Project Update

14 Jan 2019 07:00

RNS Number : 9303M
Edenville Energy PLC
14 January 2019
 

14 January 2019

 

EDENVILLE ENERGY PLC

("Edenville" or the "Company")

 

Project Update

 

Edenville Energy plc (AIM: EDL), the company developing a coal project in southwest Tanzania, is pleased to provide its latest update on developments at the Company's Rukwa Coal Project (the "Project").

 

As stated in the announcements made on 6 November 2018, 17 December 2018 and 20 December 2018 the net proceeds of the US$750,000 Initial Loan from Lind are being used by the Company for a number of purposes. This includes the purchase of a second excavator to open up the new mining area to the north of the current excavations. The Company is pleased to confirm that this second excavator has now been acquired and together with the existing excavator and four additional hired haul trucks, is in operation at the Company's Project site.

 

These vehicles are currently all being employed to increase the amount of material being mined from the existing pit, but the newly acquired second excavator and associated haul trucks will shortly move to the new northern mining area to begin opening this up. The mobile in-pit lighting to allow 24 hour per day operation in the existing pit has been installed, further increasing the Company's mining capacity.

 

As stated on 17 December 2018 the land compensation process and required regulatory documents for the northern mining area were completed and submitted by the Company to the relevant Tanzanian Government authorities. The Company is pleased to confirm that the relevant government authorities have now provided their approval and land compensation payments are being made, together with detailed delineation of the northern mining area being undertaken. The Company anticipates that mining of the new northern area will commence shortly and will provide further updates regarding progress as soon as practicable.

 

As announced on 20 December 2018, the Lamella clarifier water treatment plant is now fully operational and has been delivering the anticipated improvements to both water qualities in the plant process and in the return ponds, leading to increased coal processing plant productivity.

 

Construction of the pre-screening plant and conveyors, designed to remove the majority of coal fines before they reach the washing circuit, is now complete and the plant is now undergoing testing. Alongside this testing, further refinements are being made to the feed hopper. It is expected that the pre-screen plant will be fully integrated into the Company's washed coal production process by the end of January 2019.

 

Management believe that these developments, when complete, will increase that amount of washed can that can be produced from the Project and the Company looks forward to providing further updates as matters progress.

 

As announced on 11 December 2018, the Company intends to transition its Nominated Adviser role from Northland Capital Partners Limited to SP Angel Corporate Finance LLP. This process is progressing and a further announcement will be made as appropriate.

 

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) 596/2014.

 

 

For further information please contact:

Edenville Energy Plc

Jeff Malaihollo - Chairman

Rufus Short - CEO

+44 (0) 20 3934 6630

 

Northland Capital Partners Limited

(Nominated Adviser and Broker)

David Hignell

Gerry Beaney

Jamie Spotswood

 

 

+44 (0) 20 3861 6625

IFC Advisory

(Financial PR and IR)

Tim Metcalfe

Graham Herring

Heather Armstrong

+44 (0) 20 3934 6630

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDBLGDBXUBBGCB
Date   Source Headline
18th Jul 20197:00 amRNSMining Update
27th Jun 20197:00 amRNSCommencement of Mining at the Northern Area
21st Jun 20191:37 pmRNSHolding(s) in Company
21st Jun 20197:00 amRNSAnnual Results for the year ended 31 December 2018
13th Jun 20192:09 pmRNSRukwa Coal Project Update
3rd Jun 20192:48 pmRNSHolding(s) in Company
31st May 20197:00 amRNSTotal Voting Rights
29th May 201911:07 amRNSHolding(s) in Company
21st May 20193:42 pmRNSHolding(s) in Company
21st May 20197:00 amRNSHolding(s) in Company
20th May 20196:04 pmRNSHolding(s) in Company
17th May 20191:49 pmRNSResult of General Meeting
16th May 20194:02 pmRNSNew Company Presentation
15th May 20194:36 pmRNSPrice Monitoring Extension
15th May 20199:00 amRNSPrice Monitoring Extension
14th May 20197:00 amRNSRukwa Coal Project - Update
9th May 20194:26 pmRNSHolding(s) in Company
3rd May 20191:11 pmRNSHolding(s) in Company
3rd May 20197:00 amRNSUpdate re: Collateral Shares issued to Lind
2nd May 201911:51 amRNSHolding(s) in Company
29th Apr 20197:00 amRNSPlacing and Notice of GM
1st Apr 20197:00 amRNSCorporate Update
15th Feb 20194:08 pmRNSResult of General Meeting & Open Offer
14th Feb 201911:39 amRNSTanesco Update
12th Feb 20193:59 pmRNSHolding(s) in Company
30th Jan 20197:00 amRNSOpen Offer and Notice of General Meeting
29th Jan 20197:00 amRNSAppointment of Nominated Adviser and Broker
25th Jan 20197:00 amRNSNomad Status Update
14th Jan 20197:00 amRNSProject Update
20th Dec 20187:00 amRNSLamella Plant Operational
17th Dec 20187:00 amRNSProject Update
11th Dec 20187:00 amRNSNomad Status
7th Dec 201810:40 amRNSTanesco Re-submission
8th Nov 20187:00 amRNSLatest Tanesco Announcement
6th Nov 20187:00 amRNSConditional Convertible Loan Facility
2nd Nov 20183:51 pmRNSRecent Tanesco Announcement
22nd Oct 20187:00 amRNSSubmission of RFQ Documentation to Tanesco
9th Oct 20187:00 amRNSCoal supply contract
8th Oct 20187:00 amRNSFurther Coal Supply Contract
24th Sep 20187:00 amRNSInterim Results for the six months to 30 June 2018
22nd Aug 20187:00 amRNSCoal supply contract
14th Aug 201811:00 amRNSPrice Monitoring Extension
14th Aug 20187:00 amRNSCommercial Coal Production Update
18th Jul 20187:00 amRNSBroker Update
28th Jun 20183:55 pmRNSResult of AGM
25th Jun 20181:50 pmRNSExtension of MOU with Sinohydro
22nd Jun 20188:45 amRNSPowerline Financing
12th Jun 20187:00 amRNSInterview with CEO
5th Jun 20189:05 amRNSNotice of AGM
5th Jun 20187:00 amRNSAnnual Results for the year ended 31 December 2017

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.