If you would like to learn more about future focusIR related events and roundtables, please submit your details here

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksWolf Minerals Regulatory News (WLFE)

  • There is currently no data for WLFE

Hemerdon Tungsten Project Pre-Construction Update

20 Jan 2014 07:00

RNS Number : 9269X
Wolf Minerals Limited
20 January 2014
 



20 January 2014 Wolf Minerals

 

 

Hemerdon Tungsten Project Pre-Construction Update

 

· Review of capital and operating costs

· Forecast tungsten prices have strengthened

· EPC contractor to commence project construction this month

 

Specialty metals development company, Wolf Minerals Limited (ASX: WLF, AIM: WLFE) (Wolf, the Company) is pleased to provide the following update on recent and planned activities at its world class Hemerdon Tungsten and Tin Project (Project) in the southwest of England.

 

Project Milestones

On 16 May, 2011, the Company announced the results of its Definitive Feasibility Study (DFS) for the Hemerdon Project.

 

Since completing the DFS, Wolf has successfully advanced the project to now being 'construction-ready', with the following key milestones achieved in recent months:

 

Financing

· A US$75 million Bridge Finance Facility secured from major shareholder, Resource Capital Funds, to commence design and construction work;

· Senior Project Finance Facilities of £75 million from ING, Unicredit and CAT Financial are in place;

 

Operational

· £75 million fixed price, fixed term EPC contract awarded to GR Engineering Services (ASX: GNG) for the design and construction of the process plant;

· £85 million Mining Services contract awarded to CA Blackwell Ltd to mine the open pit and build the mine waste facility;

· All major permits to proceed with development have been received; and

· The properties to be acquired as a condition of the Planning Permission have all been purchased.

 

Wolf is now finalising the arrangements to complete project funding in parallel with project site activities.

 

Project Timetable

The Project remains on schedule to commence earthworks this month with construction scheduled to commence during Q2 2014. First production is timetabled for the second half of 2015.

 

An indicative timeline of activity through to production is available in an updated presentation, on the Company's website.

 

Capital Costs

Since announcing the positive results of the DFS in May 2011, detailed design for the Project has been undertaken. The capital costs for a 3 million tonne per annum project have been updated to reflect this detailed design work and to account for any variance in costs in the period of time since the initial costs were estimated in the DFS.

 

The updated capital cost of the project totals £123.2 million. A breakdown of the updated costs is made up as follows:

 

Item

£ M

Process Plant

73.4

Infrastructure

13.4

Land and property purchases

13.7

Owners Costs

15.7

Contingency

7.0

Total

123.2

  

 

As at 1 December 2013 there were £106.7 million of capital costs remaining.

 

It is important to note that the EPC contract which Wolf has for the construction of the process plant is a fixed price and fixed construction term contract of 24 months from date of commencement (June 2013). In addition, the properties to be acquired as a condition of the Planning Permission have all been purchased.

 

Financing

Wolf is also obligated to fund certain bonds, over-run facilities, debt service reserve account and producer shortfall guarantees as required under the project finance facilities. These are currently estimated as follows:

£m

Project Bond (excess above bank facility)

5.0

Debt Service Reserve Account

8.2

Cost Over-run Account

10.5

Producer Shortfall Guarantee

3.0

Lee Moor Road bond

2.7

Total

29.4

  

Funding of these facilities will be managed through cash or letter of credit facilities, or a combination, and has yet to be finalised.

 

The US$75 million Bridge Finance Facility ("RCF Bridge Finance Facility"), secured on the Company's Hemerdon Project, is due to repaid by 7 June 2014. First draw-down of the Senior Project Finance Facilities of £75 million is subject to completion of conditions precedent (many of which have already been satisfied) customary for a financing of this nature including repayment of the RCF Bridge Finance Facility.

 

Operating Costs

As previously reported, the Company has appointed a mining contractor, an EPC contractor and has also recruited a local management team. With these key components now in place, the Project's operating costs have also been updated from those reported in the DFS to reflect current costings.

 

The updated average C1 cash cost for the operation is US$109 per mtu tungsten (mtu = metric tonne unit = 10kg).

 

Note: C1 cash costs: The costs of mining, milling and concentrating, onsite administration and general expenses, property and production royalties not related to revenues or profits, metal concentrate treatment charges, and freight and marketing costs less the net value of the by-product credits.

 

Tungsten Market

The Tungsten market has strengthened since the release of the DFS with growth occurring in all major regions around the globe. Since 2011, some of the potential future producers of new tungsten expected to come on-line have not materialised due to technical and financing challenges. This may result in demand for tungsten outstripping supply in the short to medium term, and is expected to coincide with the scheduled commencement of production at Hemerdon, in mid-2015.

 

The forecast prices for tungsten that Wolf used in the DFS have undergone independent review resulting in an increase through the life of the project and are shown below.

 

Year

2013

2014

2015

2016

2017

2018+

Real (2012) APT price forecast - US$/mtu

375

428

471

481

446

466

 

 

The 2011 DFS study used an APT price of US$360/mtu.

