Polymetal: Q3 2019 production results

24 Oct 2019 07:01

Polymetal International plc (POLY) Polymetal: Q3 2019 production results 24-Oct-2019 / 09:00 MSK Dissemination of a Regulatory Announcement, transmitted by EQS Group. The issuer is solely responsible for the content of this announcement.


 

Release time

 

IMMEDIATE LSE, MOEX, AIX: POLY / ADR: AUCOY

Date

24 October 2019

 

Polymetal International plc

Q3 2019 production results

 

Polymetal reports solid production results for the third quarter and nine months ended September 30, 2019.

 

"Continued strong performance at Kyzyl is driving our production dynamics. We now expect to exceed our full-year production guidance", said Vitaly Nesis, Group CEO of Polymetal.

HIGHLIGHTS

In Q3, the Company's gold equivalent ("GE") production grew by 7% year-on-year to 476 Koz driven by Kyzyl contributing 94 Koz. Following the successful completion of several improvement projects, Kyzyl concentrator achieved steady-state throughput of 2.0 Mtpa, 11% above the original design. Quarterly gold production gained 13% while silver output contracted by 20% on the back of 2018 asset disposals and planned grade decline at Dukat. GE production for the first nine months of 2019 increased 16% to 1,232 Koz. Polymetal is likely to exceed its full-year production guidance of 1,550 Koz by up to 50 Koz. Q3 revenue increased by 43% to US$ 656 million on the back of higher sales volumes and prices. The seasonal gap between production and sales has been closed. The Company notes cost increases from royalties driven by commodity prices yet maintains its cost guidance for 2019: TCC of US$ 600-650/GE oz and AISC of US$ 800-850/GE oz. Net Debt of US$ 1.7 billion as of 30 September 2019 remained largely unchanged compared to 30 June 2019. The Company generated significant free cash flow and paid a regular semi-annual dividend of US$ 94 million (US$ 0.20 per share). Construction and development activities at the Nezhda and the POX-2 projects continued on schedule. In Q3, Polymetal had its ESG ratings upgraded - MSCI ESG Ratings score improved from BBB to A, and ISS-Oekom Corporate Rating was raised to C+. Furthermore, the Company was reaffirmed as a member of the Dow Jones Sustainability Index and FTSE4Good Index Series.

 

3 months ended Sep 301,

% change2

9 months ended Sep 301,

% change2

 

2019

2018

2019

2018

 

 

 

 

 

 

 

Waste mined, Mt

41.3

33.6

+23%

118.9

94.5

+26%

Underground development, km

25.9

31.2

-17%

80.2

96.8

-17%

Ore mined, Mt

4.5

3.6

+22%

13.0

10.2

+28%

Open-pit

3.4

2.5

+36%

9.9

6.7

+48%

Underground

1.1

1.2

-7%

3.1

3.5

-11%

Ore processed, Mt

3.9

4.4

-12%

11.5

11.4

+1%

Production

 

 

 

 

 

 

Gold, Koz

402

356

+13%

1,005

801

+25%

Silver, Moz

5.4

6.7

-20%

16.4

19.4

-16%

Copper, Kt

0.6

0.9

-36%

2.0

2.5

-21%

Gold equivalent, Koz3

476

447

+7%

1,232

1,066

+16%

Sales

 

 

 

 

 

 

Gold, Koz

388

321

+21%

992

766

+30%

Silver, Moz

6.1

5.3

+15%

16.4

17.4

-6%

Copper, Kt

1.0

0.5

+109%

2.0

1.9

+5%

Revenue, US$m4

656

459

+43%

1,602

1,248

+28%

Net debt, US$m5

1,702

1,700

+0%

1,702

1,518

+12%

Safety

 

 

 

 

 

 

LTIFR6

0.11

0.07

+57%

0.15

0.13

+15%

Fatalities

0

0

NA

2

1

+1

Notes: (1) Including discontinued operations.

 (2) % changes can be different from zero even when absolute numbers are unchanged because of rounding. Likewise, % changes can be equal to zero when absolute numbers differ due to the same reason. This note applies to all tables in this release.

 (3) Based on 1:80 Ag/Au, 5:1 Cu/Au, 2:1 Pb/Au and 2:1 Zn/Au conversion ratios.

 (4) Calculated based on the unaudited consolidated management accounts.

(5) Non-IFRS measure based on unaudited consolidated management accounts. Comparative information is presented for 30 June 2019 (for the three months period) and 31 December 2018 (for the nine months period).

