Drilling programme update

Range is pleased to advise that it has finalised the drilling schedule with LandOcean for the next 22 development and exploration wells, as summarised in the table below. This schedule complements the work programme released on 7 August 2015.

Proposed Well

Well Location

Target Depth (ft.)

Target Horizon

Drilling Rig

Proposed Spud Date

GY 161S (development)

Beach Marcelle

1,840

Middle Gros Morne

Rental Rig 1

Q3 2015

MD 42N (development)

Morne Diablo

3,000

Upper Cruse and Middle Cruse

Rig 2

Q3 2015

Canari North (exploration)*

Guayaguayare (Shallow)

5,000

Lower Gros Morne

Rig 8

Q3 2015

QUN 16R (development)

Morne Diablo

1,800

Upper Cruse

Rig 2

Q3 2015

GY 180SE (development)*

Beach Marcelle

1,820

Lower Gros Morne

Rental Rig 1

Q4 2015

QUN 39-2 (development)

Morne Diablo

4,350

Middle Cruse

Rig 8

Q4 2015

MD 51-2 (development)

Morne Diablo

3,750

Middle Cruse

New Rig (4,000 m)

Q4 2015

GY 68 NW (development)

Beach Marcelle

1,467

Middle Gros Morne

Rental Rig 1

Q4 2015

QUN 158 redrill (development)

Morne Diablo

2,000

Upper Cruse

Rig 2

Q4 2015

MD 51-3 (development)

Morne Diablo

3,850

Middle Cruse

New Rig (4,000 m)

Q4 2015

GY 180 NW (development)

Beach Marcelle

4,000

Middle Gros Morne

New Rig (2,000 m)

Q4 2015

QUN 15 outstep (development)

Morne Diablo

3,000

Upper Cruse

New Rig (1,500 m)

Q4 2015

SQ 1 (development)

South Quarry

2,000

Q19 Sands

Rental Rig 1

Q4 2015

GY 180 SW (development)

Beach Marcelle

1,870

Middle Gros Morne

New Rig (1,000 m)

Q1 2016

Calyx 40 RD (development)

Morne Diablo

700

Forest

Rental Rig 1

Q1 2016

QUN 16 outstep (development)

Morne Diablo

1,800

Upper Cruse

Rig 2

Q1 2016

QUN 39-1 (development)

Morne Diablo

6,100

Middle Cruse

New Rig (4,000 m)

Q1 2016

GY 218 SE (development)

Beach Marcelle

4,500

Lower Gros Morne

New Rig (2,000 m)

Q1 2016

LD 3 (development)

Morne Diablo

2,500

Upper Cruse

New Rig (1,500 m)

Q1 2016

SQ 2 (development)

South Quarry

2,000

Q19 Sands

Rental Rig 1

Q1 2016

GY 150 SE (development)

Beach Marcelle

1,850

Middle Gros Morne

New Rig (1,000 m)

Q1 2016

SQ 3 (development)

South Quarry

2,000

Q19 Sands

Rental Rig 1

Q1 2016

 

Drilling Schedule

 

*Please note proposed spud dates for the Canari North and the GY 180SE wells have changed to Q3 and Q4 2015, respectively.

 

It is expected that the proposed 22 wells will be drilled by the end of Q1 2016, however certain drilling logistics are beyond the Company's control and, therefore, the drilling schedule remains subject to a number of variables, including availability of suitable rigs, arrival and commissioning of new rigs into RRDSL's rig fleet, various regulatory approvals, and the construction of drilling pads. RRDSL will also be required to recruit additional drilling staff to operate the new rigs.

The Company has been granted permission to construct 15 drilling pads. Construction of the drilling pads for the wells GY 161S, MD 42N, Canari North, GY 180SE and QUN 158 redrill has been completed. Contracts for land work and construction of the remaining 7 locations are currently being negotiated.

The GY 161S well is expected to spud once the rental rig has been contracted, and the MD 42N well will spud once rig 2 inspections are completed.

