La Parrilla Scalable Development

7 Mar 2016 07:00

RNS Number : 1795R
W Resources PLC
07 March 2016
 

 

 

 

 

 

 

7 March 2016

 

W Resources Plc

("W" or the "Company")

 

 

La Parrilla Scalable Development

 

W Resources Plc (AIM:WRES), the tungsten, copper and gold exploration and development company with assets in Spain and Portugal, is pleased to provide an update on design and development planning for the La Parrilla Tungsten Project following completion of the initial engineering work in Germany.

Metallurgical testing, plant design and expansion planning work has advanced with engineering consultants MBE Coal & Minerals Technology GmbH which has confirmed the La Parrilla plant can be executed in three phases:

1. Initial production will start with the Fast Track Mine ("FTM") at 1,300 tonnes per annum ("tpa") of concentrate, at an estimated cost of US$16m. The FTM is on track for first production in late 2016

2. The FTM will then be scaled up to 2,600 tpa at the low incremental cost of US$6.0m

3. The final Full Mine ("FM") will incorporate ore sorters and duplicate the processing plant expanding the capacity to 5,000 tpa

The wide availability of crushing equipment in Europe has enabled W to design the initial FTM plant with higher installed equipment capacity whilst simultaneously achieving substantial cost savings. This allows the Company to install larger capacity from day one that will allow production to be ramped-up by increasing the run hours of the installed equipment. Minor modifications are required to ensure sufficient surge capacity between the jig and concentrator plants remains available during the ramp-up phase of the project. The final expansion to 5,000 tpa of concentrate requires duplication of the pre-concentration and final concentration circuits.

The proposed three-stage configuration allows for low-cost incremental expansion to supply the expected steady growth in the European, US and Middle East markets.

Michael Masterman, Chairman of W Resources said: "La Parrilla is a very capital efficient project that can be quickly scaled to significantly higher production rates at low incremental expansion costs. Plans remain on track to complete the FTM in 2016. Within this design we have embedded the expansion capability to double capacity to 2,600 tpa through oversizing of the crusher and jigs circuit. The scalability of the project adds significant flexibility, NPV and optionality to La Parrilla. Development work is progressing on track and financing discussions for the first phase are advancing."

 

Enquiries:

W Resources Plc

Michael Masterman

T: +44 (0) 20 7193 7463

www.wresources.co.uk

Grant Thornton UK LLP

Colin Aaronson / Jen Clarke / Harrison Clarke

T: +44 (0) 20 7383 5100

SI Capital - Joint Broker

Andy Thacker / Nick Emerson

T: +44 (0) 1483 413500

www.sicapital.co.uk

Gable Communications

Justine James

T: +44 (0) 20 7193 7463

M: +44 (0) 7525 324431

Northland Capital Partners - Joint Broker

John Howes / Abigail Wayne (Corporate Broking)

T: +44 (0) 20 7382 1100

www.northlandcp.co.uk

About La Parrilla

The La Parrilla project site is situated in the Extremadura region of southwest Spain, in the Provinces of Caceres-Badajoz, approximately 310 km southwest of Madrid. The site has exceptional infrastructure in place, which is accessed directly from the highway along a 3 km asphalt road and is serviced by electricity and water. The project comprises a tungsten mine and a tungsten tailings project. The mineral resource estimated by Golder in February 2016 at 0.04% WO3 cut-off grade is 51 million tonnes at 0.096% WO3 and 0.108 Sn, making it one of the largest tungsten deposits in the western world.

