Patagonia Gold reports update on the Cap-Oeste heap leach project pre-feasibility studies

 

London, United Kingdom 19th March 2015 - Patagonia Gold Plc (AIM: PGD)("Patagonia Gold" or the "Company") provides an update on the Cap-Oeste heap leach project Pre-Feasibility studies.

 

Cap-Oeste heap leach project:

 

Initial results from the pre-feasibility studies being carried out on the Cap-Oeste project using the heap leach process route indicate that additional oxide resources are required to make the project economically robust at current gold and silver prices.

 

We continue to work to establish those additional resources through our exploration programmes.

Commenting on this announcement, Bill Humphries, CEO of Patagonia Gold stated that:

 

"The Company continues to see a promising long term future for the Cap-Oeste project once conditions in mining markets have normalised. Meanwhile, we will continue to maximise free cash flow from our Lomada operations. We will also concentrate our exploration efforts on replacing reserves at Lomada and continue to grow our global resource."

 

 El Tranquilo property block:

 

The El Tranquilo property block, covering approximately 80,000 hectares, contains Patagonia Gold's flagship project, the Cap-Oeste deposit, together with the COSE bonanza gold and silver deposit and numerous other prospects including Monte Leon.

 

Cap-Oeste Project:

The Cap-Oeste resource, published in September 2012, contained 269,000 ounces of gold equivalent (oz AuEq) of oxide material and 1,118,300 oz AuEq of sulphide material, predominantly in the indicated category.

 

Preliminary studies commenced in Q4 2013 indicated that Cap-Oeste should be developed in two stages with stage 1 concentrating on the oxide component amenable to cyanide leaching while design and test work was completed on the more complex sulphide material.

 

The quantity of oxide material at Cap-Oeste was deemed too small to support a CIL plant thus management decided to first investigate the possibility of adopting a heap leach processing route with low capital and operations costs similar to the Company's successful Lomada project to the north. At the same time, exploration would be aimed at proving up additional oxide resources on the El Tranquillo property to add to the Cap-Oeste resource.

 

Pre-feasibility study:

The first draft of the pre-feasibility study has been received and is currently being evaluated by management. Optimisation studies are continuing.

 

The study to date indicates a material that is easy to crush to a size suitable for heap leaching. Metallurgical testing has shown that the Cap-Oeste ore is very amenable to processing with conventional cyanide heap leaching after crushing and agglomeration with a high cyanide cure resulting in gold and silver recoveries of 80% and 40% respectively utilising a 2 stage leach over a period of 90 days.

 

Although the studies indicate that the process route and design are well suited to the Cap-Oeste ore the current oxide ore reserves are considered to be insufficient to advance the project at this stage.

Further test work will be undertaken on the neighbouring high grade COSE deposit to evaluate the possibility of extracting the gold and silver through agglomeration of a gravity tails product for inclusion with the Cap-Oeste oxide ore to increase the available ounces of cyanide leachable gold and silver.

 

Exploration efforts are currently aimed at increasing the oxide or cyanide extractable oxide resource base.

 

Ends

About Patagonia Gold

Patagonia Gold Plc is a mining company that seeks to grow shareholder value through exploration, development and production of gold and silver projects in the southern Patagonia region of Argentina. The Company is primarily focused on three projects: the flagship Cap-Oeste/COSE project, the La Manchuria project and the Lomada heap leach project, which is generating free cash flow. Patagonia Gold, indirectly through its subsidiaries or under option agreements, has mineral rights to over 220 properties in several provinces of Argentina and Chile, and is one of the largest landholders in the province of Santa Cruz.

Matthew Boyes, (BSC. Geology, Fellow AusIMM) Chief Operating Officer for Patagonia Gold PGSA and a qualified person as defined in Canadian National Instrument 43-101, has reviewed and verified all scientific or technical mining disclosure contained in this press release.

