RE: Re. Moz11 Mar 2019 15:17
Actually, my post at 01:22 this mormning was wrong - the first Moz licence applications were not made in April last year they were made in January - see RNS 16/01/2018. So they have now been outstanding for 14 months as against the government guideline of 6 months. The PFS was started in August 2017 so has now been ongoing for nearly 19 months. No timescale for completion was given in the 23/08/2017 RNS, only the meaningless phrase 'it is anticipated that this work will be finalised in coming months'. In the RNS of 17/08/2017 regarding the construction of a pilot plant DA stated 'the completion of the plant will be a key milestone for the Mutamba Consortium as we move the Project towards a development decision.' So he reckoned we were moving towards a development decision back in August 2017 ??!