Construction complete at ENVIA's GTL plant

21 Sep 2016 07:00

RNS Number : 3801K
Velocys PLC
21 September 2016
 

News release

Velocys plc

("Velocys" or the "Company")

This announcement contains price sensitive information.

21st September 2016

 

Construction complete at ENVIA's GTL plant

Velocys plc (VLS.L), the company at the forefront of smaller scale gas-to-liquids (GTL), is pleased to announce that construction of ENVIA Energy's GTL plant in Oklahoma City is now complete. On-site loading of catalyst into the Fischer-Tropsch reactors has been completed by Velocys with support from its internationally-recognised partner, Mourik. Photographs of recent progress on site are available at www.velocys.com/media_image_library.php.

 

Highlights:

· Construction of ENVIA Energy's GTL plant in Oklahoma City complete.

· On-site loading of catalyst into Velocys reactors complete.

· Pre-commissioning activities substantially complete.

· Early commissioning steps begun.

· ENVIA GTL plant provides a commercial reference site for the Velocys technology.

· Drawdown of Velocys' US$9 million senior loan to begin in Q4 2016.

 

Pre-commissioning work, including hydro-testing of the lines and vessels, and a rigorous inspection process, is substantially complete. The team has made extensive and detailed preparations; operating manuals and procedures have been completed and robust commissioning and start-up plans are in place. In line with best practice, the commissioning plan will ensure that each process system in sequence is working robustly, safely, and within specification, in order to best assure a successful, safe and uneventful plant start up. Early commissioning steps have begun.

 

In February 2016, as part of a stakeholder capital contribution, Velocys made available to ENVIA a senior loan of US$9 million, secured on the project. Additional equity ownership units and voting rights were granted to the Company as part of the terms of the loan agreement and Velocys sought and gained greater operational management involvement in the project.

 

Velocys has been supporting the EPC contractor, Ventech, in leading and executing the planning for the commissioning, start-up and operation of the plant. For example, the Company has provided, under contract, an operability review, operating procedures and commissioning management.

 

Additionally, under the secondment agreement with ENVIA, Velocys' team of experienced GTL operations managers, operators and engineers have been on site in Oklahoma City since their deployment began in July. This Velocys operations team, which is serving under the ENVIA Plant Manager, will bring essential support to the ENVIA team through commissioning, start-up and early stage operations until the permanent operations team is phased in over a planned period. The Velocys team brings a wealth of operational GTL plant expertise including commissioning and plant performance optimisation, drawing on experience gained at a number of large scale commercial GTL projects as well as from the Velocys pilot plant.

Drawdown on the loan to ENVIA will begin in Q4 2016, with the final drawdown expected in Q1 2017. The majority of the drawdown will fall in the current financial year. Velocys will pursue options for the early repayment of the loan once the plant is operational. The Company does not currently anticipate any additional funding needs from Velocys for the project.

 

Evaluation continues, with our partners, on future ENVIA projects using learnings from the Oklahoma City project.

 

David Pummell, CEO of Velocys, said:

"Operational start-up of the ENVIA plant is now within sight; its successful steady state operation will represent the next seminal milestone for Velocys and a significant step for the smaller scale GTL industry. Velocys and its partners continue to work together on site in a high-performing professional collaboration and I remain confident that we will continue to build on this progress to deliver a safe and successful start-up of the plant in the near future, and the timely production of in-specification product."

 

- Ends -

 

For further information, please contact:

Velocys

David Pummell, CEO

Susan Robertson, CFO

 

+44 1235 841 700

 

Numis Securities (Nomad and Broker)

Alex Ham

Stuart Skinner

Jamie Lillywhite

+44 20 7260 1000

 

 

Camarco (financial communications & PR)

Billy Clegg

Georgia Mann

+44 20 3757 4983

 

Notes to editors

About Velocys

Velocys is the company at the forefront of smaller scale gas-to-liquids (GTL) that turns natural gas or biomass into premium products such as diesel, jet fuel, waxes and base oils. Smaller scale GTL adds value to a range of gas and biomass resources, and makes stranded or flared gas economic - an untapped market of up to 25 million barrels per day.

 

Velocys technology, protected by several hundred patents in over 30 countries, is specifically designed for smaller scales, combining super-active catalysts with intensified reactor systems. The Company's standardised modular plants are easier to ship and faster to install, at lower risk, even in the most remote or challenging locations. Together with world-class partners, Velocys works flexibly to unlock gas resources of 15,000 to 150,000 mmbtu per day, allowing more companies to take advantage of more opportunities.