 (6) LTIFR = lost time injury frequency rate per 200,000 hours worked.

PRODUCTION BY MINE

 

3 months

ended Sep 30,

%

change

9 months

ended Sep 30,

%

change

 

2019

2018

2019

2018

 

 

 

 

 

 

 

GOLD EQ. (KOZ)1

 

 

 

 

 

 

Kyzyl

94

10

NM

253

10

NM

Dukat

75

77

-2%

233

231

+1%

Albazino-Amursk

75

88

-15%

211

241

-12%

Omolon

49

50

-3%

148

136

+8%

Mayskoye

72

47

+52%

76

47

+62%

Varvara

37

37

-1%

113

103

+10%

Voro

28

23

+20%

85

78

+9%

Svetloye

46

59

-22%

107

112

-4%

TOTAL (continuing operations)

476

392

+21%

1,227

959

+28%

Okhotsk

-

44

NA

-

68

NA

Kapan

-

11

NA

5

38

NA

TOTAL (including discontinued operations)

476

447

+7%

1,232

1,066

+16%

Notes: (1) Based on 1:80 Ag/Au, 5:1 Cu/Au, 2:1 Pb/Au and 2:1 Zn/Au conversion ratios.

CONFERENCE CALL AND WEBCAST

Polymetal will hold a conference call and webcast on Thursday, 24 October 2019 at 12:00 London time (14:00 Moscow time).

To participate in the call, please dial:

From the UK:

+44 330 336 9411 (local access)

0800 279 7204 (toll free)

From the US:

+1 929 477 0324 (local access)

800 458 4121 (toll free)

From Russia:

+7 495 646 9190 (local access)

8 10 8002 867 5011 (toll free)

To participate from other countries, please dial any of the local access numbers listed above.

Conference code: 2360288

To participate in the webcast follow the link: https://webcasts.eqs.com/polymetal20191024. Please be prepared to introduce yourself to the moderator or register.

A recording of the call will be available immediately after the call at +44 20 7660 0134 (from the UK), +1 719 457 0820 (from the USA) and 8 10 8002 702 1012 (from Russia), access code 2360288, from 17:30 Moscow time Thursday, 24 October, till 17:30 Moscow time Thursday, 31 October, 2019. Webcast replay will be available on Polymetal's website (www.polymetalinternational.com) and at https://webcasts.eqs.com/polymetal20191024.

About Polymetal 

Polymetal International (LSE, MOEX: POLY, ADR: AUCOY) (together with its subsidiaries - "Polymetal", the "Company", or the "Group") is the top-20 global gold producer and top-5 global silver producer with assets in Russia and Kazakhstan. The Company combines strong growth with a robust dividend yield.

Enquiries

Media   Investor Relations

FTI Consulting

Leonid Fink

Viktor Pomichal

+44 20 3727 1000

Polymetal

Evgeny Monakhov

Timofey Kulakov

Kirill Kuznetsov

ir@polymetalinternational.com

+44 20 7887 1475 (UK)

 

+7 812 334 3666 (Russia)

Joint Corporate Brokers  

Morgan Stanley

Andrew Foster

Richard Brown

Panmure Gordon

Charles Lesser

James Stearns

+44 20 7425 8000

 

 

 

+44 20 7886 2500

RBC Europe Limited

Marcus Jackson

Jamil Miah

+44 20 7653 4000

 

Forward-looking statements

This release may include statements that are, or may be deemed to be, "forward-looking statements". These forward-looking statements speak only as at the date of this release. These forward-looking statements can be identified by the use of forward-looking terminology, including the words "targets", "believes", "expects", "aims", "intends", "will", "may", "anticipates", "would", "could" or "should" or similar expressions or, in each case their negative or other variations or by discussion of strategies, plans, objectives, goals, future events or intentions. These forward-looking statements all include matters that are not historical facts. By their nature, such forward-looking statements involve known and unknown risks, uncertainties and other important factors beyond the company's control that could cause the actual results, performance or achievements of the company to be materially different from future results, performance or achievements expressed or implied by such forward-looking statements. Such forward-looking statements are based on numerous assumptions regarding the company's present and future business strategies and the environment in which the company will operate in the future. Forward-looking statements are not guarantees of future performance. There are many factors that could cause the company's actual results, performance or achievements to differ materially from those expressed in such forward-looking statements. The company expressly disclaims any obligation or undertaking to disseminate any updates or revisions to any forward-looking statements contained herein to reflect any change in the company's expectations with regard thereto or any change in events, conditions or circumstances on which any such statements are based.