The Company also continues to prepare for spudding of its first exploration well, Canari North, located on the Guayaguayare Block. The well is expected to spud once rig 8 repairs are completed. The required pre-spud meeting and inspections will be held once the rig is ready to drill. The drilling the well on paper (DWOP) meeting was successfully held on 16 July 2015.

The Canari North well approval is currently valid until 7 September 2015, which was extended from 7 June 2015, and Range plans to seek an extension to that date should rig 8 not be operational by that time.

The management believes that the 22 well programme presents an ambitious target, given a number of challenges that need to be overcome. However, the management will spare no effort to achieve and deliver on its targets, in order to grow production and turn the Company around. Range is committed to provide all the required assistance to RRDSL to complete the proposed work programme.

The Company will continue to provide regular updates to the market on the progress of its operations.

Drilling fleet

As advised by RRDSL, the status of the drilling rigs is as follows:

Rig

Status

Rig 2

The rig is on location at MD 42N development well. Drilling of the well is estimated to commence once inspection of the rig is completed (expected late August)

Rig 6

Continue planned maintenance upgrades, following the incident in May.

RRDSL will evaluate the feasibility of re-introducing the rig into drilling operations, once the inspections are finalised. In the event that it is considered not feasible to use the rig for drilling purposes, the rig will be used for workover operations

Rig 8

Continue mast and crown repairs (expected during September)

Rental Rig 1

The contract for the rig is still being negotiated. The delay in finding a suitable rig has been due to a limited availability of mid-size rigs in Trinidad

New Rig (4,000m)

Expected to arrive in Trinidad during the week. The customs clearance documents are currently being prepared ahead of the arrival. The rig is expected to be available for drilling from October 2015, subject to government and regulatory approvals

New Rigs (2,000m,1,500m, 1,000 m)

On route to Trinidad, expected to arrive in early October and be available for drilling during Q4 2015, subject to government and regulatory approvals

 

*Rigs 1 and 5 are not included in the table above as those rigs will not be used for drilling operations in the near term.

Guayaguayare block

Range is pleased to advise that consent has been obtained from the Minister of Energy and Energy Affairs of Trinidad and Tobago and the other partners in the block, Niko Resources Ltd. ("Niko") and Petrotrin, for the assignment of Niko's partial interest as contemplated in the original farm-in transaction entered into in December 2013. Therefore, Range now holds a 40% interest in the Deep Production Sharing Contract ("PSC") and a 32.5% interest in the Shallow PSC. In addition, Range has been appointed as the Operator of the block.

As announced on 21 May 2015, Range signed an amendment agreement to acquire the full remaining interest of Niko in the block. Range has applied for the approvals to transfer the remaining interest and for the extension of the PSCs and hopes to receive these shortly. Following completion of the agreement, Range will hold an 80% interest in the Deep PSC and a 65% interest in the Shallow PSC.

Waterflood programme

The Company has submitted applications for necessary government and regulatory approvals for Morne Diablo waterflooding and will be submitting approvals for Beach Marcelle during this week. Once approvals are in place, the Company looks forward to sharing further details on the waterflood programmes and the benefits of LandOcean's detailed work and studies completed on the projects as part of purchase order 1.

Management changes

Range advises that Mr. Yan Liu, currently Chief Executive Officer of the Company, will be extending his role to that of Trinidad General Manager, focusing on managing the Trinidad business, growing production and driving profitability.

Mr. Walter Cukavac (previously, Trinidad Chief Operations Officer) has been appointed as Trinidad Director of Operations, responsible for overseeing the Health, Safety and Environment functions, government communications, managing production, and other oilfield support activities.

These changes are effective immediately.

