Gas leaks delay Angola LNG plant shutdown to mid-September

Thu, 05th Sep 2013 17:00

By Oleg Vukmanovic

LONDON, Sept 5 (Reuters) - Angola's new liquefied naturalgas (LNG) plant has pushed back the start of a 53-daymaintenance period to mid-September after engineers discoveredsmall gas leaks in onshore pipelines last month, sources linkedto the project said.

The $10 billion plant was initially due to shut on Aug. 18,but the discovery of two leaking wells led site managers todelay maintenance until the problem was traced and fixed, a siteengineer said.

The start-up of Angola's first LNG project, which convertsgas into a liquid form for export, suffered long delays as theplant was beset by various technical problems, including a firein April that occurred just hours before production was tobegin.

The Chevron-operated project eventually shipped itsfirst LNG cargo to Brazil in June, 18 months behind schedule.

Maintenance has now been pushed back until Sept. 13, thesite engineer said, while a second engineer at the plantconfirmed that maintenance was scheduled to start inmid-September.

"It will be 53 days from production to production after theplant shuts ... the maintenance is there to replace thestrainers and remove limescale and conduct a performanceacceptance test," the first source said.

Officials at Angola LNG could not be reached to comment.

As part of maintenance, engineering firm Bechtel must ensurethat the plant passes a performance test, hitting certainmilestones such as running close to its maximum capacity.

Angola LNG has so far exported three cargoes on tankers toBrazil, China and Japan, in that order, and traders wereexpecting a fourth and possibly fifth shipment from the plantprior to shutdown.

It is not clear whether there is enough LNG in its storagetanks to allow a fourth cargo to be loaded.

"Only if they produced more than expected, could they loadanother cargo. They have to keep some LNG in the tank to keep itcold during the shutdown period," the first source said.

Chevron holds a 36.4 percent stake in the project and Angolastate oil company Sonangol 22.8 percent, while Total,BP and ENI each hold 13.6 percent.

Related Shares

More News
3 May 2024 13:47

British regulator awards more North Sea oil and gas licences

NSTA awards 31 new licences aimed at boosting output *

2 May 2024 12:02

LONDON MARKET MIDDAY: FTSE 100 shines but "mixed feelings" after Fed

(Alliance News) - London's FTSE 100 was solidly higher on Thursday, outperforming European peers, as earnings from the likes of Shell and Standard Cha...

1 May 2024 18:30

Sector movers: Oil, Autos drag on FTSE 350

(Sharecast News) - Weakness in the oil patch and among select cyclicals dragged on the FTSE 350 in the middle of the week.

30 Apr 2024 14:38

UK earnings, trading statements calendar - next 7 days

29 Apr 2024 14:21

Norway's wealth fund falls short on climate ambitions, NGO says

OSLO, April 29 (Reuters) - Norway's $1.6 trillion sovereign wealth fund, the world's largest, is falling short on its climate ambitions by failing t...

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.