Completion of FEED & P90 Estimate

22 Nov 2018 12:42

RNS Number : 2370I
Infrastrata PLC
22 November 2018
 

Prior to publication, the information contained within this announcement was deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 ("MAR"). With the publication of this announcement, this information is now considered to be in the public domain.

 

 

22 November 2018

 

InfraStrata plc

("InfraStrata" or the "Company")

 

Islandmagee Gas Storage Project - Completion of FEED & P90 Estimate

 

InfraStrata plc (AIM: INFA), the UK quoted company focused on the development of natural gas storage capacity, is pleased to announce that work on the FEED (Front End Engineering Design) for its Islandmagee gas storage project (the "Project") has now been completed by the engineers and consultants, both for the surface and subsurface elements, and the final reports received by InfraStrata.

 

FEED commenced in May 2018 and has been completed in full as contracted, having been delivered on budget and ahead of time. In accordance with the EU grant provisions for the FEED study, the required reports will be submitted to the EU in December 2018.

 

The Owners Engineer teams, WSP (surface) and Atkins (subsurface), have been working tirelessly, ensuring the technical elements of the FEED studies are in keeping with InfraStrata's expectations as FEED has been reaching a climax in recent weeks. Whilst it will take InfraStrata some time to fully analyse the studies, it is clear that nothing material has been uncovered during either the surface FEED works carried out by Costain or the subsurface FEED works carried out by DEEP KBB that should physically prevent construction of the gas storage facility.

 

As part of the FEED studies, a "P90" cost estimate has been undertaken for delivering the Project determined by probabilistic analysis. P90 values are established to provide a high level of confidence (90% confident) such that the Project outturn cost will have a 90% chance to be below this estimate and a 10% chance above. The P90 estimate is consistent with the economic modelling undertaken on the Project and therefore InfraStrata proceeds into the next phase of development with a high level of confidence from a technical, cost and economic basis.

 

The economic modelling undertaken was on a range of cost estimates of £100m - £120m for delivering Phase 1 (2 caverns) and £300m - £330m for Phase 2 (adding an additional 6 caverns, resulting in a total of 8 Caverns). The combined FEED studies have delivered P90 cost estimates of £114m for Phase 1 and £265m for Phase 2, with an additional risk allowance for a total of £11.6m for both phases. The schedule has confirmed an expectation of injection of first gas for storage in 2022 with full operations (withdrawal and injection) expected in Q1 2023 assuming FID (final investment decision) is taken by the end of H1 2019. The Company continues to work with various potential partners in relation to providing funding for the Project and updates will be provided as appropriate.

 

The engineering design that has been completed will position InfraStrata's Islandmagee facility as a globally competitive and technologically advanced, fast cycle, pioneering gas storage facility. Costain, Deep, Atkins and WSP have all worked together seamlessly to ensure the best possible outcome for InfraStrata.

 

John Wood, Chief Executive Officer commented: "Completing FEED successfully and receiving independent confirmation that the Project can be constructed within our financially modelled ranges is a credit to the entire team that has worked on the Project. We are now working on planning the next development stages of the project whilst ensuring all elements come together for a successful final investment decision before the end of H1 2019. I would like to thank Costain, Deep KBB, Atkins and WSP for the delivering the FEED study in the time available to realise the EU Grant."

 

 

Current Milestone Progress

 

Milestone

Month

Description

Status

1

April

Contract Award Costain

InfraStrata

√ - Completed

2

May

Contract Award DEEP

InfraStrata

√ - Completed

3

May

Appointment of Subsurface Expert

InfraStrata

√ - Completed

4

May

Issue FEED schedule, project and quality plans

Costain

√ - Completed

5

May

Current Design Agreed

Costain

√ - Completed

6

June

Current Design Agreed

DEEP KBB

√ - Completed

7

June

Appoint Owners Engineer

InfraStrata

√ - Completed

8

July

Issue Process Flow Diagrams

Costain

√ - Completed

9

August

Gas & Leaching layout review

Costain

√ - Completed

10

August

All Process & Instrumentation Diagrams

Costain

√ - Completed

11

Oct.

Engineering Design Complete

Costain

√ - Completed

12

Oct.

All Investigation work on samples complete

DEEP KBB

√ - Completed

13

Oct.

Cavern Design & Rock Mechanics Complete

DEEP KBB

√ - Completed

14

Nov.

Surface FEED Deliverables & Estimates

Costain

√ - Completed

15

Nov.

Subsurface FEED Deliverables & Estimates

DEEP KBB

√ - Completed

16

Dec.

