Serica Energy Restarts Production At Erskine After Blockage Removal

Fri, 26th Oct 2018 12:07

LONDON (Alliance News) - Serica Energy PLC said on Friday action to remove gas hydrates in the Erskine to Lomond pipeline in the UK North Sea has been completed, with production from Erskine now restarted and flow rate optimised.

Erskine, in which Serica holds an 18% interest, was suspended in mid-January due to a blocked export pipeline which carried condensate from Erskine to the neighbouring Lomond platform. A new 26 kilometres long section of the line was completed in September.

Serica said it will provide further updates once the re-commissioning process is completed.

Shares in the oil and gas company were up 2.9% at 109.03 pence on Friday.

Related Shares

More News
20 Jun 2024 15:48

UK shareholder meetings calendar - next 7 days

20 Jun 2024 15:33

UK dividends calendar - next 7 days

5 Jun 2024 15:07

North Sea firms postpone oilfield opening after early UK election called

June 5 (Reuters) - Three British energy companies have decided to delay by a year the planned start of oil production at their joint-venture oilfiel...

3 Jun 2024 22:10

EXECUTIVE CHANGES: Shaun Hinds joins Newbury Racecourse as CEO

(Alliance News) - The following is a round-up of London-listed company director and manager changes announced on Monday and not separately reported by...

20 May 2024 09:29

Serica Energy gets final approval for Belinda field development

(Sharecast News) - Independent upstream oil and gas company Serica Energy announced the final approval from the North Sea Transition Authority (NSTA) ...

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.