IM-5 testing update

19 Apr 2013 07:00

RNS Number : 7373C
BowLeven Plc
19 April 2013
 



 

 

19 April 2013

 

Bowleven plc ('Bowleven' or 'the Company')

 

IM-5 testing update

 

IM-5 well, Block MLHP-7, Etinde Permit, Cameroon

 

Bowleven, the Africa focused oil and gas exploration group traded on AIM, is pleased to announce the results of the second test at the IM-5 appraisal/development well drilling offshore Cameroon. A drill stem test (DST) has now been performed on the Intra Isongo reservoir interval and this following the Middle Isongo DST announced on 2 April 2013 completes the successful drilling and testing programme at IM-5.

 

Highlights

 

Testing Overview

·; Condensate-rich gas flowed on test from both Middle and Intra Isongo intervals confirming commercial production rates and the significant liquids content of gas.

·; Combined maximum flow rates of 60 mmscfd and 7,819 bcpd (total over 17,800 boepd).

 

Intra Isongo update

·; Average flow rate of 37 mmscfd and 4,664 bcpd (total over 10,800 boepd) achieved from 29 metres of perforated section out of 70 metres of net pay.

·; High quality condensate (approximately 43 degree API) produced on test.

 

 

Testing update

The well, designed to appraise the reservoir and fluid properties of the Middle Isongo and to explore the additional potential of the Intra Isongo, was drilled to a TD of 3,430 metres MD in water depths of around 56 metres.

 

Further to our update on the 2 April 2013 post completion of the Middle Isongo DST, testing has now been performed on the Intra Isongo interval with the following results:

 

Intra Isongo update

As previously announced, the well encountered approximately 70 metres of log evaluated net hydrocarbon-bearing pay in the Intra Isongo over a gross interval of approximately 80 metres.

 

The well has now successfully flow tested condensate-rich gas from a perforated section of 29 metres out of a total of 70 metres of net pay. The interval flowed at an average rate of 37 mmscfd and 4,664 bcpd (total over 10,800 boepd) on a 64/64 inch choke. During the test sequence the interval also flowed at a peak gas rate in excess of 40 mmscfd. The average rate infers a CGR of 125 bbl/mmscf and measured CGRs of up to 133 bbls/mmscf were achieved on test. Further significant liquids (including LPGs) can be recovered via secondary processing. Further analysis of test data is required although it is our expectation that optimised Intra Isongo development well locations and completions are likely to lead to production rates well in excess of 40 mmscfd per well.

 

The Intra Isongo test result combined with the test on the Middle Isongo delivered a maximum flow rate of 60 mmscfd and 7,819 bcpd (total over 17,800 boepd).

 

Forward plan

The IM-5 drilling and testing programme is now complete and the well will be suspended as a future development/production well. The Atwood Aurora jack-up rig will be released by Bowleven following completion of suspension operations. With testing complete, volumetrics for the IM field will be updated.

 

Kevin Hart, Chief Executive, said:

 

"We are delighted with the overall results from the IM-5 well which have surpassed our expectations. The flow rates that have been achieved on test demonstrate substantial well deliverability from both the Middle and Intra Isongo intervals and further strengthen the foundation for the planned phased development of Etinde. Due to the high deliverability of the Intra and Middle Isongo reservoirs we are confident we will be able to reduce the number of wells required to supply the planned fertiliser plant.

 

The IM-5 well has not only delivered a substantial increase in estimated hydrocarbon volumes but it has also confirmed the presence of liquids rich hydrocarbons at the Isongo Marine field, a significant value driver for development plans on Etinde. In addition to proving that there are more than sufficient gas volumes present on a P90 basis to meet the 70 mmscfd dry gas requirements of the fertiliser plant, the IM-5 well has derisked considerable further prospectivity with significant volumetric upside on the block.

 

We are continuing to make good progress on the path to development in Cameroon. With the recently announced agreement between Bowleven, Ferrostaal and SNH of a gas sales term sheet for the proposed fertiliser plant and work already underway to update the formal EEAA to integrate the very successful IM-5 well results, the Group remains focused on delivering the planned phased Etinde development and reaching FID, targeted by the end of 2013. 

 

Achieving the first development phase will deliver value to all stakeholders and open up the significant hydrocarbon potential of the Etinde Permit uncovered by our successful exploration activities. We look forward to the work ahead of us in 2013. "

 

 

ENQUIRIES

For further information please contact:

 

Bowleven plc

Kevin Hart, Chief Executive 00 44 131 524 5678

Kerry Crawford, Head of Investor Relations

 

Brunswick Group LLP

Patrick Handley 00 44 207 404 5959

Catriona McDermott

Bank of America Merrill Lynch (Nomad)

Tony White 00 44 207 628 1000

Derek Ross

 

Notes to Editors:

Bowleven is an African focused oil and gas exploration group, based in Edinburgh and traded on AIM. Bowleven's strategy is focused on creating and realising material value through exploration led organic growth. Bowleven holds equity interests in five blocks in Cameroon, with three blocks located offshore in shallow water and two onshore. All of these blocks are operated by Bowleven. Bowleven also holds an equity interest in an onshore block in Kenya operated by Adamantine Energy.

 

The total flow period for the IM-5 Intra Isongo DST over various choke sizes was 48 hours with an overall test duration of several days.