 

KYZYL

 

3 months ended Sep 30,

%

change

9 months ended Sep 30,

% change

 

2019

2018

2019

2018

MINING

 

 

 

 

 

 

Waste mined, Mt

17.5

16.1

+9%

49.9

44.8

+11%

Ore mined (open-pit), Kt

527

436

+21%

1,560

833

+87%

 

 

 

 

 

 

 

PROCESSING

 

 

 

 

 

 

Ore processed, Kt

502

362

+39%

1,490

436

NM

Gold grade, g/t

7.5

5.1

+45%

7.0

4.7

+49%

Gold recovery

88.3%

78.7%

+12%

87.7%

75.3%

+16%

Concentrate produced, Kt

31.4

20.4

+54%

89.7

21.7

NM

Concentrate gold grade, g/t

104.8

69.1

+52%

101.7

67.7

+50%

Gold in concentrate, Koz1

105.9

45.2

+134%

293.3

47.2

NM

 

 

 

 

 

 

 

Concentrate shipped, Kt

17.2

5.4

+220%

54.2

5.4

NM

Payable gold shipped, Koz

35.8

10.0

+259%

127.0

10.0

NM

 

 

 

 

 

 

 

Amursk POX

 

 

 

 

 

 

Concentrate processed, Kt

15

-

NA

35

-

NA

Gold grade, g/t

125.9

-

NA

125.3

-

NA

Gold recovery

91.7%

-

NA

92.9%

-

NA

Gold produced, Koz

58.2

-

NA

126.5

-

NA

 

 

 

 

 

 

 

TOTAL PRODUCTION

 

 

 

 

 

 

Gold, Koz

94.0

10.0

NM

253.5

10.0

NM

Note:  (1) For information only; not considered as gold produced and therefore not reflected in the table representing total production. It will be included in total production upon shipment to off-taker or dore production at Amursk POX.

Kyzyl continued to exceed budget on throughput and grade. Gold in concentrate in Q3 was 106 Koz while payable gold production amounted to 94 Koz.

Q3 is expected to be the last quarter with significant positive grade reconciliation. Starting from Q4 mining will continue beyond the near-surface area with significant high-grade lenses and the average grade will revert to open-pit reserve average.

The Chinese market for refractory concentrates is continuing to tighten. In response, the Company moved to increase the share of gold contained in low-carbon concentrate processed at Amursk POX to 70% (versus 50% planned). This drove POX recoveries lower, but will ensure higher production and lower costs at Kyzyl at the expense of reducing 3rd-party concentrate processing.

Following the successful completion of several improvement projects, Kyzyl concentrator achieved steady-state throughput of 2.0 Mtpa, 11% above the original design. Several initiatives are under way to evaluate pushing throughput to 2.1 Mtpa level by H2 2020.

Polymetal Engineering is finalizing a FS-level technical study to re-optimize the open pit under updated operational and economic assumptions. The results, including the updated Ore Reserves estimate, will be presented on November 11 at the Analyst and Investor Day.

 

 

 

DUKAT OPERATIONS

 

3 months ended Sep 30,

% change

9 months ended Sep 30,

%

change

 

2019

2018

2019

2018

MINING

 

 

 

 

 

 

 

 

 

 

 

 

 

Underground development, km

15.0

14.9

+1%

45.0

44.5

+1%

Ore mined, Kt

642

610

+5%

1,894

1,831

+3%

 

 

 

 

 

 

 

PROCESSING

 

 

 

 

 

 

Omsukchan concentrator

 

 

 

 

 

 

Ore processed, Kt

506

500

+1%

1,535

1,496

+3%

Grade

 

 

 

 

 

 

Gold, g/t

0.5

0.6

-15%

0.5

0.6

-5%

Silver, g/t

282

296

-5%

291

300

-3%

Recovery1

 

 

 

 

 

 

Gold

86.7%

87.0%

-0%

86.1%

86.8%

-1%

Silver

86.8%

88.6%

-2%

86.8%

88.2%

-2%

Production

 

 

 

 

 

 

Gold, Koz

7.2

8.2

-13%

21.6

22.5

-4%

Silver, Moz

3.9

4.0

-4%

12.1

12.4

-2%

 

Lunnoye plant

 

 

 

 

 

 

Ore processed, Kt

116

120

-3%

348

347

+0%

Grade

 

 

 

 

 

 

