IN BRIEF: ITM Power says Leuna contract module testing delayed

Wed, 16th Mar 2022 11:00

ITM Power PLC - South Yorkshire-based energy storage and clean fuel firm - Says 24 megawatt Leuna contract is delayed due to a local supply chain constraint involving tooling for the scale up of stack manufacture. ITM previously said Factory Acceptance Testing for all 12 modules would be completed by late April, but FAT completion for delayed modules is now expected in the new financial year, which starts in May.

"A longer-term solution for this supply chain constraint has already been defined and implemented, the benefit of which will be felt in the new financial year," ITM says.

Current stock price: 344.20 pence, down 3.9% on Wednesday

12-month change: down 26%

By Elizabeth Winter; elizabethwinter@alliancenews.com

Copyright 2022 Alliance News Limited. All Rights Reserved.

Itm Power

Shares in this article

Related News

ITM Power formally awarded DESNZ grant for "superior" Chronos project
1 day ago

ITM Power formally awarded DESNZ grant for "superior" Chronos project

(Alliance News) - ITM Power PLC on Thursday announced that the UK government has formally awarded a planned GBP46.5 million grant, with its chief exec...

LONDON BRIEFING: Centrica signs UK contract; Computacenter ups outlook
2 days ago

LONDON BRIEFING: Centrica signs UK contract; Computacenter ups outlook

(Alliance News) - Centrica secures a 20-year regulated contract to extend the life of the Sizewell B nuclear power station, Severn Trent says trading ...

Corporate News Severn Trent + 13 more shares
Director dealings: ITM Power's Warren East makes share purchase
1 Jul 2026

Director dealings: ITM Power's Warren East makes share purchase

(Sharecast News) - ITM Power revealed on Wednesday that non-executive director Warren East had acquired in the AIM-listed hydrogen economy business.