Less Ads, More Data, More Tools Register for FREE

Pin to quick picksBushveld Minerals Regulatory News (BMN)

  • This share is currently suspended. It was suspended at a price of 0.306
  • There is currently no data for BMN

Lemur Q4 Operational Update

13 Feb 2019 08:30

RNS Number : 8798P
Bushveld Minerals Limited
13 February 2019
Ā 

Market Abuse Regulation (MAR) Disclosure

Certain information contained in this announcement would have been deemed inside information for the purposes of Article 7 of Regulation (EU) No 596/2014 until the release of this announcement.

Ā 

13 February 2019

Ā 

Bushveld Minerals Limited ("Bushveld Minerals" or the "Company")Lemur Q4 Operational Update

Ā 

Bushveld Minerals Limited (AIM: BMN), the AIM listed, integrated primary vanadium producer, with ownership of high grade vanadium assets in South Africa,Ā is pleased to provide an operational update in respect of Lemur Holdings Limited ("Lemur"), the Company's coal and energy subsidiary that is developing an integrated thermal coal mining and independent power project (the "Imaloto Project") in Madagascar.

Key Highlights

Ā· Review completed of the Bankable Feasibility Study ("BFS") for the power aspect of the Imaloto Project.

Ā· Review process initiated for the final draft of the BFS for the coal mine portion of the Project.

Ā· Issued a Request for Proposals ("RFP") for Legal Advisory Services to draft and negotiate EPC (Engineering, Procurement and Construction) Contract(s) for the power project.

Ā· Continued progress on the Social and Environmental Impact Assessment Study ("SEIA") fieldwork.

Ā· Concluded the due diligence for the project preparation finance with one lender and continued engagement with all lenders on project financing.

Ā· Advanced discussions with export credit insurance provider for credit and political risk insurance cover.

Ā 

Prince Nyati, CEO of Lemur Holdings Limited, commented:

"The completion and review of the Bankable Feasibility Study for the power component of the Imaloto Project represents a key milestone achieved as we press ahead in ensuring Lemur delivers on the potential of the Imaloto Project. The Project's bankable feasibility study shows that the Imaloto Project is feasible and can deliver significant economic returns. More importantly, the Imaloto power project is the most advanced Independent Power Project ("IPP") baseload project in Madagascar.Ā It will have transformational developmental benefits for the country's southwest region, where the government has already implemented significant road infrastructure expansion. The coal reserve and transmission line is capable to support the generation capacity in excess of 60MW in the medium to long term as suppressed demand is unlocked in the region.

Furthermore, the peaceful democratic elections in Madagascar held in December 2018 are a welcome development and positive indication for projects in the country. With our development partner, Sinohydro,and advanced funding discussions with financial institutions, the Imaloto project remains on track to supply electricity to south westernĀ Madagascar."

Details of Operational Update

1. Power BFS:

In Q4 2018, Lemur and its technical advisors completed the review of the power BFS that was prepared by Sinohydro. The BFS was prepared on the basis of the agreement signed between Lemur and Sinohydro in March 2017. The Study contains the technical specifications for the generation and transmission aspects of the project:

Ā 

The main findings from the BFS are summarized as follows:

Ā 

Ā· Plant site: This project is located in the Owner's mining area of Imaloto area, which is near the town of Benenitra in Toliara Province, Madagascar. Water and coal source assessment determines that identified sources on site from the Imaloto mine and the Imaloto-Onilahy rivers confluence meet project requirements.

Ā· Installed capacity: Phase-1 installed capacity will be 30MW. The site expansion is reserved in the design for additional 30MW in Phase-2, to bring the total capacity to 60MW as prescribed by the concession agreement with the government of Madagascar.

Ā· The plant will utilize Circulating Fluidized Bed Combustion ("CFB") technology and Electrostatic Precipitators ("ESP") will be equipped for emission control.

Ā· New transmission lines will interconnect the Imaloto power station, Ilakaka, Toliara and Ambalavao. The initial distance of the transmission line will be 250km. Post Phase-2, the Imaloto project transmission network will cover an addressable market stretching approximately 500km - and will connect Toliara in the west to Fainaranstoa in the east for the first time.

Ā· The selected transmission voltage level is 138 kV, which matches the voltage level currently adopted by JIRAMA.

Ā· Supporting projects include 3 fully automatic controlled substations at Toliara substation, Ambalavao substation and Ilakaka as well as an access road between Ilakaka and the Imaloto power plant site.

Ā· The BFS also includes a Staffing plan as well as buildings and other structure design.

Ā· Design codes and standards: The BFS is performed based on international standard practices; IFC Environmental, Health, and Safety General Guidelines; and the relevant provisions of the law in Madagascar.

