Namwele Test Pit Results

24 Nov 2014 07:00

RNS Number : 7699X
Edenville Energy PLC
24 November 2014
 

Edenville Energy plc

 

("Edenville" or the "Company")

 

 

Namwele Test Pit Results

 

Edenville Energy is pleased to announce positive results from the first set of detailed coal sampling and test work at the Namwele deposit, part of the Rukwa Coal Project, near Sumbawanga in Western Tanzania.

 

During the past three months, test pits were dug to a depth of approximately 3 metres at the Namwele, Mkomolo and Muze deposits, collectively known as the Rukwa Coal Project, and the samples analysed for quality. The test results from Namwele are presented below, with further sampling analysis from Mkomolo and Muze expected to be announced by the end of 2014.

 

Four test pits were excavated at Namwele to expose the near surface coal seam, better defining the coal that could be extracted in the initial stage of mining operations. For near surface coal seams, test pitting is the most common, efficient and effective way of gathering data, not only quicker and less costly than a drill programme but also allowing a specific coal seam to be exposed, examined and sampled more thoroughly. The excavation and sampling work was carried out by Edenville personnel with full quality control processes and procedures in place.

 

This near-surface coal seam has an average thickness of 2.0m and was sampled to a maximum depth from surface of 4m, with an average depth from surface of 2.56m. The four test pits were distributed along a total strike length of approximately 870 metres through the Namwele deposit.

 

The samples from these four test pits at Namwele have been analysed at Alfred H Knight's laboratory in Scotland, UK. Alfred H Knight ("AHK") is a highly respected analytical laboratory group that specialises in metals and minerals testing, with particular expertise in coal. It is ISO 9001:2008 accredited and operates in 35 countries carrying out a wide range of test work on coal and other fuel sources.

 

The results shown in Table 1 below show the combined raw coal analysis and the washed results at a Relative Density ('RD') of 1.7 for the Namwele test pits.

 

Table 1 - Raw Coal Analysis (Air Dried Basis)

 

Sample

Inherent Moisture (%)

Ash

(%)

Volatile

Matter (%)

Sulphur

(%)

GCV (Mj/Kg)

5523

6.80

39.00

22.80

2.36

15.40

5522

5.80

50.50

20.00

7.05

11.95

5521

8.30

37.80

23.60

7.54

15.22

5520

7.70

39.60

22.80

6.84

15.00

Average

7.15

41.73

22.30

5.95

14.39

Table 2 - Floats Basis Float and Sink Coal Analysis (Air Dried)

 

 

Sample

Mass

Yield

R.D.

Inherent Moisture (%)

Ash

(%)

Volatile

Matter (%)

Sulphur

(%)

GCV (Mj/Kg)

5523

8027.4

54.78

F1.70

4.80

27.78

29.02

1.70

21.18

5522

5049.3

35.89

F1.70

4.09

24.17

29.93

3.07

22.68

5521

7826.9

58.37

F1.70

5.79

18.90

33.39

4.15

23.32

5520

7602.9

54.29

F1.70

7.31

18.65

31.95

3.79

23.43

Average

7126.625

50.83

F1.70

5.62

22.27

31.16

3.17

22.63

 

 

Of specific note is the yield of over 50% from the latest wash tests at a relative density of 1.7, which produced an average 22.6MJ/kg product. The original wash tests on the Namwele resource, cited in the Geological Modelling and Resource Estimation for the Rukwa Coal Project dated March 2013 returned a washed yield of 11.6%, albeit on a global basis over the entire coal measures.

 

The recent test pit samples averaged a raw energy value of 14.39MJ/kg compared to a previous global value of 6.8MJ/kg in the original drill samples at Namwele, again described in the above report.

 

Sulphur and ash varied over the test pits with sulphur washing out to 1.7% in some areas whilst remaining above 3% in others. Washed ash averaged 22.27% being reduced to as little as 18.6% in some samples. A degree of selective mining and blending would be envisaged to give a consistent coal product.

 

Putting these test pit results in context, the improved coal quality applies to the uppermost, near surface seam, whilst the original resource values apply to the entire coal measures both laterally and vertically. We are, however, very encouraged by these positive results in the top seam of three at Namwele.

 

The results indicate high quality, near surface coal is available in the Namwele area. The utilisation of selective mining techniques to extract this coal may bring improvements in the quality of available feedstock for a Thermal Power Plant and also provides the basis for the detailed investigation into the potential to sell higher quality coal directly into the local and regional markets.

