Liqhobong Diamond Mine Construction Update

20 Jul 2016 07:00

RNS Number : 6712E
Firestone Diamonds PLC
20 July 2016
 

20 July 2016

 

Firestone Diamonds plc

("Firestone", the "Group" or the "Company") (AIM: FDI)

 

Liqhobong Diamond Mine Construction Update

 

Firestone Diamonds plc, the AIM-quoted diamond development company, is pleased to announce an update on construction activities at its Liqhobong Diamond Mine ("Liqhobong" or the "Project") as at the end of June 2016. Liqhobong is owned 75% by Firestone and 25% by the Government of Lesotho.

 

Highlights as at the end of June 2016

· Construction 85% complete, ahead of revised target of 81%

· Plant 18% commissioned, ahead of target

· Initial production now expected in early Q4 2016, with full production rates expected to take at least six months

· Revised capital budget of ZAR2.1 billion, remains within the original project budget of US$185.4 million

· Production guidance for financial year ending June 2017 between 1.8 - 2.0 million tonnes ("Mt")

· First diamond sales anticipated in January 2017

· Zero lost time injury record maintained, with approximately 2.6 million man hours worked

 

Stuart Brown, Chief Executive Officer, commented:

 

"I am pleased to report that construction activities at the Liqhobong Diamond Mine have continued to progress well over the last quarter. As at the end of June, construction was ahead of schedule and initial production is now expected in early Q4 2016. The Company remains fully financed throughout its ramp-up period and expects to host its first diamond sale in January 2017.

 

"The excitement and momentum is building nicely and we are looking forward to the recovery of our first carats in Q4 2016."

 

Project Construction

 

Liqhobong has continued the momentum achieved during Q1 2016 and as at 30 June 2016 the Project was 85% complete and ahead of schedule. The strong performance is once again attributed to hard work from the dedicated Project and construction teams. Pleasingly, the Project team have been able to accelerate the commissioning phase of Liqhobong and at the end of June this was 18% compete. As a result, the Company now anticipates initial production to commence in early Q4 2016.

 

The remaining 15% of the Project relates to the continued completion of the final equipment installation together with the installation of the electrical and control cabling and is expected to be completed early in Q4 2016.

 

Liqhobong has fully harvested its water requirements for its first year of production, with in excess of 400,000 cubic metres of water on site.

 

Currently the Company's total workforce at Liqhobong stands at 779 (March: 795) which includes both employees and contractors. The operational staffing of the mine is progressing well with all senior positions filled and the remaining required positions to be completed prior to the start of production ramp-up.

 

In May 2016 the Company received approval for the updated Environmental Management Plan and the revised standards and targets have been implemented. In addition, the Company is working alongside the local community to implement agreed local community improvement and sustainability projects.

 

 

Health & Safety

 

Firestone continues to impose a rigorous safety policy and is very pleased to have maintained its Lost Time Injury free record, with approximately 2.6 million man hours worked as at the end of June 2016. This is a remarkable achievement and the entire Project team on site is committed to ensuring that all members of the team start and end their shifts safely.

 

 

Financial

 

As at the end of June 2016, the Project was 85% complete, against the revised target of 81%. The Project also remains within the original US$185.4 million budget and as at 30 June 2016, ZAR 1.6 billion (US$142 million) or 76% had been spent on the Project against the revised capital budget of ZAR2.1 billion. The cash on hand at the end of June 2016 was US$10.7 million and the Company also had US$39.0 million available pursuant to the ABSA debt facility, resulting in forecast headroom available to the Company of approximately US$9.0 million as at the end of December 2016. This does not include the US$15.0 million standby facility available to the Company.

 

 

Production Guidance

 

Following the successful construction progress achieved in Q2 2016, Liqhobong is expected to commence initial production in early Q4 2016. Once initial production has started, Firestone anticipates that the ramp up process to full nameplate capacity, being 3.6 million tonnes per annum or 500 tonnes per hour to recover up to 1 million carats per annum, will take at least six months.

 

During commissioning, ore from mixed low grade stockpiles and diluted ore from the main pit will be processed through the plant. The variability of this ore will influence the recovery of run of mine carats. It is difficult at this stage to predict the average dollar per carat expected for early sales of diamonds. The Company expects to treat between 1.8 and 2.0 Mt of ore during the financial year ending June 2017. Within this period, it is estimated that between 380,000 and 450,000 carats will be produced at Liqhobong. Costs are projected to be in the region of US$12 to US$14 per tonne processed.

 

 

Diamond Sale

 

Firestone has scheduled its first diamond sale for January 2017, in Antwerp. Thereafter the Company will aim to host two sales per quarter. As mentioned, during the initial stages of commissioning and ramp-up, the plant will be treating lower grade ore and not run of mine production. It is expected that with a purpose built plant and mining larger volumes of kimberlite across the main pit, we will get a better understanding of the occurrence and value of large stones over time.

