Reduction in Gangama Dry Mining project cost

6 Aug 2013 07:00

RNS Number : 0033L
Sierra Rutile Limited
06 August 2013
 

 

Sierra Rutile Limited

Sierra Rutile reduces Gangama Dry Mining project capital cost by over 17%

Significant capex savings also identified for the Gbeni deposit

 

London, UK, 6 August 2013: Sierra Rutile Limited (AIM: SRX) ("Sierra Rutile") is pleased to announce a significant reduction in the Gangama Dry Mining project capital costs. In addition, given the experience in Lanti Dry Mining, Sierra Rutile will change its mining method for the Gbeni deposit from dredging to dry mining, resulting in significant capital savings.

 

Gangama Dry Mining capital cost

 

Sierra Rutile has recently completed a value-optimisation and re-costing exercise for the Gangama Dry Mining feasibility study, which has resulted in a decrease of over 17% in the capital cost to a total of US$85 million from the US$103 million anticipated in the pre-feasibility study. This re-costing exercise focused on integration of updated foreign exchange rates and steel prices into the contract, as well as optimising the work packages to leverage Sierra Rutile's existing power infrastructure.

 

Sierra Rutile is highly confident that this revised price is achievable due to its experience in building the Lanti Dry Mining project ahead of time and on budget and given that approximately 75% of the capital cost requirement, being made up of a lump-sum-turn-key ("LSTK") contract and mobile equipment procurement, is fixed.

 

Cost Area

Proportion of cost

LSTK contract - Process plant & associated infrastructure

52%

Mobile equipment

23%

Earthworks & SRL infrastructure (e.g., power supply)

14%

Other (incl. owner's team, contingency, taxes, insurance)

11%

 

Sierra Rutile continues to refine the operating costs in light of actual performance data from the Lanti Dry Mining project and these will be incorporated into the final feasibility study report that will be reviewed by the Board during the third quarter of 2013. As previously announced, any decision by the Board of Sierra Rutile to proceed will be viewed in the context of the market.

 

Gbeni mining method

 

The historical mine plan for the Lanti Dredge had envisaged that, on completion of the Lanti deposit, the dredge would move to the Gbeni deposit, requiring a move of approximately 6.8 km. This move was expected to occur in 2018. Given the long lead times required to establish a deposit for dredging, preparations for this move would be required to start in 2014 to ensure that the dredge pond is established prior to the move in 2018. The preparations, totalling approximately US$23 million, would have involved creation of canals to float the dredge to the deposit, relocation of 152 households across two villages, clearing of all vegetation over the Gbeni deposit and creation of dams and a dredge pond.

 

Following the successful ramp-up of the Lanti Dry Mining project and having fully evaluated the risk and cost of the potential move, Sierra Rutile has concluded that the mining of the Gbeni deposit by dry mining methods and processing the ore through the existing Lanti Dry Mining processing plant, located approximately 2.5 km from the Gbeni deposit, is a superior solution to mining the Gbeni deposit with the Lanti Dredge. This change in mining method will result in a significantly lower capital profile over the next four-years, extend the useful life of the Lanti Dry Mining process plant, in its current location, from 5 to 15 years and allow Sierra Rutile to optimise its ore blend and better manage its dry mining haulage fleet to maximise its return from the Lanti Dry Mining processing plant. Additionally, this change in mining method will also result in significantly lower sustaining business capital requirements over the next five-years for the 35-year-old Lanti Dredge.

 

The Lanti Dredge, first commissioned in 1979, is expected to retire on conclusion of the Lanti deposit after which serviceable parts will be used, as appropriate, in other areas of the operation, such as Sembehun.

 

With the now-expanded dry mining resource, Sierra Rutile continues to review the potential for expanding the Lanti Dry Mining plant to greater than 500 tonnes per hour. Given the 12-month implementation of additional dry mining processing capacity, a decision will not need to be made until 2016 earliest.

 

Commenting on the revision to the Gangama capital costs and the capex savings on the Gbeni deposit, CEO John Sisay said: "With our continued focus on costs and disciplined investment, we are pleased by the outcome of both the Gangama value optimisation study and Gbeni mining method review. These reviews have resulted in the elimination of a significant amount of near-term capital requirements while at the same time maintaining our optionality around the growth of the business. This result provides the Board of Sierra Rutile with a number of options, including returning cash to shareholders."