 

Velocys plc is listed on the AIM market of the London Stock Exchange (LSE: VLS). The Company has a strong, multi-disciplinary staff operating from its commercial centre in Houston, Texas, USA and technical facilities near Oxford, UK and Columbus, Ohio, USA. Construction is complete at its commercial reference plant, which is located adjacent to Waste Management's East Oak landfill site in Oklahoma City.

 

www.velocys.com

 

Think Smaller. Velocys is changing the way fuels are made.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCSEDFASFMSEDU
Date   Source Headline
18th Jan 20247:00 amRNSCancellation - Velocys Plc
17th Jan 202412:26 pmRNSScheme of Arrangement becomes Effective
17th Jan 202411:16 amRNSForm 8.5 (EPT/RI)
17th Jan 20247:30 amRNSSuspension - Velocys plc
16th Jan 202411:45 amRNSForm 8.5 (EPT/RI)
15th Jan 202410:55 amRNSForm 8.5 (EPT/RI)
15th Jan 20249:28 amGNWForm 8.5 (EPT/RI) - Velocys Plc
12th Jan 20241:15 pmRNSCourt sanction of the Scheme of Arrangement
12th Jan 202411:27 amRNSForm 8.5 (EPT/RI)
12th Jan 20248:14 amGNWForm 8.5 (EPT/RI) - Velocys Plc
11th Jan 20249:31 amRNSForm 8.5 (EPT/RI)
11th Jan 20248:13 amGNWForm 8.5 (EPT/RI) - Velocys Plc
10th Jan 20245:45 pmRNSVelocys
10th Jan 20249:38 amRNSForm 8.5 (EPT/RI)
10th Jan 20249:37 amGNWForm 8.5 (EPT/RI) - Velocys Plc
9th Jan 20249:31 amRNSForm 8.5 (EPT/RI)
8th Jan 20246:04 pmRNSBlock listing Interim Review
8th Jan 20245:03 pmRNSResult of Court Meeting and General Meeting
8th Jan 20249:34 amRNSForm 8.5 (EPT/RI)
8th Jan 20248:18 amGNWForm 8.5 (EPT/RI) - Velocys Plc
5th Jan 202411:01 amRNSForm 8.5 (EPT/RI)
5th Jan 20249:29 amGNWForm 8.5 (EPT/RI) - Velocys Plc
4th Jan 202410:06 amGNWForm 8.5 (EPT/RI) - Velocys Plc
4th Jan 20249:58 amRNSForm 8.5 (EPT/RI)
3rd Jan 202410:55 amRNSForm 8.3 - Velocys plc
3rd Jan 202410:13 amRNSForm 8.5 (EPT/RI)
3rd Jan 20248:14 amGNWForm 8.5 (EPT/RI) - Velocys Plc
2nd Jan 20248:44 amRNSForm 8.5 (EPT/RI)
2nd Jan 20248:15 amGNWForm 8.5 (EPT/RI) - Velocys Plc
29th Dec 20239:30 amRNSForm 8.5 (EPT/RI)
29th Dec 20239:14 amGNWForm 8.5 (EPT/RI) - Velocys Plc
28th Dec 20239:33 amRNSForm 8.5 (EPT/RI)
28th Dec 20238:56 amGNWForm 8.5 (EPT/RI) - Velocys Plc
27th Dec 20239:22 amRNSForm 8.5 (EPT/RI)
27th Dec 20237:58 amGNWForm 8.5 (EPT/RI) - Velocys Plc
22nd Dec 20239:33 amRNSForm 8.5 (EPT/RI)
22nd Dec 20238:50 amRNSForm 8.3 - Velocys plc
22nd Dec 20237:39 amGNWForm 8.5 (EPT/RI) - Velocys Plc
21st Dec 202311:54 amRNSForm 8.5 (EPT/RI)
21st Dec 202310:27 amRNSForm 8.3 - Velocys plc
21st Dec 20239:29 amGNWForm 8.5 (EPT/RI) - Velocys Plc
20th Dec 202311:06 amRNSForm 8.5 (EPT/RI)
20th Dec 20238:13 amGNWForm 8.5 (EPT/RI) - Velocys Plc
19th Dec 202311:56 amRNSForm 8.5 (EPT/RI)
19th Dec 202310:18 amRNSForm 8.3 - Velocys plc
19th Dec 20237:54 amGNWForm 8.5 (EPT/RI) - Velocys Plc
18th Dec 20239:59 amGNWForm 8.5 (EPT/RI) - Velocys Plc
18th Dec 20239:42 amRNSForm 8.5 (EPT/RI)
15th Dec 202311:13 amRNSForm 8.3 - Velocys plc
15th Dec 20239:52 amRNSForm 8.5 (EPT/RI)

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.