Drilling Update

28 Jan 2013 07:00

RNS Number : 4552W
W Resources PLC
28 January 2013
 



 

 

 

 

 

28 January 2013

 

 

W Resources Plc

("W" or the "Company")

 

Drilling Update - La Parrilla IP07, IP08 and IP09

 

W Resources (AIM:WRES), the tungsten and gold exploration and development company, announces the latest update on drilling at its La Parrilla tungsten project, located in southwest Spain, in which it has an exclusive option to purchase a 100% interest.

Drilling of the extension of the La Parrilla ore body is now complete, drill results are being progressively received and W expects to complete the compilation of a new JORC compliant resource estimate in the second quarter of 2013.

Assay results have been confirmed for core Holes 7, 8 and 9 of the extended La Parrilla drilling programme. Key highlights include 8 metres at 0.29% Tungsten Trioxide (WO3) in hole 9, three times the average grade of the current La Parrilla resource in hole 9. Holes 7, 8 and 9 were drilled to final depths of 200.0m, 200.0m and 250.50m and are located 640m, 470m and 200m, respectively, to the northwest of the main ore body and continue the series of strong results from the extension drilling programme.

Chairman of W, Michael Masterman, commented: "The Board continues to be encouraged by the results on the extension drilling programme, with the process of further delineating a more significant increase in both the grade and tonnage of the resource at La Parrilla nearing completion. Drilling has been completed on budget and on schedule and we expect positive results from the re-estimation of the resources incorporating these results."

With the final approval for the La Parrilla tailings project granted by the Mining Department of the regional authority of the Junta de Extremadura, (announced 22 January) the Company is making good progress towards first production in H2 2013.

W has completed 11 holes on its drilling programme with assays received on holes 1-9. The full weighted averaged results of Holes 7, 8 and 9 are shown in the tables below:

DRILL HOLE IP-09 (VERTICAL) 250.50 m LONG

FROM

TO

INT

TRUE THICKNESS

WO3 %

Sn %

86.00

94.00

8.00

6.93

0.286

0.011

118.00

122.00

4.00

3.46

0.063

0.089

184.00

200.00

16.00

13.86

0.081

0.007

228.00

236.00

8.00

6.93

0.114

0.011

 

 

 

 

 

DRILL HOLE IP-08 (VERTICAL) 200.0 m LONG

FROM

TO

INT

TRUE THICKNESS

WO3 %

Sn %

37.00

43.00

6.00

3.00

0.132

0.003

113.00

119.00

6.00

2.05

0.098

0.005

145.00

151.00

6.00

5.46

0.053

0.004

 

 

 

 

DRILL HOLE IP-07 (VERTICAL) 200.0 m LONG

FROM

TO

INT

TRUE THICKNESS

WO3 %

Sn %

69.00

77.00

8.00

5.68

0.017

0.010

109.00

117.00

8.00

4.56

0.041

0.009

109.00

111.00

2.00

1.14

0.145

0.009

 

The weighted average grades have been calculated for intersections through mineralised envelopes defined by quartz veining and no cut off grade has been used.

 

A detailed map of the La Parrilla site including the drill hole locations can be found on the Company's website at http://www.wresources.co.uk/projects/la-parrilla/

 

Enquiries:

W Resources Plc

Grant Thornton Corporate Finance - Nomad

Michael Masterman

Gerry Beaney / Melanie Frean / Jen Clarke

T: +44 (0) 20 7193 7463

T: +44 (0) 20 7383 5100

 www.wresources.co.uk

Simple Investments - Broker

Gable Communications

Andy Thacker / Nick Emerson

Justine James

T: +44 (0) 1483 413500

T: +44 (0) 20 7193 7463

www.simple-investments.co.uk

M: +44 (0) 7525 324431

 

About La Parrilla

The La Parrilla project site is situated in the Extremadura region of southwest Spain, in the Provinces of Caceres-Badajoz, approximately 310 km southwest of Madrid. The site is accessed directly from the highway along a 3km asphalt road and is serviced by electricity and water. The project comprises a tungsten mine and a tungsten tailings project. The historic mine resource estimated by SRK in 2008 is 36.0m tonnes at 0.09% WO3, making it one of the largest tungsten deposits in the western world.

The technical design of the La Parrilla tailings project has now been finalised and the final approval has been granted by the Mining Department of the regional authority of the Junta de Extremadura. Annual plant feed will be 330,000 tonnes and annual production is anticipated to be 28,000 MTU Tungsten (W) and 26 tonnes Tin (Sn), which will deliver over €7million per annum in revenue at current tungsten and tin prices. The tailings project is expected to be in production in H2 2013.

The price of tungsten has increased rapidly over the last 3 years by more than double. The La Parrilla tailings deposit and tungsten mine development offer a low cost, high margin resource development opportunity for W Resources.

 

Sampling, Assaying and Quality Assurance / Quality Control (QA/QC) Measures

Drill sample intervals are reported as metres (m) down hole. True widths of mineralised intersections have been calculated assigning an average dip of the mineralised zones of 45º-55º for hole IP-07, 60º for hole IP-08 and 30º for hole IP-09. All drill core is transported by the Company personnel from drill site to a nearby secure storage facility for logging, by an experienced geologist, and sampling. The core is halved using a rotary diamond blade core saw, with one half of the core sent for analysis, while the other half is retained in the core boxes for reference. Sampling is mainly carried out over two-metre intervals.

