Operational Update

27 Feb 2020 07:00

RNS Number : 3204E
Edenville Energy PLC
27 February 2020
 

27 February 2020

 

EDENVILLE ENERGY PLC

("Edenville" or the "Company")

 

Operational Update

 

Edenville Energy Plc (AIM: EDL), the AIM quoted company developing the Rukwa coal project in southwest Tanzania ("Rukwa" or the "Project'), is pleased to provide an update regarding mining operations at Rukwa and the status of discussions with a potential strategic partner (the "Strategic Partner") for the Project.

 

Operational Update

 

Following the receipt of gross proceeds from the £700,000 capital raise, announced on 23 January 2020, progress has been made at the Project site, including:

 

- Reinstatement of an on-site operational advisor with extensive coal experience and historic involvement in the Project;

- A detailed review and assessment of the wash plant has been completed with minor plant modifications being made. The wash plant is now operating again and continuous production is targeted for early March 2020;

- Critical spares including new belts have been ordered which are expected to reduce any future downtime;

- A stockpile of approximately 6,000 tonnes of unwashed run of mine ("ROM") coal, which was mined from the southern pit at Rukwa,has been established adjacent to the wash plant; and

- The region is experiencing one of its wettest "rainy" seasons in many years. Accordingly, as the Directors believe that all economic coal has now been recovered from the southern pit, equipment will shortly be relocated to the northern pit and mining and hauling activities will be undertaken during periods of dryer weather. Based on the Company's previous experiences, the rainy season is expected to end in late April.

 

Update Re Potential Strategic Partner

On the 11 December 2019 the Company announced it was in discussions with a potential strategic partner for the Project (the "Strategic Partner"). The Company confirms that these discussions are progressing and a non-binding heads of terms has been agreed with the Strategic Partner covering a potential asset-level loan, a potential coal mining agreement and a potential coal marketing agreement. The Strategic Partner recently visited the Project and is now conducting due diligence on Edenville's operations. Whilst there is no guarantee that this period of due diligence will lead to a successful outcome for the Company, the Board is encouraged by the progress that has been made to date and looks forward to providing further updates regarding the Strategic Partner as appropriate.

Alistair Muir, CEO of Edenville, commented: "We are encouraged by the progress we have made since the receipt of funds, focusing firstly on re-establishing the workforce and secondly making essential modifications to the wash plant, including the delivery of a critical spares inventory and establishing the interim ROM coal stockpile. We intend to re-establish continuous production at Rukwa, as the weather conditions allow, and look forward to providing further updates regarding progress as appropriate."

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) 596/2014. 

 

For further information please contact:

 

Edenville Energy Plc

Jeff Malaihollo - Chairman

Alistair Muir - CEO

 

+44 (0) 20 3934 6630

SP Angel Corporate Finance LLP

(Nominated Adviser and Joint Broker)

David Hignell

Charlie Bouverat

Abigail Wayne

 

+44 (0) 20 3470 0470

Brandon Hill Capital Ltd

(Joint Broker)

Oliver Stansfield, Jonathan Evans

 

+44 (0) 20 7936 5200

IFC Advisory Limited

(Financial PR and IR)

Tim Metcalfe

Graham Herring

Florence Chandler

+44 (0) 20 3934 6630

 

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDPPUAWPUPUUQM
Date   Source Headline
8th May 201810:30 amRNSNew Company Presentation
27th Apr 20183:25 pmRNSPlacing to raise ?740,000 & Appointment of Broker
6th Mar 20183:04 pmRNSHolding(s) in Company
27th Feb 20188:51 amRNSProject Update
26th Feb 201810:36 amRNSDeputy Minister of Minerals Site Visit
31st Jan 20187:00 amRNSCompany Update
8th Jan 20187:00 amRNSProject Update
23rd Nov 20177:00 amRNSProject update
12th Oct 20178:36 amRNSHolding(s) in Company
10th Oct 20177:00 amRNSCoal Offtake Agreement
9th Oct 20177:00 amRNSStart of Washed Coal Production
4th Oct 20177:00 amRNSSubscription to raise £1.25m
29th Sep 20177:00 amRNSWash plant construction completed
21st Sep 20179:00 amRNSWarrant Exercise
15th Sep 20177:00 amRNSInterim Results
29th Aug 20177:00 amRNSProject Marketing and Construction Update
25th Aug 20178:45 amRNSReplacement - Project Construction Update
25th Aug 20177:00 amRNSProject Construction Update
1st Aug 20177:00 amRNSProject Update
12th Jul 20177:00 amRNSProject Update
5th Jul 20177:00 amRNSTanzanian Legislative Changes
26th Jun 201712:25 pmRNSResult of AGM
26th Jun 20177:00 amRNSAGM Statement
19th Jun 20173:15 pmRNSWarrant Exercise
13th Jun 201711:42 amRNSWarrant Exercise and Director Dealing
31st May 20177:00 amRNSPosting of Accounts and Notice of AGM
30th May 20177:00 amRNSRukwa Coal Project - Update
25th May 20177:00 amRNSFull Year Results
19th May 20177:00 amRNSRukwa Coal Project - Update
19th Apr 20177:00 amRNSRukwa Coal Project - Update
6th Apr 201710:05 amRNSMining Licence Update
30th Mar 20177:00 amRNSProject Update
29th Mar 20177:00 amRNSWarrant Exercise
28th Mar 20173:55 pmRNSGrant of Options
20th Mar 20173:54 pmRNSWarrant Exercise
17th Mar 201710:27 amRNSResult of General Meeting
6th Mar 20177:00 amRNSProject Update
24th Feb 20177:00 amRNSRelinquishment of Uranium Prospecting Licence
23rd Feb 20177:00 amRNSWash Plant Secured
22nd Feb 20174:14 pmRNSNotice of General Meeting
20th Feb 20177:00 amRNSSubscription to raise £2m
7th Feb 20174:07 pmRNSWarrant Exercise
1st Feb 201712:55 pmRNSWarrant Exercise
25th Jan 20172:30 pmRNSWarrant Exercise
23rd Jan 20177:00 amRNSPartnership with Sinohydro Corporation
23rd Jan 20177:00 amRNSIssue of Equity
20th Jan 201712:50 pmRNSHolding(s) in Company
18th Jan 20177:00 amRNSESIA Update
12th Jan 201710:30 amRNSTrial Mining Commences
30th Dec 201612:56 pmRNSHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.