PROGRESS REPORT LOMADA GOLD PROJECT

18 May 2011 07:00

RNS Number : 7736G
Patagonia Gold PLC
18 May 2011
 



PATAGONIA GOLD PLC

 

 

PROGRESS REPORT

LOMADA GOLD PROJECT

SANTA CRUZ PROVINCE, ARGENTINA

 

Highlights:

 

·; Patagonia Gold Plc (PGD) is pleased to announce the successful commissioning of the the Lomada trial heap leach pad and processing facility with gold now being accumulated onto activated carbon. The project has been completed within time and budget.

 

·; Expansion of the trial heap leach pad from the current 50,000 tonnes x 6 metres high to 180,000 tonnes x 12 metres high has commenced with earthworks and liner placement completed. Ore loading and irrigation of the expansion is planned to commence Q3 2011.

 

Photographs of the above are available for viewing on our web site at www.patagoniagold.com 

 

Lomada de Leiva project:

The Lomada de Leiva gold-heap leach project (Lomada project) is located on the La Paloma property block approximately 40km to the south of the town of Perito Moreno and currently contains a Canadian National Instrument 43-101 (NI 43-101) compliant resource of 161,346 ounces of gold in the measured and indicated categories with a further inferred 73,725 ounces of gold.

 

Prior to the construction of the full Lomada project, PGD elected to construct and operate a 50,000 tonne 6 metre high trial heap leach pad to test and optimise construction methods together with the irrigation and processing facilities. Construction of the trial pad and facilities commenced in October 2010 and has been completed and successfully commissioned within time and budget.

 

The trial is now in full operation with gold being accumulated onto activated carbon. The trial is expected to yield approximately 2,500 ounces of gold in 120 days. PGD is investigating several options for the production of gold bars. This includes stripping of the above carbon to produce Dore for refining into pure gold by a third party or stockpiling the carbon until PGD has its own Gold room which is currently in the planning stage.

 

Following the successful operation of the above trial heap leach pad, PGD plans to expand the trial by raising the pad from the current 6 metres height to 12 metres to test the kinetics of the piling. This will expand the trial from 50,000 tonnes to 180,000 tonnes. The expanded trial is expected to yield approximately 8,000 ounces of gold.

 

Construction of the expansion has commenced with earthworks and liner placement completed. Ore loading and irrigation is expected to commence Q3 2011.

 

 

 

Lomada Resource Upgrade:

Patagonia Gold SA (PGSA) has recently completed an extension and infill drilling campaign, comprising 35 diamond drill holes HQ core for 4,441 metres, aimed at enlarging the resource and advancing the inferred part of the resource into an indicated category.

 

The upgraded resource, together with the results from the trial Lomada project, will be used to revise the 2009 scoping study of the Lomada project prior to the commencement of the main heap leach project.

 

Matthew Boyes, (BSC. Geology, member AusIMM) Development Manager for Patagonia Gold PGSA and a qualified person as defined in Canadian National Instrument 43-101, has reviewed and verified all scientific or technical mining disclosure contained in this press release.

 

ENDS

 

For more information, please contact:

Bill Humphries/Richard Prickett

Patagonia Gold Plc

Tel: +44(0)20 7409 7444

 

Simon Raggett / Angela Peace

Strand Hanson Ltd

Tel: +44(0)20 7409 3494

David Bick / Mark Longson

Square 1 Consulting

Tel : +44(0)20 7929 5599

 

Robin Henshall / Tim Graham

Matrix Corporate Capital LLP

Tel : +44(0)20 3206 7172 / +44(0)20 3206 7206

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLSFUFLWFFSELI
Date   Source Headline
22nd Jul 201910:30 amRNSScheme of arrangement becomes Effective
22nd Jul 20197:30 amRNSSuspension - Patagonia Gold Plc
19th Jul 20191:00 pmRNSCourt Sanction of Scheme of Arrangement
17th Jul 20195:30 pmRNSPatagonia Gold
12th Jul 201912:26 pmRNSResults of Court Meeting and General Meeting
3rd Jul 20194:30 pmRNSForm 8.3 - Hunt Mining Corp./Patagonia Gold PLC
21st Jun 20191:48 pmRNSHolding(s) in Company Patagonia Gold Plc
20th Jun 201912:00 pmRNSPublication of Scheme Document
18th Jun 20197:00 amRNSRevision to the 2018 Financial Statements
13th Jun 20194:00 pmRNSForm 8 (OPD) Hunt Mining Corp./Patagonia Gold PLC
13th Jun 20194:00 pmRNSForm 8.3 - Hunt Mining Corp./Patagonia Gold PLC
13th Jun 20194:00 pmRNSForm 8.3 - Hunt Mining Corp./Patagonia Gold PLC
13th Jun 20194:00 pmRNSForm 8.3 - Hunt Mining Corp./Patagonia Gold PLC
13th Jun 20197:00 amRNSLoan Facility Amendment
11th Jun 20193:53 pmBUSForm 8.3 - Patagonia Gold Plc
10th Jun 20197:00 amRNSForm 8 (OPD) - Patagonia Gold plc
7th Jun 20194:30 pmRNSForm 8.3 - Patagonia Gold plc
31st May 20197:15 amRNSCalcatreu and Cap Oeste Mineral Resource Update
31st May 20197:00 amRNSOffer for Patagonia Gold plc by Hunt Mining Corp.
11th Apr 20197:00 amRNSFinal Results
1st Mar 20197:00 amRNSUS$15 million Loan Agreement
27th Feb 20197:00 amRNSDrill Results Calcatreu Project in Argentina
19th Feb 20197:00 amRNSOperations Update
13th Feb 20197:00 amRNSDrill Results - San Jose Project in Uruguay
18th Jan 20191:00 pmRNSProduction Update
18th Jan 20191:00 pmRNSProduction Update
28th Dec 20187:00 amRNSAcquisition of Exploration Properties
21st Dec 20187:00 amRNSSale of COSE Royalty Update
11th Dec 20184:30 pmRNSSale of COSE Royalty
10th Oct 20187:00 amRNSCap Oeste and Calcatreu Update
25th Sep 20187:00 amRNSHalf Yearly Financial Statements
6th Sep 201810:15 amRNSArgentine Export Tax
11th Jul 20187:00 amRNSCap Oeste Production Update
8th Jun 20187:00 amRNSCap Oeste Production Update
1st Jun 20187:00 amRNSReceipt of Balance Payment of COSE
21st May 20187:00 amRNSFinal Payment of Calcatreu Project
9th May 20182:21 pmRNSResult of AGM
27th Apr 20187:00 amRNSNotice of AGM
24th Apr 20182:18 pmRNSOperations Update
12th Apr 20187:00 amRNSProposed Capital Reorganisation and Notice of AGM
12th Apr 20187:00 amRNSFinal Results
26th Mar 20187:00 amRNSOperations Update
21st Feb 20187:00 amRNSOperations Update
1st Feb 20187:00 amRNSAcquisition of Calcatreu Deposit
18th Jan 201811:00 amRNSPrice Monitoring Extension
28th Dec 20177:00 amRNSDefinitive Agreement - Calcatreu Deposit
19th Dec 20177:00 amRNSGrant of Options
11th Dec 20177:00 amRNSCalcatreu Option
7th Dec 20174:38 pmRNSResult of General Meeting and Open Offer
21st Nov 20177:00 amRNSSubscription and Open Offer

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.