Based on a 12-hour shift (7:00 AM – 7:00 PM), 7 days a week with 3 active rigs cuts the expected timeline down to 7 to 11 months of continuous active drilling.
Operating every single Saturday and Sunday removes all weekend downtime, accelerating the project significantly.
The Core Math BreakdownAssuming an average hole depth of 450 metres (consistent with hole CRD042 targeting the full thickness of the Redmoor Sheeted Vein System), a 44-hole campaign totals roughly 19,800 to 20,000 metres of core drilling.Daily Rig Advance Rate:
A surface diamond rig in this geology typically advances 20 to 30 metres per 12-hour shift.Total Daily Team Progress: With 3 rigs running simultaneously, the site achieves 60 to 90 metres of progress per day.Total Days Required: Completing ~20,000 metres requires 222 to 333 active drilling days.
Recalculated Campaign MilestonesActive Drilling Phase: 7.5 to 11 months from the day planning is approved and the remaining two rigs mobilize.