The next focusIR Investor Webinar takes places on 14th May with guest speakers from Blue Whale Growth Fund, Taseko Mines, Kavango Resources and CQS Natural Resources fund. Please register here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksORM.L Regulatory News (ORM)

  • There is currently no data for ORM

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

Barruecopardo Tungsten Project Update

12 Sep 2018 07:00

RNS Number : 4679A
Ormonde Mining PLC
12 September 2018
 

12 September 2018

 

Ormonde Mining plc

 

("Ormonde" or "the Company")

 

Barruecopardo Tungsten Project Update

 

 

The Board of Ormonde ("the Board") is pleased to provide an update on the Barruecopardo Tungsten Project in Salamanca, Spain ("Barruecopardo" or "the Project"), where construction is well-advanced and commissioning activities have commenced.

 

Key progress updates include:

 

· The Project team achieved a major milestone during August with the commencement of commissioning of the turnkey crush and screen plant, the first trial of waste rock through the primary crusher having been successfully carried out;

· The construction of the rest of the crush and screen circuit is complete, and installation of the associated electrical circuitry is presently in progress and due for completion by the second half of September;

· Initial commissioning of the water treatment plant has also been carried out, and will continue on the imminent completion of the water management system pipework and pump installation to feed water from the old open pit;

· The installation of major equipment and structures at the process plant is also well-advanced;

· Process plant commissioning is now expected to commence at the start of December, a number of weeks later than originally envisaged; plant commissioning is then expected to run through into January 2019, with first production of tungsten concentrates from the beginning of February;

· Projected construction costs remain within the Project's Construction Budget of €53.6 million;

· Recent site photos of the construction activity can be seen on Ormonde's website at the following link http://ormondemining.com/timeline-in-pictures/.

 

Michael Donoghue, Ormonde's Chairman and Interim Managing Director, commented:

 

"It is very pleasing to have achieved another major project milestone during the quarter, with the on-target commencement of commissioning of the crush and screen plant and the water treatment plant, taking the Project into its mine commissioning phase. This major advancement accompanied progress on the construction of the process plant where most of the major equipment has been installed and structural works are well advanced.

 

"The commissioning of the process plant is now due to commence in early December, slightly later than originally planned, with first tungsten expected to be produced from early February 2019, to commence a new secure supply to the global markets."

 

 

Enquiries to:

 

Ormonde Mining plc Tel: +353 (0)1 8014184

Paul Carroll, Chief Financial Officer

Fraser Gardiner, Chief Operating Officer

 

Davy (Nomad, ESM Adviser and Joint Broker)

John Frain Tel: +353 (0)1 6796363

 

SP Angel Corporate Finance LLP (Joint Broker)

Ewan Leggat Tel: +44 (0)20 34700470

 

Capital M Consultants

Simon Rothschild Mob: +44 (0)77 03167065

 

Murray Consultants

Mark Brennock Tel: +353 (0)1 4980300 Mob: +353 (0)87 2335923

 

 

Details

 

Construction:

The construction of the turnkey crush and screen plant is complete, with only electrical circuitry remaining to be finalised, such that by the second half of September commissioning of the entire crushing circuit will commence.

 

At the process plant, the installation of major equipment and structural installation are 70 per cent completed: jigs, cyclones, spirals, hydrosizer, shaking tables, mills, concentrate thickeners, concentrate dryer and cooler, tailings dewatering screens, fines thickener and filter press are all fully installed or in position. However, a number of factors including detailed engineering, equipment delivery and contractor scheduling have combined towards the latter stages of the project to delay the completion of some installations such as the preconcentration screen structure, process piping and electrical works, when compared to the original June 2017 construction schedule.

 

In the meantime, details such as walkways, the process plant control room, external cladding, roofing, and water tanks are well advanced. Other developments in hand include the installation of the water management system pipework, and completion of site services and infrastructure, including the site laboratory, canteen and changing rooms. The underground High Tension ("HT") powerline, the main HT substation and yard, and the Medium Tension electrical ring main have all been installed.

 

Commissioning:

The Project team achieved a major milestone during August with the commencement of initial commissioning of the primary crusher. To-date, several hundred tonnes of waste rock have been successfully fed through the crusher and conveyed to the coarse ore stockpile for use in commissioning the rest of the crush and screen circuit during the second half of September. This will be the focus of the commissioning program while the process plant is being completed.

 

Initial commissioning of the water treatment plant has been carried out, and will be finalised on the imminent completion of the water management system pipework and pump installation to feed water from the old open pit.

 

Commissioning of the process plant is now due to commence at the start of December (compared to previous guidance of end-September). The current commissioning plan sees first production of tungsten from the beginning of February 2019.

 

 

Tungsten Market:

The Board notes that APT tungsten prices have seen a period of weakness over the last couple of months, with prices reducing from US$352 per metric tonne unit ("mtu") in late June to a current range of US$275-290 per mtu. This correction appears to be attributable to a combination of Chinese APT smelters coming back online following closures related to environmental inspections, and traditional weak trading demand during the summer period. Despite this short-term variability, the Board remains of the view that supply-demand fundamentals will continue to support prices over the medium to long term.