Technical information in this report and on the W website has been prepared in accordance with the JORC Code and approved for inclusion by Mr Fernando de la Fuente, is a 'qualified person' in respect of the AIM Rules for Companies with over 41 years' experience in the Exploration and Mining Geology industry. Mr de la Fuente holds a B.Sc. in Geology and an MSc in Geology from the University of Granada in Spain. He is also a member of the Spanish College of Geologists (Number 49), the Spanish Society of Mineralogy, founder member of the Spanish Society of Geology, member of the Spanish Association of Applied Geology to Mineral Deposits, member of the Society for Mining, Metallurgy and Exploration, Inc., member of PDAC.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCKMGGFNVDGVZM
Date   Source Headline
20th Nov 20187:00 amRNSLa Parrilla Commences Tungsten Tin Production
12th Nov 20184:40 pmRNSSecond Price Monitoring Extn
12th Nov 20184:35 pmRNSPrice Monitoring Extension
15th Oct 20187:53 amRNSNew Website
1st Oct 201811:30 amRNSHansource Investments Reinstated
18th Sep 20187:00 amRNSHigh Grade Tungsten Intersections at Regua
17th Sep 20187:00 amRNSNon-Executive Director Appointments
13th Sep 20187:00 amRNSLa Parrilla Project Update
10th Sep 20187:00 amRNSHalf-year Report to 30 June 2018
5th Sep 20187:00 amRNSRio Tinto & Lundin Mining Execs Strengthen Team
8th Aug 20185:33 pmRNSDirector/PDMR Shareholding
31st Jul 20187:06 amRNSDirector/PDMR Shareholding
13th Jul 20187:00 amRNSThick Gold intersections and high grades
29th Jun 201811:30 amRNSResult of AGM
27th Jun 20187:00 amRNSSteelwork & Equipment Deliveries at La Parrilla
7th Jun 20187:00 amRNSHigh-grade Tungsten at Tarouca
1st Jun 20187:00 amRNSNotice of AGM
1st Jun 20187:00 amRNSFinal Results for the Year Ended 31 December 2017
31st May 201811:30 amRNSReplacement: Final Draw Down Completes US$35m
30th May 20187:00 amRNSFinal Draw Down Completes US$35m BlackRock Funding
17th May 20187:00 amRNSUpdated Presentation - May 2018
3rd May 201812:26 pmRNSHansource Investments Limited
1st May 20187:13 amRNSS?o Martinho Drilling Programme Commences
26th Apr 20187:00 amRNSCompletion of Tarouca RC Drilling Programme
18th Apr 20187:00 amRNSInvestor Presentation - 14 May
17th Apr 20188:46 amRNSTungsten, Copper and Gold Update
5th Apr 20188:52 amRNSPlacing to Raise £1.5 million
3rd Apr 20187:44 amRNSEarthworks Commence at La Parrilla
28th Mar 20187:00 amRNSEUR5.3m Grant Awarded for Development- La Parrilla
27th Feb 20187:00 amRNSRegua Land Purchase Clears Last Hurdle for Develop
23rd Feb 20187:00 amRNSMajor Offtake Agreements
21st Feb 201811:29 amRNSExercise of Warrants
16th Feb 20187:00 amRNSUS$35m Loan Facility Finalised with BlackRock
1st Feb 20187:00 amRNSFinancing update - La Parrilla term loan
17th Jan 20182:30 pmRNSHolding(s) in Company
10th Jan 20187:00 amRNSConcentrator Contract awarded
12th Dec 20177:00 amRNSFinancing Update: US$30m Term Loan
31st Oct 20177:00 amRNSHolding(s) in Company
6th Oct 20177:00 amRNSPlacing to Director to Raise an Additional £100k
5th Oct 20178:13 amRNSEquity fundraising
27th Sep 201712:25 pmRNSHalf Year Results for the Six Months Ended 30 June
27th Sep 20178:57 amRNSIssue of Shares
20th Sep 20177:00 amRNSTarouca Exploration Licence Extension Approved
14th Sep 20174:08 pmRNSHolding(s) in Company
12th Sep 20177:00 amRNSInvestor Event - 19 September 2017
25th Aug 20175:35 pmRNSFinancial Investment Decision Report and Presentat
25th Aug 201711:01 amRNSFinancial Investment Decision Report & Debt Update
7th Aug 20177:00 amRNSCrusher Contract Awarded to Metso
21st Jul 20179:54 amRNSChange of Registered Office Address
26th Jun 201712:58 pmRNSResults of Annual General Meeting

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.