18 Dec 2008 07:00
ο»Ώ
18Β December 2008
Cadogan Petroleum
OperationalΒ ReviewΒ Update
TheΒ Board ofΒ Cadogan Petroleum plc ("Cadogan"Β or the "Company") today provides an update on its operational review, which we announced in our Interim Management Statement on 19 November.
INTRODUCTION
Since the Company's IPO in June 2008, Cadogan has continued to invest in the appraisal and development of its assets inΒ Ukraine. For various operational reasons,Β first production from Pirkovskoe and Zagoryanska is not now expected until Q1 2009. In view of this deferral of revenue, and taking account of future production risks and external factors, the Board has undertaken a review of the Company's planned operations to ensure that it retains appropriate financial headroom going forward. Under the revised operational plan,Β the Company remains able to finance itself independently during 2009 and 2010, by which time it expects to be generating significant revenues from production.Β
The objective of the revised operational plan is to focus the Company's available resources in the most cost efficient manner on thoseΒ assetsΒ which are most likely to produce near term cash flow benefits, with the longer term objective of adjustingΒ theΒ capital expenditure profileΒ to be consistent with internal cash flow generation.Β In this way we are confident of our abilityΒ maintain a viable stand-alone funding strategy.Β AsΒ a result of these measures, the Board is confident that we willΒ maintainΒ aΒ positiveΒ net cashΒ positionΒ for the foreseeable future, with theΒ near-termΒ low pointΒ ofΒ in excess of $20 millionΒ expected inΒ SeptemberΒ 2009.
Cadogan'sΒ revised operational plan incorporates the followingΒ keyΒ components:
completeΒ a total ofΒ 8Β exploration and development wells in 2009 and 2010;
investΒ someΒ $76.2millionΒ (Β£50.8Β million)Β in capital expenditure in 2009Β and some $56.7Β millionΒ (Β£37.8Β million)Β in 2010Β thereby deferring some $179.0Β millionΒ (Β£119.3Β million)Β of capital expenditureΒ in total over those two yearsΒ ;
monthlyΒ averageΒ expenditureΒ rateΒ to be $15.7 million (Β£10.5 million) in the first quarter of 2009, reducing to $3.8 million (Β£2.5 million) in the third quarter of 2009, leavingΒ in excess of $20 millionΒ (Β£13.3Β million) headroom in September 2009;
decideΒ whether to incur further drilling expenditureΒ in relation toΒ theΒ PokrovskoeΒ fieldΒ inΒ MarchΒ 2009, depending on the outcome ofΒ testingΒ ofΒ theΒ V20/V21Β horizonsΒ in the PokrovskoeΒ 1Β wellΒ which is due to commence in mid January and be completed by midΒ March;
bringΒ production on lineΒ from ourΒ PirkovskoeΒ 1 and ZagoryanskaΒ 3Β wellsΒ by the end of Q1 2009;
defer delivery ofΒ theΒ PirkovskoeΒ gas plantΒ which is being constructed forΒ us byΒ Global Process SystemsΒ Inc.Β in DubaiΒ until 2010, thereby deferring significant capital expenditureΒ associated with theΒ import,Β installationΒ and commissioningΒ of the plantΒ until after we are generatingΒ more significantΒ revenues;Β and
a rigorous cost control plan to minimise our overhead expenditure.
WeΒ will continue to maintain a closeΒ and proactiveΒ dialogueΒ with the relevant authoritiesΒ in relation to our licence obligations with a view toΒ protectingΒ the value inherent in those licences which we choose to develop further.Β
The Board also continues to explore additional financing and strategic options to enable the Company to develop its assets more quickly and efficiently with a view to optimising the NAV. However, the Board believes that the revised operational plan outlined above is an essential precursor to any other strategic options in the present market environment.
