RE: Over half way through July16 Jul 2025 12:28
@Synergiaenergy Cambay PSC Work Program Update #SYN Selan Exploration Technology Ltd has contracted a 50-tonne workover rig from Aakash Exploration to carry out three #SYN workover operations, starting with the C-64 well. Although civil works at the C-64 wellsite have been delayed due to monsoon conditions, the workover—scheduled for July 2025—will proceed with the installation of a sucker rod pump (SRP). Historically, the C-64 well has produced oil intermittently, but the installation of the SRP is expected to significantly improve production consistency and output.