 

Contact Information

Bill Humphries, CEOPatagonia Gold PlcTel: +44 (0)20 7409 7444

David Bick / Mark LongsonSquare 1 Consulting+44 (0)20 7929 5599

Angela Hallett/James SpinneyStrand Hanson LimitedTel: +44 (0)20 7409 3494

Jeremy Stephenson/Stewart DicksonCantor Fitzgerald EuropeTel: +44 (0)20 7894 7000

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCKMGMFKRVGKZM
Date   Source Headline
3rd Nov 20177:00 amRNSProduction Guidance and Resource Update
11th Oct 20177:24 amRNSCalcatreu Option Extension
27th Sep 20177:00 amRNSHalf Yearly Financial Statements
19th Sep 20171:18 pmRNSInterim Results Announcement Date Replacement
19th Sep 20177:00 amRNSInterim Results Announcement Date
31st Aug 20171:00 pmRNSCap-Oeste and Exploration Update
10th Jul 20177:00 amRNSOperations Update for Cap-Oeste
1st Jun 20177:00 amRNSCompletion of the Disposal of COSE
5th May 20177:00 amRNSOperations Update
2nd May 20177:00 amRNSChange of Registered Office Address
27th Apr 201712:40 pmRNSResult of AGM
25th Apr 20177:00 amRNSDisposal of COSE and Option
19th Apr 20173:20 pmRNSHolding(s) in Company
28th Mar 20177:00 amRNSFinal Results for the Year Ended 31 December 2016
23rd Dec 20167:00 amRNSCap-Oeste Project Operations Update
7th Nov 20167:00 amRNSUruguay Exploration Update
31st Oct 20167:00 amRNSCap-Oeste Project Operations Update - REPEAT
28th Oct 20165:39 pmRNSCap-Oeste Project Operations Update
29th Sep 20167:00 amRNSHalf Yearly Financial Statements
28th Sep 20167:00 amRNSInterim Results Announcement Date
30th Aug 20167:00 amRNSCap-Oeste Project and Lomada Operations Update
1st Jul 201612:00 pmRNSBoard Changes / Issue of shares to Directors
1st Jul 20167:00 amRNSChange of Broker
16th Jun 20162:05 pmRNSSecond Price Monitoring Extn
16th Jun 20162:00 pmRNSPrice Monitoring Extension
25th May 20169:00 amRNSHolding(s) in Company
20th May 20167:00 amRNSFurther Subscription
10th May 20163:20 pmRNSResult of Open Offer and General Meeting
10th May 20163:14 pmRNSResult of AGM
22nd Apr 20167:00 amRNSSubscription and Open Offer
15th Apr 20167:00 amRNSFinal Results
26th Feb 20167:00 amRNSUpdate on Lomada and Cap-Oeste
2nd Feb 20167:00 amRNSTrilogy Earn-In Agreement
6th Jan 20167:00 amRNSFurther re: Trilogy earn-in agreement
23rd Dec 20157:00 amRNSRemoval of tax on gold exports
21st Dec 20157:00 amRNSEconomic & fiscal policy changes in Argentina
24th Nov 20157:00 amRNSLomada Production Update
9th Nov 20157:00 amRNSProposed Earn-In Agreement
26th Oct 20154:40 pmRNSSecond Price Monitoring Extn
26th Oct 20154:35 pmRNSPrice Monitoring Extension
30th Sep 20157:00 amRNSHalf Yearly Report
21st Aug 20157:00 amRNSChange of Registered Office
19th Jun 20157:00 amRNSAdditional Listing/Directors' Shareholdings
10th Jun 20153:52 pmRNSResult of AGM
10th Jun 201510:30 amRNSDirectorate Change
1st Jun 20157:00 amRNSDirectorate Change
15th May 20157:00 amRNSPosting of Annual Report and Notice of AGM
12th May 20152:21 pmRNSCap-Oeste infill drilling update
21st Apr 20157:00 amRNSAppointment of CEO
9th Apr 20157:00 amRNSFinal Results

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.