 

 

Image Gallery

 

Each month the Company updates its media gallery to include images to illustrate the Project's progress and these can be found on Firestone's website: www.firestonediamonds.com/media.

 

For more information contact:

 

Firestone Diamonds plc

+44 (0)20 8741 7810

Stuart Brown

Strand Hanson Limited (Nomad)

+44 (0)20 7409 3494

Stuart Faulkner

Richard Tulloch

James Dance

Macquarie Capital (Europe) Limited (Joint Broker)

Raj Khatri

+44(0)20 3037 2000

Nick Stamp

Mirabaud Securities LLP (Joint Broker)

Rory Scott

+44 (0)20 7878 3360

Ed Haig-Thomas

+44 (0)20 7878 3447

Tavistock (Public and Investor Relations)

+44 (0)20 7920 3150

Jos Simson

+44 (0)7788 554 035

Barney Hayward

 

Background information on Firestone

 

Firestone is an international diamond development company with operations focused on Lesotho. Firestone is currently in the process of developing the Liqhobong Mine Development Project in Lesotho to become a one million carat per annum producer.

 

Lesotho is emerging as one of Africa's significant new diamond producers, and hosts Gem Diamonds' Letseng Mine, Firestone's Liqhobong Mine, as well as Namakwa Diamonds' Kao Mine.

 

For more information please visit: www.firestonediamonds.com.

 

**ENDS**

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCRLMBTMBJBTTF
Date   Source Headline
11th Jan 20193:32 pmRNSIssue of Shares re: Eurobond
18th Dec 20182:59 pmRNSUpdate on Option Agreement for Botswana operations
14th Dec 20187:00 amRNSRecovery of 46 carat white gem diamond
28th Nov 201811:40 amRNSResults of AGM
29th Oct 20187:00 amRNSQuarterly Update on Operations
25th Oct 20184:04 pmRNSIssue of shares re: Eurobond
28th Sep 20187:00 amRNSFinal results for the year ended 30 June 2018
2nd Aug 20184:48 pmRNSIssue of shares re: Eurobond
23rd Jul 20187:00 amRNSQuarterly Update and Guidance for FY 2019
12th Jul 20187:00 amRNSBoard Appointment
6th Jul 20187:16 amRNSHolding(s) in Company
5th Jul 20187:00 amRNSBoard changes
14th May 20187:00 amRNSAppointment of CEO
19th Apr 20187:00 amRNSQuarterly Update on Operations
17th Apr 201811:27 amRNSIssue of shares
27th Mar 20187:00 amRNSHalf-year Report
19th Jan 201812:22 pmRNSIssue of Equity
17th Jan 20187:00 amRNSQuarterly Update on Operations
10th Jan 20188:04 amRNSHolding(s) in Company
29th Dec 201712:27 pmRNSResult of AGM
28th Dec 20172:09 pmRNSHolding(s) in Company
20th Dec 201712:17 pmRNSResults of General Meeting and Open Offer
20th Dec 20177:00 amRNSSale of BK11 Asset - Extension of Option Period
1st Dec 201710:22 amRNSResults of Firm Placing & Placing, Notice of GM
1st Dec 20177:01 amRNSFirm Placing, Placing and Open Offer, etc
1st Dec 20177:00 amRNSFinal Results
23rd Oct 20177:00 amRNSQuarterly Update on Operations
17th Oct 20177:00 amRNSIssue of shares
9th Oct 20177:00 amRNSChange of Adviser
3rd Oct 20177:00 amRNSRecovery of 134 carat gem-quality diamond
29th Sep 20177:00 amRNSDiamond Sales Results and Operational Update
6th Sep 20177:00 amRNSABSA Debt Facility Update
8th Aug 20177:00 amRNSProduction Guidance for FY 2018
10th Jul 20172:18 pmRNSIssue of shares
22nd Jun 20177:00 amRNSAmendment to Standby Facility
31st May 20177:00 amRNSHolding(s) in Company
24th May 20177:00 amRNSOption Agreement in respect of Botswana operations
4th May 20175:20 pmRNSHolding(s) in Company
4th May 20172:31 pmRNSHolding(s) in Company
3rd May 20179:19 amRNSHolding(s) in Company
26th Apr 20177:00 amRNSQuarterly Update
10th Apr 201712:58 pmRNSIssue of shares
5th Apr 20177:00 amRNS110 carat gem-quality diamond recovered
28th Mar 20177:00 amRNSInterim Results
13th Feb 20177:00 amRNSResults of First Diamond Sale
31st Jan 20177:00 amRNSHolding(s) in Company
27th Jan 20171:53 pmRNSIssue of shares
26th Jan 20177:00 amRNSQuarterly Update on Construction & Commissioning
8th Dec 201611:43 amRNSResult of AGM
1st Nov 20167:05 amRNSBoard Changes

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.