Operations Update: Production Enhancement Plan

27 Sep 2022 07:00

RNS Number : 7155A
Echo Energy PLC
27 September 2022
 

27 September 2022

 

Echo Energy plc

("Echo" or the "Company")

 

Operations Update: Production and Infrastructure Enhancement Plan

 

Echo Energy, the Latin American focused energy company, is pleased to provide an operational update regarding further progress in the execution of the Santa Cruz Sur assets Production and Infrastructure Enhancement Plan previously announced by the Company on 7 July 2022 (the "Plan").

 

The first operational priority under the Plan has now been successfully completed with all three power generation units now successfully commissioned and fully operational in the Cerro Molino Oeste, El Indio Oeste and Oceano fields, providing additional power to support existing and future production levels from, inter alia, the recommissioning of shut-in wells using the existing Santa Cruz Sur joint venture rig.

 

Upgrades to the workover rig owned by the Santa Cruz Joint Venture are underway. The timing of key upgrade activities are being scheduled and are dependent upon the availability of materials and third party services . These activities include an overhaul of the hydraulic system and the blowout preventer (BOP) stack.

 

The second operational priority under the plan is focussed on the maintenance and optimisation of the existing compressors at Cerro Norte and Campo Bremen to enable future increased volumes of gas to be processed and then sold into the main gas export line. Initial maintenance work has now commenced, and the full set of operations to optimise the compressors is anticipated to take approximately three months, based on the current parts and materials availability. These operations will be carried out with the intention of minimising disruption to existing gas production, although some impact is to be expected. 

 

In addition to the stated objectives of the Plan, further infrastructure upgrades have been carried out in the Oceano field with the intention of increasing the amount of available sales gas. Work to convert the Oceano compressor from gas power to electrical power has now been successfully completed during a 12 day period during which, as a result of these operations requiring the Oceano field to be shut-in, total net-gas production was temporarily reduced by approximately 2 MMscf/d and net liquids production was reduced by approximately 20 bopd over the 12 day period.

 

The Company looks forward to continuing to update shareholders on further operational progress.

 

For further information, please contact:

 

Echo Energy

Martin Hull, Chief Executive Officer

 

via Vigo Communications

Vigo Consulting (IR & PR Advisor)

Patrick d'Ancona

Chris McMahon

 

+44 (0) 20 7390 0230

Cenkos Securities (Nominated Adviser)

Ben Jeynes

Katy Birkin

 

+44 (0) 20 7397 8900

Arden Partners plc (Corporate Broker)

Simon Johnson (Corporate Broking)

John Llewellyn-Lloyd (Corporate Finance)

 

+44 (0) 20 74614 5900

 

Note

 

The assignment of Echo's 70% non-operated participation in the Santa Cruz Sur licences is subject to the authorisation of the Executive Branch of Santa Cruz's Province, which is part of the overall process of title transfer that is proceeding as anticipated.

 

Certain of the information contained within this announcement is deemed by the Company to constitute inside information as stipulated under The Market Abuse Regulation (EU 596/2014) pursuant to the Market Abuse (Amendment) (EU Exit) Regulations 2018. Upon the publication of this announcement via a Regulatory Information Service ("RIS"), this inside information is now considered to be in the public domain.

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDUNORRUKUKUUR
Date   Source Headline
21st Jun 20189:05 amRNSSecond Price Monitoring Extn
21st Jun 20189:00 amRNSPrice Monitoring Extension
21st Jun 20187:00 amRNSSignificant Hydrocarbons Interpreted in EMS-1001
15th Jun 20187:00 amRNSAcceleration of Fracción D Drilling
12th Jun 20187:00 amRNSDrilling Commences on EMS-1001
11th Jun 20187:00 amRNSCSo-85 Positive Extended Well Test Results
6th Jun 20187:00 amRNSELA-1 Well Completion
31st May 20185:13 pmRNSTotal Voting Rights
29th May 20188:15 amRNSDrilling Commences on ELA-1
25th May 20183:30 pmRNSDirector/PDMR Shareholding
25th May 20187:00 amRNSPlacing and Subscription to Raise £8.5 million
24th May 20184:52 pmRNSAnnual Report
18th May 20187:00 amRNSGas Discovery at ELM-1004
11th May 20181:05 pmRNSStatement re Argentinian Treasury Exposure
9th May 20187:00 amRNSDrilling Commences on First Exploration Well
30th Apr 20187:00 amRNSOperational Update
30th Apr 20187:00 amRNSTotal Voting Rights
23rd Apr 20187:00 amRNSOil to Surface at Second Workover
18th Apr 20184:17 pmRNSOption Exercise and Total Voting Rights
18th Apr 20187:00 amRNSFirst Oil Export Cargo and Gas Sales Update
16th Apr 20187:25 amRNSFinal Results
13th Apr 20189:05 amRNSSecond Price Monitoring Extn
13th Apr 20189:00 amRNSPrice Monitoring Extension
13th Apr 20187:00 amRNSGas to Surface at First Workover
6th Apr 20187:00 amRNSRig Mobilisation for Workover Programme
12th Mar 20187:00 amRNSAppointment of COO and Bolivia Update
28th Feb 20187:00 amRNSBlock Admissions, Issue of Options & PDMR Holding
12th Feb 20187:00 amRNS2018 Work Programme
1st Feb 20185:41 pmRNSTotal Voting Rights
31st Jan 20187:00 amRNSCorporate Update and New Website
23rd Jan 20184:11 pmRNSWarrant Exercise and Total Voting Rights
4th Jan 20188:00 amRNSReverse Takeover - Echo Energy Plc
3rd Jan 20183:58 pmRNSResult of GM, Acquisition and Re-Admission
18th Dec 20173:02 pmRNSIssue of Options and Director/PDMR Shareholding
18th Dec 20178:00 amRNSSch 1 - Echo Energy Plc
18th Dec 20177:30 amRNSRestoration - Echo Energy Plc
18th Dec 20177:00 amRNSProposed Acquisition and Notice of General Meeting
7th Dec 20173:00 pmRNSUpdate re Proposed Farm-In
1st Nov 20177:00 amRNSFarm-In Agreement
30th Oct 20177:30 amRNSSuspension - Echo Energy Plc
30th Oct 20177:00 amRNSStatement re Share Price Movement and Suspension
4th Oct 20177:00 amRNSQuarterly Update
15th Sep 20177:00 amRNSAward of Seismic Reprocessing Contract
14th Sep 20177:00 amRNSAppointment of Country Representative
13th Sep 20177:00 amRNSChange of Registered Office
31st Aug 20176:07 pmRNSTotal Voting Rights
10th Aug 201711:04 amRNSHolding(s) in Company
10th Aug 20177:00 amRNSChange of Adviser
7th Aug 20177:00 amRNSAppointment of Broker
4th Aug 20177:00 amRNSNew Investor Syndicate

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.