OPERATIONAL DEVELOPMENTSΒ TO DATE
SinceΒ its IPO, Cadogan has madeΒ the followingΒ progress on drilling its core wells:
Target depth ("TD") reached on Pirkovskoe #1Β andΒ Zagoryanska #3
Testing has been carried out on theseΒ wellsΒ as follows:
Pirkovskoe #1 -Β testingΒ of the V26 (Lower Visean) horizonΒ is currently being undertaken. Further testing is due to be carried out on the V24Β andΒ V25 horizons whichΒ is due to be completed by the end of January,Β following whichΒ the well will be prepared for production;
Zagoryanska #3 - testing resultsΒ are currentlyΒ in line with expectationsΒ over aΒ total net pay of 30 metres. Following completion of the ongoing tests, the well will be prepared for condensate production during February 2009 with gas production added during April 2009 on completion of theΒ requiredΒ processingΒ facilities; and
Drilling activity has been carried out on the followingΒ additional wells: Pirkovskoe #2, Pokrovskoe #1, Pokrovskoe #2,Β Zagoryanska #3, Borynya #3Β andΒ Bitlya #2.
REVISEDΒ OPERATIONALΒ PLAN
As outlined above,Β theΒ revisedΒ operational plan focuses activities on 8 wells during 2009 and 2010, the details of which are outlined below:
Pirkovskoe
Pirkovskoe #1 -Β as outlined above, the wellΒ is in the final phase of testing.Β CadoganΒ hasΒ no further capital expenditure scheduled on this well;
Pirkovskoe #2Β -Β has been drilled to 4580mΒ and 245mm intermediate casing will be set at this depth. The well will be suspended untilΒ Q1Β 2010 when it is planned to re-enter the well and drill to aΒ TDΒ of 5800 metres, test and complete the well for commercial production inΒ Q3Β 2010.;
Pirkovskoe #460 - initial test results were ahead of expectations, but following acid stimulation, significant water influx occurred and as a result, further workΒ on this well has been suspended with no further expenditure scheduled.Β There is the potential to undertake a future workover of this well which we will consider at a future point.
Zagoryanska
Zagoryanska #3 -Β as outlined above, the wellΒ is being testedΒ and aside fromΒ $2.3 million (Β£1.5 million)Β associated with the installation ofΒ the requiredΒ gas processingΒ facilities, Cadogan has no further capitalΒ expenditure planned on this well;
Zagoryanska #2Β -Β the workover on this well will commence in July 2009 and is planned to be completed in January 2010. ProductionΒ isΒ expected to commence duringΒ Q2Β 2010.
Pokrovskoe
Pokrovskoe #1 - currently atΒ 4810mΒ where the 245mm intermediate casing will be set. TheΒ V20/V21Β horizons will be tested between mid January and mid March 2009. The well will then be drilled to a plannedΒ TDΒ of 5400m during 3Q 2009 with production planned to commence duringΒ Q4Β 2009;
Pokrovskoe #2 - currently drillingΒ atΒ 5048m with TD ofΒ 5400m, expected to be reached inΒ AprilΒ 2009 with production expected to commence in mid 2009.
The testing programme thatΒ Cadogan has initiatedΒ on PokrovskoeΒ #1, once completed inΒ mid MarchΒ 2009,Β willΒ allow us to achieve greater certainty ofΒ the viability of the field for commercial production.
BitlyanskaΒ Licence Area
Borynya #3 - following encouraging gas showsΒ in theΒ upper unit of theΒ Oligocene horizons between 2700m and 3300m, we are now drilling atΒ 3375m. TestingΒ will shortly be carried outΒ on theΒ 2700mΒ - 3300mΒ interval.Β
Management's current intention is not toΒ continueΒ drillingΒ to the original TD ofΒ 4500m, but instead to start producing from theΒ upper unit of the OligoceneΒ with production expected to come online in late 2009 when our new gas plantΒ for the Bitlyanska licence areaΒ willΒ haveΒ been imported andΒ commissioned.
Bitlya #2 -Β the commencement of this well has been delayed until October 2009 withΒ production expected in late 2010.