Gold, g/t

1.4

1.4

+1%

1.4

1.3

+9%

Silver, g/t

241

310

-22%

258

330

-22%

Recovery1

 

 

 

 

 

 

Gold

91.4%

85.7%

+7%

87.6%

85.4%

+3%

Silver

94.5%

91.4%

+3%

91.5%

91.1%

+0%

Production

 

 

 

 

 

 

Gold, Koz

4.9

4.6

+6%

14.0

12.2

+15%

Silver, Moz

0.9

1.1

-20%

2.7

3.3

-19%

 

 

 

 

 

 

 

TOTAL PRODUCTION

 

 

 

 

 

 

Gold, Koz

12.0

12.8

-6%

35.6

34.7

+3%

Silver, Moz

4.7

5.1

-8%

14.8

15.7

-6%

Note: (1) Technological recovery, includes gold and silver within work-in-progress inventory.

At Dukat, quarterly silver and gold production were down 8% and 6% year-on-year respectively. The decline was driven by the Omsukchan concentrator processing larger volumes of lower-grade ore as well as by planned reduction in silver grade at Lunnoye mostly attributable to the depletion of higher-grade Zone 9.

Given the significant increase in the silver price, management is evaluating the postponement of the mine closure at Goltsovoye by bringing marginal stopes and areas into production. Such a development will enable full utilization of the Dukat concentrator in 2020.

 

ALBAZINO

 

3 months ended Sep 30,

% change

9 months ended Sep 30,

% change

 

2019

2018

2019

2018

MINING

 

 

 

 

 

 

Albazino

 

 

 

 

 

 

Waste mined, Mt

5.7

5.5

+4%

16.8

16.0

+5%

Underground development, Km

2.9

2.2

+28%

7.7

6.9

+12%

Ore mined, Kt

571

442

+29%

1,596

1,372

+16%

Open-pit

418

348

+20%

1,184

1,062

+11%

Underground

153

94

+62%

412

310

+33%

 

 

 

 

 

 

 

PROCESSING

 

 

 

 

 

 

Albazino concentrator

 

 

 

 

 

 

Ore processed, Kt

447

431

+4%

1,303

1,291

+1%

Gold grade, g/t

4.8

5.4

-11%

4.4

5.2

-15%

Gold recovery1

86.9%

84.9%

+2%

85.9%

84.5%

+2%

Concentrate produced, Kt

36.8

36.8

-0%

106.0

105.7

+0%

Concentrate gold grade, g/t

51.0

54.1

-6%

46.6

54.3

-14%

Gold in concentrate, Koz2

60.3

64.0

-6%

158.9

184.3

-14%

 

 

 

 

 

 

 

Amursk POX

 

 

 

 

 

 

Concentrate processed, Kt

45

49

-8%

135

131

+3%

Gold grade, g/t

51.2

56.1

-9%

50.5

57.3

-12%

Gold recovery

96.5%

96.6%

-0%

95.2%

96.9%

-2%

Gold produced, Koz

74.7

87.6

-15%

211.1

240.4

-12%

 

 

 

 

 

 

 

TOTAL PRODUCTION

 

 

 

 

 

 

Gold, Koz

74.7

87.6

-15%

211.1

240.4

-12%

Notes: (1) To concentrate.

(2) For information only; not considered as gold produced and therefore not reflected in the table representing total production. Included in total production after dore production at the Amursk POX.

At Albazino, production dynamics continued to be affected by lower-grade ore from the Ekaterina-1 open pit. Quarterly production of gold in concentrate decreased by 6% year-on-year.

However, a 62% jump in underground ore mined ensured positive quarter-on-quarter grade dynamics despite challenging ground conditions thanks to careful customization of mining methods to specific stope conditions.

AMURSK POX

 

3 months ended Sep 30,

% change

9 months ended Sep 30,

% change

 

2019

2018

2019

2018

Concentrate processed, Kt

60

49

+22%

171

131

+30%

Albazino

41

44

-6%

122

115

+6%

Kyzyl

15

-

NA

35

-

NA

Mayskoye

-

1

-100%

-

1

-100%

Other1

3

5

-27%

13

16

-17%

Gold recovery

94.3%

96.6%

-2%

94.3%

96.9%

-3%

Average gold grade, g/t

70.3

56.1

+25%

66.0

57.3

+15%

Average sulphur grade

12.5%

9.3%

+34%

12.8%

8.7%

+47%

Total gold produced2, Koz

132.9

87.6

+52%

337.5

240.4

+40%

Albazino

62.5

72.2

-13%

178.5

202.7

-12%

Kyzyl

58.2

-

NA

126.5

-

NA

 Other1

12.2

15.4

-21%

32.6

37.7

-14%

Notes: (1) Veduga and purchased concentrates which are included in reportable production in the Albazino segment.