Ā 

Overall, Sinohydro's conclusion of the BFS is that with the analysis of the project from the aspect of construction condition, technical scheme, environmental protection, economic benefits and technical and economic risks, the project is feasible. Therefore, it is recommended that Lemur progressively develops the Imaloto Power Plant along with a transmission network project.

Ā 

2. The final draft of the BFS for the opencast mine has been completed and is currently undergoing an independent final review.

Ā 

3. Fieldwork under the SEIA study has advanced with the final output expected in Q2 2019, to allow for the completion of the wet season studies which are expected to commence at the end of March 2019.

Ā 

4. With the BFS for the power aspect completed and signed-off, the company is focussing on progressing the EPC discussions for both the power station and the transmission line. In order to achieve this, Lemur issued an RFP for legal advisory services in December 2018 to enable the engagement of EPC partners for the generation and transmission. It is likely that the engagement of the EPC partners may be tendered to the market.

Ā 

5. Since early 2018, Lemur has been in discussions with a number of financial institutions regarding project financing for the Imaloto project, with one of these parties completing its due-diligence in Q4 2018. Once all the parties have concluded their due-diligence, they will progress to finalise a term sheet on a syndicated project financing basis.

Ā 

6. In October 2018, Lemur was granted an extension on an expression of interest for credit and political risk cover for the Imaloto project. This was followed by a due-diligence process that is currently ongoing. The institution involved has shared key terms with Lemur, however, this aspect of the project will be carried out together with lender discussions. Therefore, the timelines for the conclusion of the risk cover terms will be aligned with lender agreements.

Ā 

Table 1: Project Objectives: 2019

Objective

Current Status

Complete Mine BFS

Ā· Currently under final review

Conclude the SEIA Study - Q2 2019

Ā· Field work ongoing

Appoint EPC Contractor - Q2 2019

Ā· Legal advisors shortlisted

Conclude funding, credit and political risk cover

Ā· Formal discussions ongoing

Ā 

Enquiries: info@bushveldminerals.com

Bushveld Minerals

+27 (0) 11 268 6555

Fortune Mojapelo, Chief Executive Officer

Chika Edeh, Head of Investor Relations

SP Angel Corporate Finance LLP

Nominated Adviser & Broker

+44 (0) 20 3470 0470

Ewan Leggat / Richard Morrison

Jonathan Williams / Richard Parlons

Alternative Resource Capital

Joint Broker

Rob Collins

+44 (0) 20 7186 9001

Alex Wood

+44 (0) 20 7186 9004

BMO Capital Markets Limited

Joint Broker

+44 (0) 20 7236 1010

Jeffrey Couch / Tom Rider

Michael Rechsteiner / Neil Elliot

Tavistock

Financial PR

+44 (0) 20 7920 3150

Charles Vivian / Gareth Tredway

Lifa Communications

Financial PR (South Africa)

+27 (0) 711 121 907

Gabriella von Ille

Ā 

Ā 

ABOUT BUSHVELD MINERALS LIMITED

Bushveld Minerals is a low cost, integrated, primary vanadium producer, with ownership of high grade vanadium assets.

The Company's flagship vanadium platform includes a 74 per cent controlling interest in Bushveld Vametco Alloys (Pty) Ltd, a primary vanadium mining and processing company; the Mokopane Vanadium Project and the Brits Vanadium Project.

Bushveld's vision is to become a significant, low cost, integrated primary vanadium producer through owning high grade assets. This incorporates development and promotion of the role of vanadium in the growing global energy storage market through Bushveld Energy Ltd, the Company's energy storage solutions provider. Whilst the demand for vanadium remains largely anchored in the steel industry, Bushveld believes there is strong potential for an imminent and significant global vanadium demand surge from the fast-growing energy storage market, particularly through the use and adoption of Vanadium Redox Flow Batteries.

While the Company's focus is on vanadium operations and the development and promotion of VRFBs, it has additional investments in coal, power and tin.

The coal platform comprises the wholly-owned Imaloto Coal Project, which is being developed as one of Madagascar's leading independent power producers. The Company's tin interests are held through its shareholding in AIM listed AfriTin Mining Limited.

The Company's approach to project development recognises that, whilst attractive project economics are imperative, they are insufficient to secure capital to bring them to account. A clear path to production within a visible timeframe, low capital expenditure requirements and scalability are important factors in ensuring a positive return on investment. This philosophy is core to the Company's strategy in developing projects.

Detailed information on the Company and progress to date can be accessed on the website www.bushveldminerals.com

Ā 

About Lemur Holdings

Lemur Holdings is a wholly owned subsidiary of Bushveld Minerals and is the company's coal and power platform. The Imaloto Power Project is located in the southwest ofĀ MadagascarĀ and consists of a 136 million tonne coal resource (90 per cent of which is of JORC compliant Measured and Indicated). The Project also includes a 30-year Concession for an initial 60MW mine mouth coal power plant as well as over 250km of new transmission lines, developed in parallel as one ofĀ Madagascar'sĀ leading independent power producers. Imaloto also has a secured 30-year electricity off-take with JIRAMA, the State Utility.