 

Wolf Minerals' Managing Director, Russell Clark, said:

 

"During 2013 the Company worked through the numerous financing, permitting, property purchases and lease negotiations with great success. With these critical aspects now complete, our focus in 2014 is to construct the project and ensure that funds are in place to support construction in-line with our timeline for the commencement of production in 2015. The review of capital and operating costs, combined with the updated tungsten price forecasts have reaffirmed the Board's view that the project remains financially attractive and provides confidence to embark on the construction program. The forecast imbalance between tungsten supply and demand in the short to medium term may lead to an increase in tungsten prices, and is expected to coincide with the commencement of production at Hemerdon. "

 

ENDS

 

About Wolf Minerals

 

Wolf Minerals is a dual listed (ASX: WLF, AIM: WLFE) specialty metals company. With global demand for tungsten rising and future global production expected to be constrained, Wolf Minerals is developing the third largest global tungsten resource at its Hemerdon project, located in the South West of England. The Company has strong cornerstone investors and project finance and environmental permitting in place. Wolf has also secured all major contracts for the project, with GR Engineering appointed the EPC contractor and CA Blackwell being awarded the Mining contract. Production is expected to commence in mid-2015, and the project will produce approximately 3,500 tonnes of tungsten in concentrate and 450 tonnes of tin in concentrate per annum. Offtake contracts are also in place.

 

 

 

For further details, please contact:

Wolf Minerals Limited

Russell Clark

+61 8 6364 3776

Investec

Chris Sim/George Price/David Anderson

+44 (0) 20 7597 4000

 

Newgate Threadneedle

Graham Herring

+44 (0) 20 7653 9850

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCGCGDBLBBBGSR
Date   Source Headline
4th May 20167:00 amRNSAppendix 3B
4th May 20167:00 amRNSCleansing Notice Letter to ASX Under Section 708A
28th Apr 20167:00 amRNSAppendix 5B
28th Apr 20167:00 amRNSQuarterly Activities Report
22nd Apr 20167:00 amRNSStandby Subscription Facility Approved
22nd Apr 20167:00 amRNSResults of General Meeting
6th Apr 20167:00 amRNSWolf Announces New General Manager
21st Mar 20167:00 amRNSGrant of ASX Listing Rule Waivers
21st Mar 20167:00 amRNSNotice of General Meeting
14th Mar 20168:10 amRNSPublication of Interim Financial Statements
9th Mar 20167:00 amRNSWaivers on Senior Debt Facilities
3rd Mar 201611:12 amRNSInitiation Research from QuotedData
8th Feb 20169:14 amRNSExpiry of Unlisted Options
5th Feb 20167:00 amRNSCessation of Alternate Director
5th Feb 20167:00 amRNSAppendix 3Z
29th Jan 20167:00 amRNSAppendix 5B
29th Jan 20167:00 amRNSQuarterly Activities Report
29th Jan 20167:00 amRNSEstablishment of £25m equity facility with RCF
12th Jan 20167:00 amRNSRevised Securities Trading Policy
8th Jan 20167:03 amRNSAppendix 3Y
8th Jan 20167:00 amRNSAppendix 3Y
8th Jan 20167:00 amRNSAppendix 3Y
8th Jan 20167:00 amRNSAppendix 3Y
8th Jan 20167:00 amRNSAppendix 3B
8th Jan 20167:00 amRNSCleansing Notice Letter to ASX
20th Nov 20157:00 amRNSAppendix 3Y
20th Nov 20157:00 amRNSAppendix 3Y
20th Nov 20157:00 amRNSAppendix 3Y
20th Nov 20157:00 amRNSAppendix 3Y
20th Nov 20157:00 amRNSAppendix 3Y
20th Nov 20157:00 amRNSIssue of Equity
20th Nov 20157:00 amRNSAppendix 3B
16th Nov 20159:02 amRNSResults of 2015 Annual General Meeting
10th Nov 20157:00 amRNSInvestor Conference Call
28th Oct 20157:00 amRNSAppendix 5B
28th Oct 20157:00 amRNSQuarterly Activities Report
8th Oct 20157:00 amRNSNotice of Annual General Meeting
23rd Sep 20157:00 amRNSCommissioning Complete at Hemerdon Project
18th Sep 20157:00 amRNSOfficial Opening of Hemerdon Project
17th Sep 20158:52 amRNSAppendix 4G
17th Sep 20158:52 amRNSCORPORATE GOVERNANCE STATEMENT
17th Sep 20158:52 amRNSAnnual Report
1st Sep 20157:03 amRNSFirst Tungsten Conc Produced at Hemerdon Project
4th Aug 20157:00 amRNSPublication of Updated Investor Presentation
30th Jul 20157:00 amRNSAppendix 5B
30th Jul 20157:00 amRNSQuarterly Activities Report
1st Jul 201510:35 amRNSAppendix 3Y
1st Jul 201510:35 amRNSAppendix 3B
1st Jul 201510:35 amRNSCleansing Notice Letter to ASX
1st Jul 201510:35 amRNSAppendix 3Y

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.