Miyabi - Randgold to proceed

3 Jun 2008 10:04

RNS Number : 8201V
African Eagle Resources PLC
03 June 2008
 



AFRICAN EAGLE PLC

RANDGOLD RESOURCES TO PROCEED WITH PHASE TWO

OF ITS JOINT VENTURE ON THE MIYABI GOLD PROJECT IN TANZANIA

Randgold completes Phase One exploration and exercises option to begin Phase Two

Structural study reveals targets for future drilling

Follow-up drilling and increased exploration expenditure 

African Eagle Resources plc ("African Eagle" or "the Company", ticker AIM: AFE, AltX: AEA) today announces that Randgold Resources Ltd ("RRS", ticker LSE: RRS, Nasdaq: GOLD) has now completed its Phase One exploration programme on the Miyabi Gold Project in the Lake Victoria Goldfields of Tanzania and has elected to enter the Earn-in Phase.

African Eagle's Managing Director Mark Parker commented "Randgold's decision to exercise its option to begin a formal earn-in to the Miyabi Joint Venture shows that it sees the potential of the project, and we look forward to rapid progress over the coming months. Randgold's careful geological and structural interpretation has identified several new conceptual gold targetsElsewhere, African Eagle itself is progressing rapidly on a number of its other projectsparticularly Mkushi, where the Company aims to start copper production by mid-2010".

Under the joint venture agreement, which was signed in May 2007, RRS has been undertaking an agreed Phase One exploration programme to assess the gold potential of the project beyond the 520,000 ounce JORC-compliant resource alreadoutlined by African Eagle. The Phase One programme included diamond drilling in the 7km x 2km northeast trending gold-bearing Miyabi shear zone corridor and RAB drilling over the Idahina geochemical targets, together with a structural and geological interpretation of all new and previous data. RRS's total expenditure on Phase One was just over US$1 million.

On completion of Phase One, RRS had the option, which it has now exercised, to commence Phase Two, under which it can earn a 50% interest in the joint venture by solely funding all further project costs up to and including completion of a predefined Pre-Feasibility Study. On completion of the Pre-Feasibility Study, African Eagle can elect to retain a 49% stake in the project by co-funding a Definitive Feasibility Study, or to dilute to a 35% stake if RRS provides all funding for this phase

Project Update

The Phase One exploration programme included 20 diamond drill holes (4,078m), mostly along two fences across the entire Miyabi corridor, and was principally designed to provide geological and structural informationIt was not the intention of the programme to add to the existing 520,000oz resource, but none the less, mineralisation was intersected during this programme and some significant assay results were reported by RRS. These included 12.2g/t over 1m within 1.6g/t over 9m in MBDH-44, 1.3g/t over 9m within 0.6g/t over 26mand 1.3g/t over 9m in MBDH-47.

Three of the drill holes were completed over a prominent geophysical induced polarisation target located northwest of the Kilimani deposit, and revealed gold associated with sulphides at the granite-greenstone contact zone. Such contacts are favourable sites for gold mineralisation, as at Faida, which hosts a resource of 200,000 ounces 5km to the southwest. The gold intersections helped to increase confidence in the decision to proceed to the next phase.

RRS's structural and geological modelling of the drill data indicates at least two phases of folding in the Miyabi corridor. This implies the possibility of hidden fold closures with associated "blind" gold mineralisation at depth.

RRS also completed a RAB drilling programme at the Idahina gold geochemical target, which lies approximately 12km southeast of the main Miyabi Corridor A total of 99 holes were completed for 3,402 metres, but assay results are still pending. 

Mark Parker

Managing Director

African Eagle Resources plc

03 June 2008

Qualified Person

Information in this report relating to exploration results is based on data reviewed by Mr Christopher Davies BSc, MSc, DIC, FSEG, FAusIMM, Operations Director for African Eagle, who is a Fellow of the Australasian Institute of Mining and Metallurgy, has more than 27 years relevant experience in mineral exploration and is a Qualified Person under AIM rules. Mr Davies consents to the inclusion of the information in the form and context in which it appears.

Technical terms

A glossary of technical terms used by African Eagle in this announcement and other published material may be found at www.africaneagle.co.uk/african-eagle-projects-glossary.html

For further information:

Mark Parker

Managing Director

African Eagle

+44 20 7248 6059

+44 77 5640 6899 

Nicola Marrin

Seymour Pierce LimitedLondon

Nominated Adviser

+ 44 20 7107 8000

Charmane Russell

Russell & Associates, Johannesburg

+ 27 11 8803924

+27 82 8928052

Ed Portman / Leesa Peters

Conduit PRLondon

+44 20 7429 6607

+44 (0) 7733 363 501

About Miyabi

The Miyabi Gold Project lies in the southwest part of the Lake Victoria Goldfield of Tanzania, about 50km west-southwest of Kahama township in Shinyanga District. The multi-zoned gold system at Miyabi, discovered by African Eagle's geochemical prospecting team, forms a corridor around 7km long by 2km wide and is associated with a major shear zone through greenstone and granitic rocks. To date, African Eagle's drilling has delineated five principal orebodies: Faida, Shambani Main and North, Ngaya and Kilimani.