All half-core samples are sent for preparation to ALS Minerals facility in Seville (Spain). The resulting pulps are shipped to their laboratory in Vancouver (Canada) for assay using the ME-MS81 method (38 elements by lithium borate fusion and ICP-MS). Samples exceeding the upper detection limit (10,000 ppm W) are re-assayed by the lithium borate fusion and XRF determination ME-XRF10 method. Tungsten assays are reported by ALS Minerals as W and converted to WO3 using a factor of 1.26108.

Reference samples (blanks, duplicates and certified standards) are routinely inserted in each sample batch as quality control measure in addition to the laboratory's own internal QA/QC standards and duplicates.

W Resources changed its name from Caspian Holdings plc in July 2012 to align with its revised strategy focussing on projects in the mining sector.

Technical information in this report has been prepared in accordance with the JORC Code and approved for inclusion by Mr Fernando de la Fuente, who is a "qualified person" in respect of the AIM Rules for Companies with over 37 years experience in the Exploration and Mining Geology industry. Mr de la Fuente holds a B.Sc. in Geology and a MSc in Geology from the University of Granada in Spain. He is also a member of the Spanish College of Geologists (Number 49), the Spanish Society of Mineralogy, founder member of the Spanish Society of Geology, member of the Spanish Association of Applied Geology to Mineral Deposits, member of the Society for Mining, Metallurgy and Exploration, Inc., member of PDAC.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLBRMBTMBTTBBJ
Date   Source Headline
28th Mar 20123:20 pmRNSIssue of Equity
7th Feb 20122:50 pmRNSCaspian announces £460,000 Placing
6th Feb 20129:30 amRNSOption Extension at La Parrilla Tungsten Mine
11th Jan 20127:00 amRNSDrilling Campaign Commences at La Parrilla
30th Dec 20117:00 amRNSCaspian Completes £210,000 Placing
19th Dec 201111:00 amRNSResult of General Meeting
30th Nov 20117:00 amRNSCaspian to acquire La Parrilla Tungsten Project
9th Sep 201111:48 amRNSHalf Yearly Report
1st Jul 201111:28 amRNSResult of AGM
24th Jun 201110:06 amRNSCaspian Completes £80,000 Placing
10th Jun 20117:00 amRNSAnnual Report and Notice of AGM
12th Apr 20114:51 pmRNSHolding in Company
29th Sep 20107:00 amRNSHalf Yearly Report
19th Jul 20104:50 pmRNSHolding in Company
9th Jul 201011:47 amRNSHolding in Company
7th Jul 20105:38 pmRNSDirector Shareholding
29th Jun 201011:18 amRNSResult of AGM
22nd Jun 201011:57 amRNSHolding in Company
14th Jun 20104:25 pmRNSOperational Update
14th Jun 20104:25 pmRNSCaspian Completes ?200,000 Placing
8th Jun 20103:07 pmRNSNotice of AGM and Annual Report
24th May 201011:00 amRNSFinal Results
9th Apr 20107:00 amRNSTrading Update
22nd Dec 20097:54 amRNSFirst Oil Shipment in Kentucky
30th Oct 20094:19 pmRNSIssue of Shares
12th Oct 20095:44 pmRNSStatement Regarding Share Price Movement
30th Sep 20093:45 pmRNSInterim Results
10th Jul 200911:54 amRNSTrading Update
29th Jun 200912:51 pmRNSResult of AGM and Issue of Equity
3rd Jun 20095:14 pmRNSCircular to Shareholders and Notice of AGM
28th May 20093:23 pmRNSIssue of Shares
22nd May 20093:29 pmRNSFinal Results
22nd May 20093:00 pmRNSDebt for Equity Swap Agreement
29th Apr 20099:23 amRNSTrading Update
11th Feb 200912:33 pmRNSKazakhstan Court Case Update and Trading Update
14th Jan 200912:47 pmRNSCaspian Completes ?42,000 Placement
14th Jan 20098:43 amRNSCaspian wins Initial Kazakhstan Court Case
25th Nov 200812:09 pmRNSCaspian Completes ?50,000 Placement
7th Nov 20088:42 amRNSDirectorate Change
26th Sep 200811:48 amRNSInterim Results
18th Sep 20087:00 amRNSExpands Black Gold Lease Holdings in Irvine Field
1st Sep 200812:52 pmRNSZhengeldy Regulatory Update
4th Aug 200811:27 amRNSResult of AGM
25th Jul 20087:00 amRNSDirector Shareholding
17th Jul 20081:51 pmRNSHolding in Company
9th Jul 20088:30 amRNSHolding in Company
8th Jul 200810:44 amRNSFuther Expansion into the USA
27th Jun 20088:00 amRNSApproval to Restart Productio
27th Jun 20087:00 amRNSAnnual Report and Accounts
28th May 20089:01 amRNSPlacing and USA Lease Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.