(2) For information only. Already accounted for in production at operating mines.

Q3 gold production at the Amursk POX increased by 52% year-on-year driven by the introduction of high-grade Kyzyl concentrate to the feed.

By implementing tight feed management procedures, the POX team managed to increase the recovery ratio in comparison with the previous quarter and stabilize it at the level above 94%. In Q2, the beginning of processing of large quantities of Kyzyl concentrate had significantly changed the operating parameters and led to a decline in recoveries.

Increased volumes of high-grade low-carbon Kyzyl concentrate displaced 3rd party materials.

OMOLON OPERATIONS

 

3 months ended Sep 30,

% change

9 months ended Sep 30,

% change

 

2019

2018

2019

2018

MINING

 

 

 

 

 

 

 

 

 

 

 

 

 

Waste mined, Mt

1.9

1.9

+3%

5.1

4.6

+13%

Underground development, Km

3.3

3.3

+1%

9.9

9.6

+2%

Ore mined, Kt

805

176

NM

2,183

658

NM

Open-pit

690

102

NM

1,849

400

NM

Underground

115

74

+55%

334

258

+30%

 

 

 

 

 

 

 

PROCESSING

 

 

 

 

 

 

Birkachan Heap Leach

 

 

 

 

 

 

Ore stacked, Kt

350

487

-28%

897

959

-6%

Gold grade, g/t

1.2

1.2

+4%

1.2

1.1

+5%

Gold production, Koz

9.0

8.8

+2%

11.0

9.9

+12%

 

 

 

 

 

 

 

Kubaka Mill

 

 

 

 

 

 

Ore processed, Kt

184

220

-16%

612

642

-5%

Grade

 

 

 

 

 

 

Gold, g/t

6.0

4.4

+36%

6.3

4.8

+32%

Silver, g/t

131.6

151.2

-13%

90.0

118.8

-24%

Recovery1

 

 

 

 

 

 

Gold

95.8%

95.4%

+1%

95.5%

95.4%

+0%

Silver

80.8%

89.3%

-10%

79.5%

83.0%

-4%

Gold production, Koz

32.7

29.8

+10%

119.1

99.8

+19%

Silver production, Moz

0.6

0.9

-37%

1.4

2.1

-34%

 

 

 

 

 

 

 

TOTAL PRODUCTION

 

 

 

 

 

 

Gold, Koz

41.7

38.6

+8%

130.1

109.7

+19%

Silver, Moz

0.6

0.9

-37%

1.4

2.1

-34%

Note: (1) Technological recovery, includes gold and silver within work-in-progress inventory.

At Omolon, gold output was up 8% year-on-year while silver output was down 37% as the processing plant switched away from Sopka ore towards feed from Birkachan and Olcha.

Following a successful in-fill drilling campaign, open-pit mining recommenced at the Bikarchan mine with a view to extend the operation of the heap leach facility.

Quarterly volume of ore processed at the Kubaka mill decreased by 16% year-on-year due to the planned 14-day maintenance shutdown to complete SAG headgear replacement.

 

MAYSKOYE

 

3 months ended Sep 30,

% change

9 months ended Sep 30,

% change

 

2019

2018

2019

2018

MINING

 

 

 

 

 

 

Waste mined, Mt

1.4

1.6

-13%

4.0

3.6

+12%

Underground development, km

4.7

5.4

-13%

15.5

17.6

-11%

Ore mined, Kt

199

304

-34%

638

767

-17%

Open-pit

41

150

-73%

175

282

-38%

Underground

159

154

+3%

463

485

-4%

 

 

 

 

 

 

 

PROCESSING

 

 

 

 

 

 

Ore processed, Kt

232

223

+4%

658

639

+3%

Gold grade, g/t

 6.3

9.0

-30%

 6.2

7.5

-18%

Gold recovery

84.7%

71.8%

+18%

79.5%

77.5%

+3%

Gold in concentrate, Koz2

36.3

29.3

+24%

94.9

84.3

+13%

 

 

 

 

 

 

 

Gold produced in dore from concentrate (POX), Koz

 -

0.7

-100%

 -

0.7

-100%

Gold produced in dore from carbon, Koz3

1.5

1.2

+25%

6.0

1.2

+416%

 

 

 

 

 

 

 

Payable gold in concentrate shipped to off-takers, Koz

70.3

45.3

+55%

70.3

45.3

+55%

 

 

 

 

 

 

 

TOTAL PRODUCTION

 

 

 

 

 

 

Gold, Koz

71.8

47.1

+52%

76.3

47.1

+62%

Notes: (1) To concentrate.

