec 20257:00 amRNSNotice of AGM and Proposed Return of Capital
26th Nov 20257:00 amRNSPostponement of 2025 Annual General Meeting
6th Nov 20257:00 amRNSProposed Acquisition of Marula Africa Mining Ltd
31st Oct 20251:15 pmRNSAnnual Financial Report
14th May 20257:30 amRNSSuspension - Europa Metals Ltd
14th May 20257:00 amRNSSuspension of trading on AIM
7th May 20257:00 amRNSFee Conversions and Issue of Equity
23rd Apr 20257:00 amRNSPartial disposal of Denarius Metals shares
28th Mar 20259:30 amRNSHalf-year Report
21st Feb 20257:00 amRNSCorporate Update
17th Feb 20257:00 amRNSViridian Metals Transaction Update
22nd Jan 20257:00 amRNSViridian Metals Transaction Update
6th Dec 20249:00 amRNSViridian Metals Transaction Update
29th Nov 20241:00 pmRNSResult of AGM
26th Nov 20247:00 amRNSConvertible loan note issuance
13th Nov 20249:00 amRNSCompletion of Disposal of Toral Project
6th Nov 202410:00 amRNSNotice of AGM
31st Oct 20249:00 amRNSFinal Results
28th Oct 20242:00 pmRNSViridian Metals Transaction Update
25th Oct 20242:00 pmRNSResults of General Meeting
1st Oct 202411:00 amRNSNotice of General Meeting
17th Sep 20247:30 amRNSProposed Disposal of Toral Project to Denarius
17th Sep 20247:30 amRNSSuspension - Europa Metals Ltd
17th Sep 20247:00 amRNSProposed Company Acquisition, RTO & AIM suspension
16th Sep 202410:00 amRNSHolding(s) in Company
30th Aug 20248:45 amRNSHolding(s) in Company
13th Aug 20241:00 pmRNSHolding(s) in Company
26th Jul 20249:00 amRNSHolding(s) in Company
2nd Jul 202411:00 amRNSHolding(s) in Company
26th Jun 20241:00 pmRNSHolding(s) in Company
14th May 202412:00 pmRNSChange of Auditor
28th Mar 20247:28 amRNSHalf-year Report
11th Dec 20237:00 amRNSConversion of Performance Rights
30th Nov 202311:30 amRNSResult of AGM
1st Nov 20237:00 amRNSFinal Results and Notice of AGM
23rd Oct 20237:00 amRNSToral Mining Licence Application process completed
9th Oct 20237:00 amRNSAppointment of Nominated Adviser and Broker
4th Aug 20237:00 amRNSDrilling Results and Mining Licence Update
25th Jul 20238:00 amRNSDrawdown of Final Tranche of CDTI Loan
19th May 20237:00 amRNSDrilling Results
5th Apr 202310:00 amRNSOperational Update
31st Mar 20237:00 amRNSHalf-year Report
22nd Mar 20232:00 pmRNSToral JV Update: Initial budget agreed w/Denarius
24th Jan 20231:00 pmRNSDirectors’ Dealings and Issue of Equity
30th Dec 202212:00 pmRNSResult of General Meeting

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.