RE: Zaza6 Jun 2018 08:54
The trouble is because of the vague Rns's people then make up time scales in their heads.
What has been RNSd is 60 days for extended testing.
So 60 days for t-45, dino, t39 and ud2
T45 started 8th April - 66 days in
Dino started 7th may - 30 days in
T39 started 1st June (ish) - 6 days in
Ud2 started 21st April - 46 days in
Those dates are taken from "operations and corporate update" RNS on 8th may
So T-45 has run over but we have some time to wait for the other three!