(2) For information only; not considered as gold produced and therefore not reflected in the table representing total production. Included in total production upon sale to off-taker or dore production at Amursk POX.

(3) Gold produced from carbon at Amursk POX.

In Q3, Mayskoye switched back to processing sulphide ore from the underground mine. Consequently, grade fell and recoveries jumped. Gold in concentrate produced increased by 24% year-on-year.

Shipments of Mayskoye concentrate to Chinese off-takers commenced with the start of navigation period in August. Payable gold in concentrate shipped was up 55% year-on-year. The Chinese concentrate market continues to be challenging with high arsenic material starting to attract heavy penalties. This is likely to have an approximately $150-200/oz negative impact on Mayskoye's TCC and AISC for 2019.

 

VARVARA

 

3 months ended Sep 30,

%

change

9 months ended Sep 30,

% change

 

2019

2018

2019

2018

MINING

 

 

 

 

 

 

Waste mined, Mt

11.4

7.2

+59%

34.1

21.9

+56%

Ore mined, Kt

1,014

888

+14%

2,953

2,274

+30%

 

 

 

 

 

 

 

PROCESSING

 

 

 

 

 

 

Flotation

 

 

 

 

 

 

Ore processed, Kt

134

116

+16%

411

296

+39%

Grade

 

 

 

 

 

 

Gold, g/t

1.3

1.4

-6%

1.2

1.3

-11%

Copper

0.37%

0.59%

-37%

0.53%

0.55%

-4%

Recovery1

 

 

 

 

 

 

Gold

52.1%

72.3%

-28%

51.3%

68.7%

-25%

Copper

91.3%

92.8%

-2%

91.4%

92.1%

-1%

Production

 

 

 

 

 

 

Gold in concentrate, Koz

2.7

3.2

-15%

7.2

7.4

-2%

Copper in concentrate, Kt

0.6

0.6

-6%

1.8

1.5

+26%

 

 

 

 

 

 

 

Veduga ore toll processed, Kt2

35

43

-18%

98

86

+14%

 

 

 

 

 

 

 

Leaching

 

 

 

 

 

 

Ore processed, Kt

733

826

-11%

2,268

2,324

-2%

Gold grade, g/t

1.6

1.3

+18%

1.5

1.4

+7%

Gold recovery1

87.4%

89.4%

-2%

86.8%

87.7%

-1%

Gold production (in dore), Koz

31.3

31.1

+1%

96.7

88.6

+9%

 

 

 

 

 

 

 

Total ore processed, Kt

902

985

-8%

2,778

2,706

+3%

 

 

 

 

 

 

 

TOTAL PRODUCTION

 

 

 

 

 

 

Gold, Koz

34.0

34.3

-1%

103.9

95.9

+8%

Copper, Kt

0.6

0.6

-6%

1.8

1.5

+26%

Notes: (1) Technological recovery, includes gold and copper within work-in-progress inventory. Does not include toll-treated ore.

(2) To be further processed at Amursk POX.

At Varvara, gold output decreased by 1% year-on-year as the leaching circuit underwent the planned replacement of the mill lining.

Gold grade processed increased thanks to higher mining and railing volumes at Komar. New company-owned loco has been successfully commissioned and is expected to further drive down Komar ore transportation costs.

 

VORO

 

3 months ended Sep 30,

% change

9 months ended Sep 30,

% change

 

2019

2018

2019

2018

MINING

 

 

 

 

 

 

 

 

 

 

 

 

 

Waste mined, Mt

0.4

0.9

-56%

1.2

2.8

-58%

Ore mined, Kt

181

204

-11%

661

779

-15%

 

 

 

 

 

 

 

PROCESSING

 

 

 

 

 

 

Voro CIP

 

 

 

 

 

 

Ore processed, Kt

264

253

+4%

783

752

+4%

Gold grade, g/t

4.0

3.6

+11%

3.7

3.9

-6%

Gold recovery1

87.0%

80.6%

+8%

86.6%

80.7%

+7%

Gold production, Koz

26.4

21.4

+23%

71.4

72.2

-1%

 

 

 

 

 

 

 

Voro Heap Leach

 

 

 

 

 

 

Ore stacked, Kt

58

60

-2%

58

62

-5%

Gold grade, g/t

1.4

1.4

+0%

1.4

1.4

+0%

Gold production, Koz

1.5

2.1

-25%

12.7

5.8

+120%

 

 

 

 

 

 

 

TOTAL PRODUCTION

 

 

 

 

 

 

Gold, Koz

28.0

23.5

+19%

84.0

77.9

+8%

Note: (1) Technological recovery, includes gold within work-in-progress inventory.