Facilities
As stated above, the construction of the two gas plants ordered in mid 2008 remains on track inΒ Dubai
Cadogan will take delivery of the first gas plant inΒ Q2Β 2009. This plant will be commissioned on the Bitlyanska licence area andΒ is planned toΒ process gas from the Borynya and Bitlya fields
Following our operational review, the second gas plant, intended for the Pirkovskoe field, will notΒ nowΒ be commissioned during 2009 and will remain inΒ Dubai. We intend to take delivery of the plant during 2010 and commission it on the Pirkovskoe field as originally intended;
Cadogan is commissioningΒ lower cost,Β temporary gas processing plants on both the Zagoryanska and Pokrovskoe licence areasΒ to facilitate gas productionΒ from these fieldsΒ during 2009;
It is also intended that initial production from Pirkovskoe will be processed via the existing KraznozayarskaΒ gas processingΒ facility.
CASH POSITION
Cadogan's cash position as atΒ 17 December 2008Β is Β£88.1m. We set out below the key areas of expenditure since our IPO in June 2008Β (theΒ net cash positionΒ immediately followingΒ IPO was Β£153.3 million):
Expenditure of Β£18.3Β millionΒ on ongoing drilling activities;
Interim payments of Β£19.8Β millionΒ in relation to the new gas plants for Pirkovskoe and Bitlyanska;
Payments of Β£5.1Β millionΒ in relation to pre-ordering sufficient casingΒ and tubingΒ for the wellsΒ scheduled to beΒ drilled during 2009Β and 2010. Pre-ordering was requiredΒ to avoid import restrictions and higher dutiesΒ on such casingΒ and tubingΒ from 1 January 2009 inΒ Ukraine;
Payments of Β£13.3Β millionΒ in relation to the purchase of additionalΒ western drillingΒ equipment such asΒ TriplexΒ mudΒ pumps andΒ Twister Spin hydraulic power tongs,Β designed to address bottle-necks in our drilling operations and as a result toΒ increaseΒ theΒ efficiencyΒ of our operationsΒ over the intensive development period we have planned in 2009;
Β£8.1Β millionΒ of expenditure on G&A costs, which includes legal costsΒ of Β£5.1Β millionΒ in relation to our ongoing defence of ourΒ Pirkovskoe and ZagoryanskaΒ licences; and
Net operating costs and other income of Β£3.4 million and Β£2.7 million, respectively.Β
As stated above we expect theΒ monthlyΒ averageΒ expenditureΒ rateΒ to be $15.7 million (Β£10.5 million) in the first quarter of 2009, reducing to $3.8 million (Β£2.5 million) in the third quarter of 2009, leavingΒ in excess of $20Β million (Β£13.3Β million) headroom in September 2009.
OUTLOOK
Focus on implementation ofΒ new operational planΒ andΒ optimisationΒ of available cash resources;Β
Gaffney Cline and Associates assigned to reassess reserves with a view to converting contingent and prospective resources to reserves during the early part of 2009;
Cadogan continues to have a positive outlook on the Ukrainian gas price andΒ theΒ move towardΒ netbackΒ parity withΒ WesternΒ European levels. The current Ukrainian market price is $180/mcm;
Continued and vigorous pursuit of a satisfactory and timely conclusion to theΒ unwarrantedΒ legal challenges againstΒ the Company'sΒ licences.
