Cambay Drilling Update

28 Oct 2013 07:00

RNS Number : 4848R
Oilex Ltd
27 October 2013
 



 

28 October 2013

 

 

Cambay Drilling Update

 

· Critical casing ordered and delivery scheduled for early December

· Casing fulfils a recommendation of the Independent Engineering Report

· Bid evaluations for rig and fracture stimulation equipment nearing completion

 

Oilex Ltd (ASX: OEX, AIM: OEX, Oilex) is pleased to provide an update on the preparations for drilling Cambay-77H in its Cambay Tight Hydrocarbon Project. As indicated previously, the full suite of tender packages for all equipment, materials and services required for Cambay-77H have been issued and all the bid documents have been received from prospective bidders. Joint Venture representatives have completed technical evaluation of the following critical items:

 

· 4 ½ inch completion tubulars

· Drill Rig and Associated Services

Of these critical items, the commercial evaluation is now complete and approved by the Joint Venture for the 4 ½ inch completion tubulars. This critical item has been ordered with an expected delivery to the site during December 2013. Availability of these tubulars is crucial for compliance with the recommendations of the independent engineering review of Cambay-76H, announced during October 2012.

The quotations to supply the rig and associated services are currently being reviewed within the Joint Venture and the commercial evaluation will begin immediately follow endorsement by the technical team. Multiple bids have been received and based upon the technical submissions a number of rigs appear to be suitable for Cambay-77H. The evaluation of bids for the Fracture Services is progressing in parallel with the Drill Rig.

 

In relation to endorsement of the Gas Sales Agreement signed and announced in April 2013, the Government has recently informed the Joint Venture that a formal competitive tendering process is now required to demonstrate an arm's length price structure before endorsement of the GSA is granted. Competitive bids are due in late November 2013.

 

Managing Director of Oilex, Ron Miller, said

"We are confident that the tendering process is progressing and the selection of contractors, suppliers and vendors is being completed in a methodical fashion to mitigate risks as per the recommendation of the independent engineering report.

The focus is now on completion of the recommendation for the drilling rig and fracture stimulation equipment selection and we look forward to updating the market accordingly."

 

For further information, please contact:

Oilex Ltd

Ron Miller, Managing Director

Email: oilex@oilex.com.au

Tel: +61 8 9485 3200

Australia

RFC Ambrian Limited

Nominated Adviser and AIM Broker

Samantha Harrison

Email: samatha.harrison@rfcambrian.com

Tel: +44 203 440 6800

UK

 

Tavistock Communications

Conrad Harrington

Email: charrington@tavistock.co.uk

Tel: +44 207 920 3150

UK

 

Competent Person's Statement

Information in this report relating to hydrocarbon reserves or resources has been reviewed and checked by Mr Peter Bekkers B.Sc. (Hons), the Chief Geoscientist of Oilex Ltd who has over 15 years of experience in petroleum geology and is a member of the Society of Petroleum Engineers and AAPG. Mr Bekkers consents to the inclusion of the information in this report relating to hydrocarbon reserves and resources in the form and context in which it appears. Resource estimates contained in this report are in accordance with the standard definitions set out by the Society of Petroleum Engineers, Petroleum Resources Management System, 2007.

This document may include forward-looking statements. Forward-looking statements include, but are not necessarily limited to, statements concerning Oilex Ltd.'s planned exploration program and other statements that are not historic facts. When used in this document, the words such as "could", "plan", "estimate" "expect", "intend", "may", "potential", "should" and similar expressions are forward-looking statements. Although Oilex Ltd believes that its expectations reflected in these are reasonable, such statements involve risks and uncertainties, and no assurance can be given that actual results will be consistent with these forward-looking statements.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUBSUROVARUUA
Date   Source Headline
1st Jul 20157:27 amRNSTrading Halt
29th Jun 20157:00 amRNSCambay Field - Gas Sales Commence
10th Jun 20157:00 amRNSPAC Partners Broker Research
8th Jun 20157:00 amRNSCambay-73 : Pipeline & pre-commissioning completed
8th Jun 20157:00 amRNSChange of Registered Office
20th May 20158:33 amRNSAppendix 3B - Cancellation of Unlisted Options
18th May 20157:00 amRNSPESA Deal Day Presentation
14th May 201510:16 amRNSJPDA 06-103 Joint Venture
13th May 20157:00 amRNSJPDA 06-103 Joint Venture
11th May 20158:51 amRNSInterview with Oilex Managing Director
11th May 20157:00 amRNSOILEX Investor Presentation May 2015
30th Apr 20157:00 amRNSQuarterly Report 31 March 2015
29th Apr 20157:00 amRNSInterview with Oilex Managing Director
28th Apr 20157:00 amRNSCambay-73 : Production Facilities Completed
20th Apr 20157:03 amRNSOILEX Investor Presentation April 2015
16th Apr 20157:06 amRNSCambay Field - Reserves and Contingent Resources
14th Apr 20159:51 amRNSAppointment of Australian Broker
26th Mar 20157:00 amRNSCambay-73 - Construction of Oil & Gas Facilities
20th Mar 20158:37 amRNSInterview with Managing Director
19th Mar 20157:00 amRNSAppointment of UK Broker
18th Mar 20157:00 amRNSAppendix 3B - Exercise of Listed Options
16th Mar 201512:31 pmRNSOilex Investor Presentation March 2015
9th Mar 20157:46 amRNSIndia Operations Update with Addendum
9th Mar 20157:00 amRNSIndia Operations Update
19th Feb 20157:00 amRNSAppendix 3B - Issue of Employee Options
12th Feb 20159:28 amRNSInterview with Oilex Managing Director
11th Feb 20157:00 amRNSInterim Financial Report half-year 31 Dec 2014
5th Feb 20157:00 amRNSOilex Investor Presentation - February 2015
3rd Feb 20157:00 amRNSAppendix 3X J Auld
30th Jan 20157:00 amRNSQuarterly Report 31 December 2014
28th Jan 20157:00 amRNSAppointment of UK Based Non-Executive Director
27th Jan 20157:00 amRNSAppendix 3B - Cancellation of Unlisted Options
21st Jan 20157:00 amRNSInterview with Oilex Vice Chairman
20th Jan 20157:00 amRNSChange of Share Registry
19th Jan 20157:00 amRNSCambay-77H - Gas Sales Agreement Endorsed
30th Dec 20147:00 amRNSAdmission of Shares and Total Voting Rights
24th Dec 20147:00 amRNSNotice of Change in Substantial Holding
23rd Dec 20149:16 amRNSAppendix 3Y R Miller
23rd Dec 20149:14 amRNSAppendix 3Y M Cozijn
22nd Dec 20148:50 amRNSCleansing Notice and Appendix 3B
19th Dec 20149:10 amRNSCompletion of SPP Raising A$2.5 Million
12th Dec 20147:00 amRNSCambay Basin demonstrates strong economics
11th Dec 20147:00 amRNSCanning Basin SPA 17 AO
8th Dec 20147:00 amRNSCambay-77H - Successful Well Test
5th Dec 20149:18 amRNSShare Purchase Plan - Extension to ClosingDate
5th Dec 20148:31 amRNSBhandut-3 - Gas Sales Agreement Endorsed
1st Dec 20147:00 amRNSCambay-77H - Production Test Complete
28th Nov 20148:52 amRNSUK Shareholders Access to Share Purchase Plan
28th Nov 20147:00 amRNSInterview with Oilex Ltd Managing Director
26th Nov 20147:00 amRNSShare Purchase Plan Offer Document

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.