Q3 gold production at Voro climbed by 19% year-on-year as the CIP plant processed high-grade oxide ore from the southern pit.

Waste volume decreased sharply as the open pit is approaching the end of its life.

SVETLOYE

 

3 months ended Sep 30,

% change

9 months ended Sep 30,

% change

 

2019

2018

2019

2018

MINING

 

 

 

 

 

 

Waste mined, Mt

0.3

0.2

+41%

1.1

0.5

+142%

Ore mined (open-pit), Kt

406

317

+28%

1,273

978

+30%

 

 

 

 

 

 

 

PROCESSING

 

 

 

 

 

 

Ore stacked, Kt

369

491

-25%

968

1,144

-15%

Gold grade, g/t

4.1

3.8

+10%

4.0

3.8

+6%

Gold production, Koz

46.1

59.0

-22%

107.0

112.0

-4%

 

 

 

 

 

 

 

TOTAL PRODUCTION

 

 

 

 

 

 

Gold, Koz

46.1

59.0

-22%

107.0

112.0

-4%

At Svetloye, gold production contracted by 22% year-on-year as ore stacking was negatively affected by wet and cold weather in Q3.

 

DEVELOPMENT UPDATE

At Nezhda, pre-stripping and construction proceeded according to plan. Repair of the road from the Kolyma federal highway to the mine site was completed. The road is ready for the delivery of technological equipment of the plant and the power station in Q1 2020. The installation of the metal framework of the processing plant building was completed, and the manufacturing of internal metal structures is under way. The construction of foundations for the power station and the underground tunnel from the crusher to the concentrator started. The lining of the dry-stack tailings storage facility commenced.

A positive conclusion of the state environmental review of the project documentation was received.

At POX-2, the autoclave foundation boxcut was excavated and the foundation concrete bed prepared. Polymetal signed contracts for high-pressure auxiliary equipment around the autoclave through Hatch. Active construction started at the new concentrate storage area.

SUSTAINABILITY, HEALTH AND SAFETY

In Q3, our LTIFR stood at 0.11 versus 0.07 in Q3 2018 with a total of 3 work-related incidents recorded across the Group (2 incidents in Q3 2018). The increase was driven by minor incidents that occurred at remote sites outside of production shifts (falls, slips). Accordingly, risk assessment and safety training will be adjusted to take into account higher frequency of this type of incidents.

In the reporting quarter Polymetal had its ESG ratings upgraded - MSCI ESG Ratings score improved from BBB to A, and ISS-Oekom Corporate Rating was raised to C+. Furthermore, the Company was reaffirmed as a member of the Dow Jones Sustainability Index and FTSE4Good Index Series.

As a way to further align our ESG efforts to financial results, Polymetal signed a new US$ 75 million sustainability-linked credit facility with Societe Generale. The interest rate is tied to the Company's performance on specific ESG KPIs set by the agreement.

PERSONNEL

Oleg Voronin (50) was appointed as Managing Director at Albazino. Mr. Voronin graduated from the Krasnoyarsk Institute of Non-Ferrous Metal with a degree in underground mining. From 1993 until 2009 he held various positions with the Zyryanovsky mining and processing complex (now part of Kazzinc), all the way up to the chief engineer. In 2009, Oleg joined Polymetal as the chief engineer of Dukat operations. In 2015, he assumed the position of chief engineer at Albazino.


ISIN:JE00B6T5S470
Category Code:MSCH
TIDM:POLY
Sequence No.:24599
EQS News ID:895603
 
End of AnnouncementEQS News Service

UK Regulatory announcement transmitted by DGAP - a service of EQS Group AG. The issuer is solely responsible for the content of this announcement.