In early 2006, the Company commissioned SRK Consulting Ltd to conduct a formal resource estimate based on all drill results to date. The total JORC compliant Mineral Resource was estimated to be 12.4Mt at a grade of 1.3g/t, containing 520,000 ounces of gold, using a cut-off grade of 0.5g/t, which is appropriate to Tanzanian deposits of the Miyabi type. Of this, 71% is in the Indicated category.

Independent metallurgical testing of systematically selected gold-bearing drill samples representative of all of the principal mineralised zones at Miyabi showed that standard leaching recovers 95% of the gold from the ore.

The potential for adding to the gold resource at Miyabi is very good, with many targets identified from geophysical and geochemical surveys within the main mineralised corridor remaining to be drilled, and African Eagle believes that the project could hold at least one million ounces. 

The Company's prospecting licences also cover more than 500 square kilometres of highly prospective granite-greenstone terrain around the main mineralised corridor and regional exploration of these areas has identified several promising targets. 

About African Eagle

African Eagle is a mineral exploration and development company operating in eastern and central Africa. The Company's principal advanced projects are the Mkushi Copper Mines project in Zambia and the Miyabi gold project in Tanzania, which are being prioritised towards production. The Company also holds a large well-balanced portfolio of promising earlier stage gold and base metal projects, including the Mokambo and Ndola copper projects in the Zambian Copperbelt and the Eagle Eye iron-oxide copper gold project in eastern Zambia.

African Eagle's projects are in ZambiaTanzania and Mozambique, countries which all have highly prospective geology, relatively low above-ground risks and track records of successful major investments in the metals and minerals industries.

African Eagle specialises in project generation and exploration. To take its discoveries into production, it seeks to sign up industry partners with records of successful mine development. These joint ventures and, in time, the revenue from advanced projects, will finance future exploration and new discoveries.

The Company has a highly motivated team, proven management and an experienced board. African Eagle prides itself on being a low cost operator and on average 80p or more of every £1 is spent "in the ground".

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUORKRWARNRRR
Date   Source Headline
18th May 20152:57 pmRNSFuture's interim pre-tax loss narrows, CFO to step down
11th Aug 20147:30 amRNSSuspension - African Eagle Resources Plc
16th Sep 20131:30 pmRNSPlacing
8th Jul 20082:00 pmRNSDirector/PDMR Shareholding
3rd Jun 200810:04 amRNSMiyabi - Randgold to proceed
20th May 20082:30 pmRNSDirector/PDMR Shareholding
13th May 20086:00 amRNSNdola Project Update
6th May 200812:00 pmRNSFinal Results
30th Apr 20089:31 amRNSMkushi Project Update
22nd Apr 20081:00 pmRNSHolding(s) in Company
26th Mar 20087:00 amRNSHolding(s) in Company
19th Mar 20087:00 amRNSDirector/PDMR Shareholding
1st Feb 20089:55 amRNSLatest Drilling Results
31st Dec 20077:00 amRNSTotal Voting Rights
20th Dec 20077:00 amRNSPDMZ Share Subscription
6th Dec 20077:00 amRNSMokambo HoA
4th Dec 20079:15 amRNSMkushi JV Progress Update
26th Nov 20074:02 pmRNSHolding(s) in Company
1st Nov 200710:00 amRNSMkushi Drilling Report
31st Oct 20077:01 amRNSTotal Voting Rights
30th Oct 20071:00 pmRNSGrant of Share Options
8th Oct 20073:00 pmRNSLunga Project
28th Sep 20077:06 amRNSInterim Results
28th Sep 20077:01 amRNSChairmans Review of Progress
20th Sep 20078:03 amRNSClarification re Mokambo
18th Sep 20077:00 amRNSMokambo South - Licence Award
31st Aug 20077:00 amRNSTotal Voting Rights
24th Aug 20079:47 amRNSAfrican Eagle Lists on AltX
24th Aug 20079:38 amRNSDrilling Results from Mkushi
17th Aug 20072:00 pmRNSAfrican Eagle to list on AltX
15th Aug 200712:12 pmRNSAIM Rule 26
31st Jul 200710:59 amRNSIssue of Equity
31st Jul 20077:01 amRNSDrilling Report
31st Jul 20077:00 amRNSTotal Voting Rights
25th Jul 20079:05 amRNSExercise of Share Options
10th Jul 20074:42 pmRNSResult of AGM
10th Jul 20077:00 amRNSEast African Uranium Assets
11th Jun 200712:37 pmRNSHolding(s) in Company
1st Jun 20077:01 amRNSNotice of AGM
1st Jun 20077:01 amRNSProgress Report and Accounts
29th May 20077:01 amRNSMkushi Joint Venture
15th May 20077:00 amRNSRe Alliance with Troll Mining
3rd May 20079:01 amRNSJoint Venture with Randgold
20th Apr 200711:54 amRNSDirector/PDMR Shareholding
10th Apr 20077:01 amRNSDrilling Report/PLUS Markets
28th Feb 20073:30 pmRNSTotal Voting Rights
26th Feb 20077:01 amRNSAdd lstng/Update on JV
23rd Feb 20079:24 amRNSHolding(s) in Company
14th Feb 20078:55 amRNSAdditional Listing
12th Feb 20079:55 amRNSAdditional Listing

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.