 

Rufus Short, CEO of Edenville Energy commented: "We are very encouraged by the positive results returned from our Namwele test pits. They show the Namwele deposit has the possibility to provide significantly higher quality coal and a higher washed yield than previously modelled. This could improve the technical and economic parameters for the coal-to-power development and also forms the basis for a detailed investigation into potential coal sales to the regional market. The testwork on the Mkomolo and Muze deposits is well underway and we will update our shareholders as the results become available".

 

Qualified Person Review

 

Mark J.Pryor, Pr.Sc.Nat. has reviewed and approved the technical information contained within this announcement in his capacity as a Qualified Person, as defined by the AIM Rules and National Instrument 43-101 Standards of Disclosure for Mineral Projects.

 

Enquiries:

 

Edenville Energy plc

+44 (0)20 7653 9850

Sally Schofield - Chairman

 

Cantor Fitzgerald Europe (Nominated Adviser and Broker)

+44 (0) 207 894 7000

Stewart Dickson / Jeremy Stephenson

 

Newgate Threadneedle (Financial PR)

+44 (0) 207 653 9850

Roddy Watt / Edward Treadwell

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCLFFSILRLVFIS
Date   Source Headline
16th Aug 20237:00 amRNSAppointment of Joint Corporate Broker
15th Aug 20237:00 amRNSChange of Admission Date
3rd Aug 20235:40 pmRNSResult of AGM,Directorate Change,Director Dealings
10th Jul 20237:00 amRNSNotice of AGM
4th Jul 202311:14 amRNSHolding(s) in Company
30th Jun 20237:00 amRNSAnnual Results for the year ended 31 December 2022
22nd Jun 20232:51 pmRNSHolding(s) in Company
21st Jun 20235:43 pmRNSHolding(s) in Company
19th Jun 20235:28 pmRNSHolding(s) in Company
5th Jun 20239:30 amRNSHolding(s) in Company
2nd Jun 202311:25 amRNSHolding(s) in Company
2nd Jun 20237:00 amRNSProposed Change of Name
1st Jun 20239:05 amRNSStrategic Investment and Board Changes
24th May 202312:33 pmRNSHolding(s) in Company
23rd May 20234:01 pmRNSHolding(s) in Company
11th Apr 20237:00 amRNSRukwa Production Update
28th Mar 20239:16 amRNSRukwa Operational Update
24th Mar 20234:54 pmRNSHolding(s) in Company
9th Feb 20237:00 amRNSRukwa Operational Update
16th Dec 20229:07 amRNSHolding(s) in Company
14th Dec 20229:26 amRNSHolding(s) in Company
13th Dec 202211:38 amRNSHolding(s) in Company
13th Dec 202210:21 amRNSRejection of Unfair Dismissal Claim
7th Dec 20229:39 amRNSHolding(s) in Company
6th Dec 20227:00 amRNSPlacing to raise £0.4 million & Operational Update
9th Nov 20227:00 amRNSRukwa Operational Update & Corporate Update
13th Oct 20227:00 amRNSDirectors’ Dealings
11th Oct 20227:00 amRNSRukwa Coal Project Operational Update
29th Sep 20229:48 amRNSInterim Results
18th Aug 20225:20 pmRNSDirectors’ Dealings
16th Aug 20227:00 amRNSNew Coal Mining Agreement
4th Aug 20227:00 amRNSDirectorate Change
3rd Aug 20222:05 pmRNSSecond Price Monitoring Extn
3rd Aug 20222:00 pmRNSPrice Monitoring Extension
3rd Aug 202212:00 pmRNSCorporate Update
3rd Aug 202211:27 amRNSResult of AGM
8th Jul 20224:30 pmRNSNotice of AGM
5th Jul 20227:00 amRNSBoard Changes
30th Jun 20227:00 amRNSResults for the year ended 31 December 2021
31st May 20227:00 amRNSTermination of Coal Mining Agreement
26th May 20223:46 pmRNSHolding(s) in Company
18th May 20221:15 pmRNSOperational Update Rukwa Coal Project
4th May 20223:52 pmRNSOperational Update Rukwa Coal Project
3rd Feb 20221:20 pmRNSNew Coal Mining Agreement Signed
12th Jan 20227:00 amRNSAppointment of Broker
4th Jan 20227:00 amRNSAppointment of Interim Broker
7th Dec 20212:06 pmRNSSecond Price Monitoring Extn
7th Dec 20212:01 pmRNSPrice Monitoring Extension
7th Dec 202111:06 amRNSSecond Price Monitoring Extn
7th Dec 202111:00 amRNSPrice Monitoring Extension

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.