Date   Source Headline
10th Aug 20237:00 amEQSPolymetal: Resumption of trading on AIX
1st Aug 20236:00 pmEQSPolymetal: Suspension of Trading on the London Stock Exchange
28th Jul 20231:00 pmEQSPolymetal: Results of GM
25th Jul 20232:00 pmEQSPolymetal: Results of AGM
24th Jul 20233:00 pmEQSPolymetal: Q2 2023 production results webcast
21st Jul 20237:00 amEQSPolymetal: Update to the timetable of the Re-domiciliation
10th Jul 20234:55 pmEQSPolymetal: Proposed cancellation of listing on the Official List and from trading on the London Stock Exchange and notice of General Meeting
10th Jul 202311:30 amEQSPolymetal: Acquisition of the controlling stake in the Baksy property in Kazakhstan
10th Jul 20237:00 amEQSPolymetal: Clarification to the expected timetable of the Re-domiciliation
30th Jun 20233:00 pmEQSPolymetal: Report on payments to governments for the year 2022
29th Jun 20237:05 amEQSPolymetal: Update to the timetable of the Re-domiciliation
29th Jun 20237:00 amEQSPolymetal: Notice of 2023 AGM
19th Jun 20233:30 pmEQSPolymetal: Board changes
16th Jun 20237:01 amEQSPolymetal: Further Extension to Exchange Offer Timetable
5th Jun 20237:00 amEQSPolymetal: Update on the Company’s Russian-registered subsidiary, JSC Polymetal
30th May 20231:30 pmEQSPolymetal: Results of GM
26th May 20234:21 pmEQSPolymetal: Resignation of Bank of New York Mellon as depository bank for American Depositary Receipt programme
22nd May 20237:00 amEQSPolymetal: Update on the Russian-registered JSC Polymetal
18th May 20235:00 pmEQSPolymetal: General Meeting Voting Arrangements
16th May 20237:01 amEQSPolymetal: Circulation of General Meeting Materials
10th May 20237:01 amEQSPolymetal: Q1 2023 production results
10th May 20237:00 amEQSPolymetal: Proposed re-domiciliation to the AIFC (Кazakhstan) and notice of General Meeting
3rd May 20237:00 amEQSPolymetal: Analyst and Investor Briefing
23rd Mar 20237:00 amEQSPolymetal International plc: Integrated Annual Report 2022
16th Mar 20237:01 amEQSPolymetal: Preliminary results for the year ended 31 December 2022
16th Mar 20237:00 amEQSPolymetal: Board Committee Changes
1st Mar 20237:01 amEQSPolymetal: Ore Reserves, Mineral Resources and Exploration update as at 1 January 2023
10th Feb 20238:00 amEQSPolymetal: Statement in relation to trading of shares on the London Stock Exchange
10th Feb 20237:00 amEQSPolymetal: Statement in relation to trading of shares on the London Stock Exchange
27th Jan 20234:40 pmRNSSecond Price Monitoring Extn
27th Jan 20234:35 pmRNSPrice Monitoring Extension
25th Jan 20238:00 amEQSPolymetal: Q4 and FY 2022 production results
25th Jan 20237:00 amEQSPolymetal: Q4 and FY 2022 production results
17th Jan 20238:00 amEQSPolymetal: Analyst and Investor Day
17th Jan 20237:00 amEQSPolymetal: Analyst and Investor Day
11th Jan 20234:35 pmRNSPrice Monitoring Extension
30th Dec 20228:00 amEQSPolymetal: Total Voting Rights as at 30 December 2022
30th Dec 20227:00 amEQSPolymetal: Total Voting Rights as at 30 December 2022
12th Dec 20228:00 amEQSPolymetal: Results of the first tranche of the Exchange Offer
12th Dec 20227:00 amEQSPolymetal: Results of the first tranche of the Exchange Offer
8th Dec 20228:00 amEQSPolymetal: Extension to the settlement period in connection with the Exchange Offer
8th Dec 20227:00 amEQSPolymetal: Extension to the settlement period in connection with the Exchange Offer
1st Dec 20228:00 amEQSPolymetal: Board Changes
1st Dec 20227:00 amEQSPolymetal: Board Changes
10th Nov 20228:00 amEQSPolymetal: Board Committee Changes
10th Nov 20227:00 amEQSPolymetal: Board Committee Changes
2nd Nov 20228:00 amEQSPolymetal: Q3 2022 production results
2nd Nov 20227:00 amEQSPolymetal: Q3 2022 production results
12th Oct 20225:30 pmEQSPolymetal: Submission of resolutions to NSM
12th Oct 20225:30 pmEQSPolymetal: Submission of resolutions to NSM

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.