 

 

Notes to Announcement:

 

(1) The information in this release reflects the views and opinions of Bowleven as operator and has not been reviewed in advance by its joint venture partners.

 

(2) The technical information in this release has been reviewed by Ed Willett, who is a qualified person for the purposes of the AIM Guidance Note for Mining, Oil and Gas Companies. Ed Willett, Exploration Director of Bowleven plc, is a geologist and geophysicist, a Fellow of the Geological Society (FGS) and a member of the Petroleum Exploration Society of Great Britain (PESGB) with over 25 years' experience in oil and gas exploration and production. 

 

 

GLOSSARY OF TERMS

The following are the main terms and abbreviations used in this announcement:

 

AIM

the market of that name operated by the London Stock Exchange

API

a specific gravity scale developed by the American Petroleum Institute (API) for measuring the relative density of various petroleum liquids, expressed in degrees

bbls/mmscf

barrels per million standard cubic feet of gas

bcpd

barrels of condensate per day

boepd

barrels of oil equivalent per day

Bowleven

Bowleven plc (LSE:BLVN) and/or its subsidiaries as appropriate

CGR

condensate gas ratio

Company

Bowleven plc

DST

drill stem test

EEAA

Etinde Exploitation Authorisation Application

Etinde Permit or Etinde

the production sharing contract between the Republic of Cameroon and EurOil Limited (an indirectly wholly owned subsidiary of the Company) dated 22 December 2008 in respect of the area of approximately 2,316 km², comprising former blocks MLHP-5, MLHP-6 and MLHP-7, offshore Cameroon; or, as the context may require, the contract area to which this production sharing contract relates

Ferrostaal

Ferrostaal GmbH

FID

final investment decision

Group

the Company and its direct and indirect subsidiaries

IM

the Isongo Marine field area, block MLHP-7, Etinde Permit

LPG

liquefied petroleum gas

MD

measured depth

mmscfd

million standard cubic feet of gas per day

P90

90% probability that volumes will be equal or greater than stated volumes

SNH

Société Nationale des Hydrocarbures, the Cameroon state oil and gas company

TD

total depth

 

For the purposes of this announcement, 6 mscf of gas has been converted to 1 boe.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCUWSAROWASAUR
Date   Source Headline
30th Nov 20073:59 pmRNSHolding(s) in Company
29th Nov 200710:24 amRNSHolding(s) in Company
20th Nov 20071:53 pmRNSBowleven IFRS Restatement
12th Nov 20079:45 amRNSHolding(s) in Company
12th Nov 20079:41 amRNSHolding(s) in Company
12th Nov 20077:00 amRNSPreliminary Results
8th Nov 20075:28 pmRNSTotal Voting Rights
8th Nov 20079:20 amRNSHolding(s) in Company
8th Nov 20079:17 amRNSHolding(s) in Company
2nd Nov 20076:30 pmRNSHolding(s) in Company
2nd Nov 20076:23 pmRNSHolding(s) in Company
2nd Nov 20076:18 pmRNSHolding(s) in Company
2nd Nov 20076:13 pmRNSHolding(s) in Company
2nd Nov 20076:10 pmRNSHolding(s) in Company
25th Oct 200711:32 amRNSAdditional Listing
24th Oct 20074:54 pmRNSHolding(s) in Company
24th Oct 20074:42 pmRNSHolding(s) in Company
24th Oct 20074:35 pmRNSHolding(s) in Company
8th Oct 200712:44 pmRNSHolding(s) in Company
2nd Oct 200712:46 pmRNSHolding(s) in Company
17th Sep 20072:55 pmRNSHolding(s) in Company
13th Sep 20073:09 pmRNSHolding(s) in Company
13th Sep 20073:03 pmRNSHolding(s) in Company
7th Sep 200711:14 amRNSHolding(s) in Company
31st Aug 20079:26 amRNSAdditional Listing
29th Aug 20077:00 amRNSTotal Voting Rights
16th Aug 200712:48 pmRNSWebsite Address
10th Aug 20077:00 amRNSOperational Update
30th Jul 20072:46 pmRNSAdditional Listing
19th Jul 20077:00 amRNSOperational Update
12th Jul 20075:33 pmRNSHolding(s) in Company
12th Jul 200711:20 amRNSHolding(s) in Company
9th Jul 20076:15 pmRNSDirector/PDMR Shareholding
6th Jul 20076:25 pmRNSHolding(s) in Company
3rd Jul 20077:01 amRNSOperational Update
25th Jun 200710:09 amRNSHolding(s) in Company
13th Jun 20073:12 pmRNSAdditional Listing
13th Jun 20073:10 pmRNSOperational Update
29th May 200711:01 amRNSHolding(s) in Company
29th May 200710:19 amRNSHolding(s) in Company
29th May 20079:11 amRNSHolding(s) in Company
22nd May 20074:14 pmRNSDirector/PDMR Shareholding
15th May 20072:57 pmRNSDirector/PDMR Shareholding
25th Apr 20077:00 amRNSDrilling Report
23rd Apr 200712:11 pmRNSAdditional Listing
10th Apr 20077:01 amRNSFarm-out of Epameno PSC
3rd Apr 200711:21 amRNSAdditional Listing
22nd Mar 20077:01 amRNSInterim Results
21st Mar 200711:13 amRNSHolding(s) in Company
21st Mar 20078:37 amRNSOperational Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.