 

Contact Details

 

 

Range Resources Limited

Evgenia Bezruchko (Investor Relations)

e. admin@rangeresources.co.uk

t. +44 (0)20 7520 9486

Cantor Fitzgerald Europe (Nominated Advisor and Broker)

David Porter / Sarah Wharry (Corporate Finance)

Richard Redmayne (Corporate Broking)

t. +44 (0)20 7894 700

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLLFFLFTEIVFIE
Date   Source Headline
25th Feb 20117:47 amPRNUpdate on Texas Activities
16th Feb 20118:10 amPRNRig Secured for Georgian Drilling
15th Feb 20119:16 amPRNCommencement of Texas Frac/Stimulation Program
11th Feb 20117:00 amPRNASX Price Query
8th Feb 20117:00 amPRNResults of Georgian Helium Survey
4th Feb 20117:00 amPRNFrac Operations Begin on Russell Bevly and EC
3rd Feb 20117:00 amPRNRed Emperor Offer to Range Shareholders
31st Jan 20117:06 amPRNDec 10 Quarterly Activities & Cashflow Report
27th Jan 20119:04 amPRNAdmission of Shares on AIM
27th Jan 20117:26 amPRNPart Carried on 2nd P'land Well, Finance Facility and 3B
18th Jan 20117:00 amRNSHalf Yearly Report
17th Jan 20112:35 pmPRNExtension of Puntland PSA's
14th Jan 20117:00 amPRNAppendix 3B
11th Jan 20117:00 amPRNIncreased Stake in East Cotton Valley
10th Jan 20118:00 amPRNFarm out of 10% of Georgian Interests
7th Jan 20117:00 amPRNAppendix 3B
6th Jan 20117:00 amPRNRange Inclusion in FTSE AIM All Share Index
5th Jan 20117:00 amPRNASX Price and Volume Query
29th Dec 20107:00 amRNSChange of Adviser
23rd Dec 20107:00 amPRNCompany's Securities Trading Policy
13th Dec 20107:34 amPRNAppendix 3B
29th Nov 20108:05 amPRNResult of AGM
29th Nov 20107:00 amPRNCommencement of Activities in Georgia
24th Nov 20108:13 amPRNAppendix 3B
18th Nov 20107:02 amPRNGeorgian Seismic Review Results
1st Nov 20104:35 pmRNSPrice Monitoring Extension
29th Oct 20109:57 amPRNNotice of Annual General Meeting and Annual Report
29th Oct 20109:08 amPRNQuarterly Activities and Cashflow Report
26th Oct 20109:58 amPRNAppendix 3B
8th Oct 20108:08 amPRNRange Proven (P1) Texas Reserves Up 67%
1st Oct 20107:00 amPRNAnnual Financial Report
21st Sep 20108:44 amPRNAppendix 3B
15th Sep 20104:22 pmRNSResult of AGM
2nd Sep 20107:00 amPRNTexas Update - Russell Bevly First Production
26th Aug 20105:05 pmRNSPosting of Annual Report & Div Timetable - Replace
25th Aug 201010:45 amPRNCompany Presentation and Appendix 3B
25th Aug 20107:00 amRNSPosting of Annual Report and Dividend Timetable
18th Aug 201010:46 amPRNChange of Registered Office
11th Aug 201011:35 amRNSLong Term Incentive Plan
11th Aug 20107:00 amRNSFinal Results
4th Aug 201010:03 amPRNAppendix 3B
4th Aug 201010:03 amPRNAppendix 3B
2nd Aug 20107:56 amPRNQuarterly Activities and Cashflow Report
2nd Aug 20107:56 amPRNQuarterly Activities and Cashflow Report
21st Jul 20109:33 amPRNIssue of Equity
12th Jul 20108:07 amPRNOnshore Trinidad Acquisition
2nd Jul 20109:24 amPRNAllotment of Placing Shares
30th Jun 20107:00 amPRNRB 1 Well Confirms North Chapman Ranch Discovery
29th Jun 20107:00 amPRNReserves and Valuation at East Cotton Valley
28th Jun 20107:21 amPRNTexas Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.