Submit Reports To EU

InfraStrata

 

 

For further information, please contact:

 

InfraStrata plc

John Wood, Chief Executive

 

c/o Yellow Jersey

+44 (0)20 3735 8825

Allenby Capital Limited (AIM Nominated Adviser & Joint Broker)

Jeremy Porter / Alex Brearley / Liz Kirchner

 

+44 (0)20 3328 5656

SI Capital Limited (Joint Broker)

Nick Emerson

 

+44 (0) 20 3871 4038

Yellow Jersey

Tim Thompson  

+44 (0)20 3735 8825

 

 

-ENDS-

 

Notes to editors:

 

InfraStrata is an independent gas storage company focused on the UK and Ireland. Further information is available on the Company's website: www.infrastrataplc.com 

 

Background on the Islandmagee Storage Project

The Islandmagee gas storage project is a proposed salt cavern gas storage facility located on Islandmagee in County Antrim, Northern Ireland. The Board of InfraStrata believes that the proposed 500 million cubic metres Natural Gas Cavern Storage facility will provide over 25% of the UK's Natural Gas Storage once constructed, and will be situated adjacent to the Scotland Northern Ireland (gas) Pipeline (SNIP) and the Moyle 500 Megawatt Electricity Interconnector. Work commenced in 2007 with the acquisition of 3D seismic data to image the Permian salt in the Larne Lough area. During 2012, planning permission was granted for the project and a gas storage licence was issued by the Utility Regulator. In 2015 a well was drilled to core the salt and confirm the technical feasibility of the project, supported in part by the European Commission. The Front End Engineering and Design (FEED) element of the Project is scheduled for completion by the end of 2018. To date approximately £13.5m has been invested in the project.

 

Further information is available on the company's website: www.infrastrata.co.uk

 

 

 

The Front End Engineering & Design (FEED) and Insitu Downhole Testing programme for the Islandmagee gas storage project is co-financed by the European Union's Connecting Europe Facility.

 

Disclaimer releasing the European Union from any liability in terms of the content of the dissemination materials:

 

"The sole responsibility of this publication lies with the author. The European Union is not responsible for any use that may be made of the information contained therein."

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
MSCPGGRWGUPRGPP
Date   Source Headline
17th Dec 20129:42 amRNSPosting of Annual Report and Financial Statements
26th Nov 201210:39 amRNSDirector's Holdings in Company
26th Nov 20127:00 amRNSExploration Update
26th Nov 20127:00 amRNSFinal results for the year ended 31 July 2012
2nd Nov 20121:48 pmRNSHolding in Company
1st Nov 20127:00 amRNSNotification of Results
18th Oct 201210:31 amRNSIslandmagee Planning Permission Granted
10th Sep 20121:51 pmRNSNotification of Major Interest in Shares
14th Aug 20127:00 amRNSFarmout to Corfe Energy
2nd Aug 20127:00 amRNSAppointment of NOMAD and Broker
31st Jul 20127:00 amRNSSalt Production at Portland
30th Jul 20121:18 pmRNSBrigantes and Corfe Share Placings
3rd Jul 20127:00 amRNSCCS Innovation Programme Application
27th Jun 20127:00 amRNSCompletion of 2012 seismic survey in County Antrim
11th Jun 20121:26 pmRNSDirector/PDMR Shareholding
6th Jun 20127:00 amRNSAgreements with eCORP and Portland Port
29th May 20127:00 amRNSMobilisation for Infill Seismic Survey in NIreland
15th May 20123:55 pmRNSDirector/PDMR Shareholding
30th Apr 20127:00 amRNSInterim Results
12th Apr 20127:00 amRNSHolding(s) in Company
26th Mar 20127:00 amRNSFurther seismic acquisition in Northern Ireland
22nd Mar 20127:00 amRNSNotice of Results
12th Mar 201212:00 pmRNSDirector's Holdings in Company
12th Mar 201212:00 pmRNSDirector's Holding in Company
29th Feb 20125:21 pmRNSDirector/PDMR Shareholding
27th Feb 20122:04 pmRNSDirector/PDMR Shareholding
21st Feb 20127:00 amRNSFarm-in by Corfe Energy Limited
17th Feb 20127:00 amRNSDirector's Holdings in Company
27th Jan 20124:40 pmRNSSecond Price Monitoring Extn
27th Jan 20124:35 pmRNSPrice Monitoring Extension
24th Jan 201211:57 amRNSResult of AGM
20th Jan 20127:00 amRNSBP Gas Marketing equity option in Islandmagee
5th Jan 20129:26 amRNSOffer of exploration licence
14th Dec 201111:14 amRNSPosting of Annual Report and Financial Statements
15th Nov 20117:00 amRNSFinal Results
27th Oct 20117:00 amRNSNotice of Results
22nd Sep 20117:00 amRNSExclusivity Agreement signed - Islandmagee Project
12th Sep 20117:00 amRNSMobilisation for seismic survey in N.Ireland
1st Aug 201112:33 pmRNSSale of Interests in the Avington Oil field
16th Jun 20117:00 amRNSAppointment of Tesla-IMC as Seismic Contractor
9th May 20114:35 pmRNSPrice Monitoring Extension
9th May 20117:00 amRNSOperational update
6th May 20114:35 pmRNSPrice Monitoring Extension
28th Mar 20117:00 amRNSInterim results
17th Mar 20117:00 amRNSNotification of Results
4th Mar 201112:00 pmRNSLicence Award, Completion of Funding
1st Mar 201110:59 amRNSTotal Voting Rights
11th Feb 20112:53 pmRNSHolding(s) in Company
7th Feb 20117:00 amRNSPlacing of shares
3rd Feb 20119:30 amRNSHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.