 

 

 

 

 

Notes:

This announcement includes certain statements that may be deemed "forward-looking statements". Although the Company believes the forward-looking statements are based on reasonable assumptions, such statements should not be in any way construed as guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements.

 

Risk factors are typical of a mining project development and include (but are not limited to): the availability and / or delivery of equipment and contractor services to complete mine construction on schedule and on budget; plant performance during and after commissioning; rates of metal recovery in the process plant; mined ore tonnages and grade in comparison to estimated ore reserves; cost overruns and the potential for future additional funding requirements; and tungsten concentrate sales prices.

 

Barruecopardo is a fully permitted and funded mining project currently being developed through a US$99.7 million funding package agreed with Oaktree Capital Management (70% interest). Ormonde's participation in the Project is held through its 30 per cent minority interest in Barruecopardo Joint Venture BV, a company which is governed by a Shareholder Agreement between Ormonde and its partner which provides for certain rights and obligations for each party. 

 

For more information, visit www.ormondemining.com 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDQFLFFVKFBBBF
Date   Source Headline
15th Apr 201510:49 amRNSForm 38.5a Ormonde Mining Plc
14th Apr 201510:15 amRNSForm 38.5a Ormonde Mining Plc
13th Apr 20157:00 amRNSBarruecopardo Project Financing Update
31st Mar 201510:16 amRNSForm 38.5a Ormonde Mining Plc
27th Mar 201510:55 amRNSForm 35.8a Ormonde Mining Plc
25th Mar 201510:22 amRNSForm 38.5a Ormonde Mining Plc
24th Mar 201510:30 amRNSForm 38.5a Ormonde Mining Plc
23rd Mar 201510:05 amRNSForm 38.5a Ormonde Mining Plc
20th Mar 201511:27 amRNSForm 38.5a Ormonde Mining Plc
19th Mar 201510:24 amRNSForm 38.5a Ormonde Mining Plc
18th Mar 201511:39 amRNSForm 38.5a Ormonde Mining Plc
16th Mar 20151:57 pmRNSHolding(s) in Company
16th Mar 20151:55 pmRNSHolding(s) in Company
16th Mar 201511:09 amRNSForm 38.5(a) Ormonde Mining Plc
13th Mar 201511:41 amRNSForm 38.5(a) Ormonde Mining Plc
12th Mar 201512:37 pmRNSForm 8.3 - Ormonde Mining plc
12th Mar 201510:42 amBUSForm 38.5 (b) - Ormonde Mining Plc
12th Mar 201510:25 amRNSRule 2.10 Announcement
12th Mar 201510:17 amRNSForm 38.5a Ormonde Mining Plc
11th Mar 201512:21 pmRNSRule 2.10 Announcement
11th Mar 201511:09 amRNSApproach from Almonty Industries
11th Mar 20157:27 amRNSStatement on Approach to Ormonde Mining Plc
2nd Mar 20152:58 pmRNSHolding(s) in Company
18th Feb 20157:00 amRNSBarruecopardo - Financing and Operations Update
16th Jan 20151:33 pmRNSHolding(s) in Company
17th Dec 20145:37 pmRNSHolding(s) in Company
27th Nov 20145:35 pmRNSHolding(s) in Company
26th Nov 20145:03 pmRNSHolding(s) in Company
21st Nov 20147:00 amRNSBarruecopardo - Granting of Mining Concession
6th Oct 20144:35 pmRNSHolding(s) in Company
30th Sep 20145:47 pmRNSHolding(s) in Company
29th Sep 20147:00 amRNSHalf Yearly Report
21st Jul 20147:00 amRNSEnterprise Securities Market Notice
16th Jul 201411:59 amRNSResult of AGM
15th Jul 20147:00 amRNSBarruecopardo Permitting Update
20th Jun 20142:41 pmRNSAnnual Financial Report
11th Jun 20147:00 amRNSFinal Results 2013
8th May 20142:03 pmRNSHolding(s) in Company
8th May 20142:01 pmRNSHolding(s) in Company
6th May 20147:01 amRNSEnterprise Securities Market Notice
2nd May 201410:46 amRNSResult of EGM
29th Apr 20147:00 amRNSBarruecopardo Update
15th Apr 20145:44 pmRNSHolding(s) in Company
11th Apr 20147:00 amRNSEnterprise Securities Market Notice
8th Apr 20145:28 pmRNSNotice of EGM
4th Apr 20142:00 pmRNSPlacing Raising
24th Mar 20147:00 amRNSOfftake Agreement
3rd Mar 20147:00 amRNSFairport Engineering Appointment
11th Feb 20145:54 pmRNSHolding(s) in Company
3rd Feb 20147:00 amRNSBarruecopardo Permitting

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.