Mark Tolley, Chief Executive commented:
"Mindful of the current challenging market and economic backdrop, we have revised our operational plansΒ toΒ optimise the use of our cash resources while delivering meaningful production in the near-term. At the same time, significant expenditure has been deferred to preserve funding and strategic flexibility. We continue to believe that we haveΒ aΒ diverse and excitingΒ portfolio, whichΒ will give us optionsΒ to developΒ the most attractive assetsΒ further fromΒ our existing cash resources andΒ buildΒ internally generated cash flows following the implementation of ourΒ revisedΒ operational plan. WeΒ alsoΒ remainΒ confident that we will be successful in the continued defence of ourΒ Pirkovskoe and ZagoryanskaΒ licences"
Enquiries
|
Pelham PR |
|
|
James Henderson |
+44 20 7743 6673 |
|
Alisdair Haythornthwaite |
+44 20 7743 6676 |
|
Evgeniy Chuikov |
+44 20 3008 5506 |
This operational review update includes forward-looking statements which reflect the Company's current expectations and objectives in relation to future operations. These forward-looking statements, as well as those regarding the Company's financial position, reserves, business strategy, asset development plan and any statements preceded by, followed by or that include forward-looking terminology such as the words "targets", "believes", "plans", "estimates", "expects", "forecasts", "aims", "intends", "will", "can", "may", "anticipates", "would", "should", "could" or similar expressions or the negative thereof, are subject to risks, uncertainties, contingencies and assumptions about the Company and its subsidiaries and investments, including, among other things, the development of its business, trends in its operating industry and future capital expenditures and acquisitions, commodity price fluctuations and political risk as well as other risks detailed in the Company's prospectus which can be accessed at www.cadoganpetroleum.com and elsewhere in documents filed from time to time with applicable regulatory authorities. In light of these risks, uncertainties, contingencies and assumptions, many of which are beyond the control of the Company, the actual results could differ materially from the forward-looking statements included in this operational review update. These forward-looking statements speak only as at the date of this operational review update and the Company undertakes no obligation to update any forward-looking statements to reflect events or circumstances after that date except as may be required by applicable securities laws.
Overview of Cadogan's licence interests
Cadogan is an independent oil and gas exploration, development and production company with onshore gas and condensate assets inΒ Ukraine. Cadogan currently has significant working interests in 11 licence areas covering 14 fields in Easter andΒ Western UkraineΒ with a combined area of approximately 1,150 sq. km. The headquarters inΒ KievΒ are supported by operational offices in eastern and westernΒ UkraineΒ together with a representative office inΒ London.
The Group's assets are located in two of the three proven hydrocarbon basins inΒ Ukraine, the Dnieper-Donets basin and the Carpathian basin. The Dnieper-Donets basin is the major oil and gas producing region ofΒ UkraineΒ accounting for approximately 90 per cent. of Ukrainian production from over 120 oil and gas fields. The Carpathian basin is one of the largest petroleum provinces inΒ Central Europe.
The Group classifies its assets into Major Fields, being those assets containing greater than 40 million barrels of oil equivalent ("MMboe") of reserves, contingent resources or prospective resources, and Minor Fields, being those containing less than 40 MMboe of reserves, contingent resources or prospective resources.Β
Gaffney Cline and Assocaites ("GCA"), an independent petroleum engineering consulting firm, estimates that, as at 31 January 2008, the Group had:
β’ proved net reserves of 109 Bcf of gas, 7.6 MMbbl of condensate and 0.16 MMbbl of oil;
β’ proved and probable net reserves of 320 Bcf of gas, 22 MMbbl of condensate and 0.77 MMbbl of oil; and
β’ proved and probable and possible net reserves of 588 Bcf of gas, 42 MMbbl of condensate and 1.6 MMbbl of oil.
GCA also estimates that, as at 31 January 2008, the Group had net best estimate contingent resources of 1,583 Bcf of gas, 48 MMbbl of condensate and 1.5 MMbbl of oil. In addition, GCA estimates that the Group has significant prospective resources.
For illustrative purposes, the Group has converted the net reserves and resources figures into MMboe, using the conversion factor of one MMboe equals 0.18 Bcf. This conversion results in proved net reserves of approximately 27.4 MMboe, proved and probable net reserves of approximately 80.4 MMboe, proved and probable and possible net reserves of approximately 149.4 MMboe and net best estimate contingent resources of approximately 334.4 MMboe.
Further information can be located on the Company's website at www.cadoganpetroleum.com
Follow the stocks