The initial phase of the Imaloto Power Project will potentially increaseĀ Madagascar'sĀ baseload capacity by approximately 15 per cent and almost double the transmission lines in the country. This is particularly important as the southwest region is mostly rural and about 95 per cent of the population does not have access to electricity. In terms of the in economic impact on southwestĀ Madagascar, the Imaloto Power Project is set to contribute close toĀ US$200 millionĀ in foreign direct investment intoĀ MadagascarĀ and will create over 1,000 jobs and approximatelyĀ US$1 billion dollarsĀ in revenue for the government ofĀ MadagascarĀ over its useful life.

Ā 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
Ā 
END
Ā 
Ā 
UPDZMGMZRFLGLZG
Date   Source Headline
16th May 20257:00 amRNSCancellation - Bushveld Minerals Limited
15th Apr 20254:28 pmRNSAppointment of Liquidators & Resignation of Nomad
11th Apr 20257:57 amRNSNotice of appointment of liquidators
15th Jan 20256:00 pmRNSBushveld Minerals
16th Dec 20247:15 amRNSBusiness Rescue and Operations Update
4th Dec 20247:00 amRNSResignation of Directors
29th Nov 20247:00 amRNSDefault on Shareholder Loan Repayment by Vanchem
19th Nov 202410:01 amRNSAppointment of Business Rescue Practitioners
18th Nov 20247:30 amRNSSuspension - Bushveld Minerals Limited
18th Nov 20247:00 amRNSTrading Suspension
8th Nov 20249:25 amRNSQ3 and 9M 2024 Operational Update
1st Nov 20243:05 pmRNSVanchem Sale Update
25th Oct 20242:21 pmRNSOperational Update
18th Oct 20249:18 amRNSDisposal of Interests in Lemur Holdings Limited
17th Sep 20247:00 amRNSInterim Results for Six Months ended 30 June 2024
10th Sep 20247:00 amRNSTurnaround Initiatives Underway
2nd Sep 20244:22 pmRNSOrion Matched Funding Received
14th Aug 20246:00 pmRNSSARB Approval for Orion US$10M Matched Funding
12th Aug 20244:13 pmRNSUS$2 million SPR Debt Funding Received
9th Aug 20249:55 amRNSAgreement re Settlement of SPR Subscription Funds
7th Aug 20244:25 pmRNSAnnual General Meeting Results
7th Aug 20247:00 amRNSDirector/PDMR Shareholding
6th Aug 20247:00 amRNSAnnual General Meeting Statement
31st Jul 20247:00 amRNSQ2 and H1 2024 Operational Update
24th Jul 20244:46 pmRNSHolding(s) in Company - Correction
15th Jul 202412:39 pmRNSDirector/PDMR Shareholding
12th Jul 20244:57 pmRNSDirector/PDMR Shareholding
11th Jul 20245:04 pmRNSPosting of Accounts & Notice of General Meeting
28th Jun 20245:30 pmRNSFinal Results for Year Ended 31 December 2023
28th Jun 20243:29 pmRNSFinancing Update: Orion matched funding of US$10m
28th Jun 20241:17 pmRNSHolding(s) in Company
26th Jun 202412:13 pmRNSHolding(s) in Company
24th Jun 20241:50 pmRNSSPR Funding & Orion 2024 Financing Package Update
31st May 20244:07 pmRNSCCSA Approval for sale of 64% interest in Mokopane
31st May 20241:07 pmRNSResult of Meeting
24th May 20245:53 pmRNSShareholder Correspondence and Questions & Answers
13th May 20247:00 amRNSPosting of Circular and Notice of General Meeting
7th May 20247:00 amRNSProposed conditional disposal of Vanchem
23rd Apr 20247:01 amRNSQ1 2024 Operational & Corporate Update
23rd Apr 20247:00 amRNSMineral Resources and Reserves Annual Update
14th Mar 20249:32 amRNSFurther Update on Outstanding Funds
14th Mar 20247:00 amRNSTR-1 Notification of Major Holdings
7th Mar 20243:00 pmRNSTR-1 Notification of Major Holdings
29th Feb 20245:30 pmRNSFurther Update on Outstanding Funds
16th Feb 20247:08 amRNSFurther update on Outstanding Funds
5th Feb 20247:08 amRNSFull year 2023 Operational Update
2nd Feb 20242:30 pmRNSForm 8.3 of the Takeover Code
1st Feb 20247:00 amRNSCompletion of Convertible Loan Note Refinancing
29th Jan 20244:25 pmRNSResignation of Finance Director
19th Jan 20244:32 pmRNSFurther Update on Outstanding Funds

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.