 

ENDS

For Further Information:

Sierra Rutile Limited

Yves Ilunga

Chief Financial Officer

 

 

+44 (0)20 7074 1800

RBC Capital Markets

Nominated Adviser and Joint Corporate Broker

Martin Eales / Jonny Hardy

 

 

+44 (0)20 7653 4000

Mirabaud Securities

Joint Corporate Broker

Peter Krens

 

 

+44 (0)20 7321 2508

Kreab Gavin Anderson

Marc Cohen / Christina Clark

 

+44 (0)20 7074 1800

 

 

Notes to Editors

 

About Sierra Rutile Limited

 

Sierra Rutile produces titanium feedstock industrial minerals (primarily rutile, with some associated ilmenite), as well as smaller quantities of zircon. Sierra Rutile's mine, located in the south west of Sierra Leone, is one of the largest natural rutile deposits in the world, with a JORC-Compliant Mineral Resource for measured, indicated and inferred resources for the Sierra Rutile mine of over 800 million tonnes (as at 31 August 2012).

www.sierra-rutile.com

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUVOKROWAWRAR
Date   Source Headline
3rd Mar 201112:59 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
3rd Mar 201110:27 amRNSRare earth mineralization confirmed at SRL
1st Mar 201110:36 amRNSAdmission of Placing Shares & Total Voting Rights
23rd Feb 20117:00 amRNSPlacing to raise approximately £11.4 million
22nd Feb 20114:21 pmRNSResource upgrade & Rare Earth mineralisation
14th Feb 20117:00 amRNSAppointment of Chief Financial Officer
4th Feb 20117:00 amRNSNotice of Meeting and Despatch of Circular
19th Jan 20117:00 amRNSShareholder Resolutions
13th Jan 20117:00 amRNSChange in Shareholders & Shareholder Resolutions
29th Dec 20107:00 amRNSFinal Resolution of Loan Dispute with the GOSL
23rd Dec 20107:00 amRNSTrading Update and Board Change
10th Dec 201010:00 amRNSAppointment of Non-Executive Director
16th Nov 20108:50 amRNSDirectorate Change
9th Nov 20107:00 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
9th Nov 20107:00 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
5th Nov 20104:14 pmRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
14th Oct 20103:46 pmRNSAppointment of Non-Executive Director
7th Oct 20107:00 amRNSSuccessful resolution of dispute with GOSL
30th Sep 20107:00 amRNSAppointment of Non-Executive Directors
15th Sep 20103:02 pmRNSNotifiable Interests and Directorate Changes
9th Sep 20107:00 amRNSInterim Results
20th Aug 20101:32 pmRNSUpdate
10th Aug 20106:01 pmRNSAppointment of Executive Chairman
10th Jun 201012:10 pmRNSResult of AGM
10th Jun 20109:02 amRNSAGM Statement
3rd Jun 201011:00 amRNSDirectorate Change
26th May 20104:29 pmRNSPosting of Annual Report and Accounts
26th Apr 20107:00 amRNSFinal Settlement of Insurance Claims
23rd Mar 20107:00 amRNSPreliminary Results
5th Mar 20109:33 amRNSNotifiable Interest
19th Feb 20102:43 pmRNSInsurance Update
26th Jan 20107:13 amRNSAppointment of Marketing Director
26th Jan 20107:00 amRNSOperational Update
24th Dec 20097:01 amRNSInsurance Update
17th Dec 200911:52 amRNSSignificant Shareholders
23rd Nov 200910:57 amRNSHolding(s) in Company
16th Nov 20097:36 amRNSReplacement Placing to raise approx US$25.0 m
16th Nov 20097:05 amRNSPlacing to raise approximately US$25.0 Million
9th Nov 200910:52 amRNSMark Button joins Titanium Resources Group as COO
5th Oct 20097:00 amRNSDredge D2 Insurance Update
29th Sep 20097:00 amRNSNotice of Substantial Shareholding
14th Sep 20097:00 amRNSInterim Results
8th Sep 20097:00 amRNSDate of Interim Results Announcement
14th Jul 20097:00 amRNSAppointment of Arbuthnot as NOMAD
17th Jun 200912:01 pmRNSNotice of Substantial Shareholding
11th Jun 20094:12 pmRNSResult of AGM
27th May 20092:17 pmRNSPosting of Annual Report and Accounts
11th May 20095:04 pmRNSBoard Changes
20th Apr 20091:56 pmRNSBoard Changes
15th Apr 20092:11 pmRNSPositive Settlement of Dredge D2 Insurance Claims

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.