DFS defines world-class fertilizer business

17 Mar 2016 07:00

RNS Number : 3664S
Sirius Minerals Plc
17 March 2016

17 March 2016

Sirius Minerals Plc

DFS defines world-class fertilizer business

DFS defines framework for production capacity of 20 million tonnes per annum ("Mtpa") with initial installed capacity of 10Mtpa

Project net present value ("NPV") of US$15 billion today at a 10% discount rate

Project NPV rising to US$27 billion upon commencement of production

Project after-tax debt-free internal rate of return ("IRR") of 26%

Annual operational EBITDA ranging between US$1 and 3 billion through various volume and price outcomes

High margin business model with average cash operating costs estimated at US$27.2 per tonne, delivering industry leading cash margins of 70 to 85%

Two stage financing plan with stage 1 comprising US$1.63 billion and stage 2 comprising US$1.93 billion (total US$3.56 billion) for installation of 10Mtpa capacity

Funding plans well developed to deliver tailored financing package

First product expected in 2021 followed by completion of fit out and ramp-up with 10Mtpa rate anticipated in 2023

The Directors of Sirius Minerals Plc (AIM: SXX, OTCQX: SRUXY) ("Sirius" or the "Company") announce the material findings from the Definitive Feasibility Study ("DFS") for its North Yorkshire polyhalite project ("the Project").

A detailed DFS presentation has been placed on the Company's website and a webcast of that presentation is available at www.siriusminerals.com. The Company will be holding an analyst presentation today at 3pm (GMT). Further details can be obtained from sirius@tavistock.co.uk.

Chris Fraser, Managing Director and CEO of Sirius, comments:

"The business that is created from this Project will sit as a world leader in the fertilizer industry based here in the UK. It is expected to have a low operating cost structure, high margins and a very long asset life in one of the most business friendly, stable and dynamic economies in the world.

"In delivering this Project we can create thousands of jobs in North Yorkshire and Teesside, deliver billions of pounds of investment to the UK and put the country at the forefront of the multi-nutrient fertilizer industry.

"The DFS represents the blueprint to bring this global fertilizer business into large-scale production and successfully delivers on the core strategic vision of the Company to become a major low cost producer of multi-nutrient fertilizers.

"Work is advancing with our financing partners globally to bring together the pieces of the initial financing of this Project. This process is expected to take a number of months but certain parts of the early construction activity, such as highways upgrades, are commencing soon to facilitate an efficient start of the Project."

DFS compilation process

The DFS was prepared between 2014 and 2016 by a number of industry leading specialist consultants and contractors under the management of the Company's in-house team and Bechtel, as project management study consultant. Bechtel coordinated the compilation of the DFS including compiling the cost estimate, the schedule and the risk assessment. The other consultancy firms involved in the various areas of the DFS preparation were:

Geology & Mining - SRK

Environment - Royal Haskoning DHV

Shafts - Worley Parsons (RSA)

Mineral transport system ("MTS") - Arup

Materials handling facility ("MHF") - K Home International

Port - Royal Haskoning DHV

Implementation - Bechtel

A short biography of each consultancy can be found at the end of the RNS.

Business strategy

A number of strategic decisions have been made by the Company in setting the framework for the DFS and for the business, ensuring maximum value can be extracted from its exceptional resource, including:

Adopt a disruptive market penetration strategy - make the product widely available through established distribution channels;

Install large production capacities to capitalise on the value opportunity created by the unique nature of the large scale high quality polyhalite deposit in North Yorkshire;

Design sustainably low cash operating costs driven by resource quality and core infrastructure implementation decisions;

Select quality over cost where it leads to either reduced operational risk or operating cost; and

Mitigate risk where possible through strategy, design, or implementation approach.

Disruptive market penetration strategy

Detailed independent studies and direct engagement in the fertilizer market over the last five years has confirmed the very large opportunity for bulk high quality multi-nutrient fertilizers like the Company's POLY4 product. The size of the market opportunity is framed in three key areas:

Substitution of existing products in the market;

Market growth; and

Premium performance.

Independent analysis by groups such as CRU Strategies and Fertecon have assessed the substitute market opportunity for polyhalite to be between 30 and 50Mtpa. These independent assessments however did not take into account the longer-term growth within the different sectors of demand or factor in any value for premium performance over that of the specific substitute. The Company believes the potential aggregate substitution market for polyhalite could be in excess of 300Mtpa.

The Company has identified multiple market growth opportunities in both high-value crops and broad acre crops. 32% of potassium used in the world today is used on chloride sensitive crops, but only 9% of the world's potassium supply is currently chloride free. This represents an incremental opportunity of circa 70Mtpa of POLY4.

The Sulphur Institute estimates a world plant nutrient sulphur deficit. This could represent a potential demand for 60Mtpa of polyhalite in order to address the imbalance. In addition to these significant opportunities, a number of key agricultural regions are magnesium deficient, thereby representing further market growth opportunities for POLY4.

The Company's agronomic studies undertaken over the last four years have confirmed the importance and value of polyhalite as a premium multi-nutrient fertilizer. Demand for multi-nutrient fertilizers continues to grow and outpace that of the underlying straight products due to the inherent efficiencies of having more nutrients in a single product and the natural agronomic synergies available from products like POLY4. Crop trials undertaken on broad acre crops (corn, soybean, wheat and sugarcane) have consistently demonstrated POLY4's premium performance over potassium sources such as MOP. These four crops alone could represent a potential global demand of over 200Mtpa.

Existing well established and comparable multi-nutrient products command a significant premium to the nutrient sum-of-the-parts. Analysis of some of these comparable products reveals a volume weighted average premium of approximately 64%. The Company's base case polyhalite price path is linked to the initial discounted pricing mechanism in the current offtake agreements. Over time, as the performance of POLY4 becomes more widely known and available, and the initial offtake agreement discount pricing mechanisms begin to unwind, prices are expected to trend towards nutrient parity.

The DFS assumes average real prices for the first 10 years of production of US$166/t (real 2016) and average mine life equivalent prices of US$186/t (real 2016). The initial pricing range is based on CRU's nutrient forecasts during the first 10 years of production and calculated using the pricing mechanisms included in the offtake agreements already executed. After this period and as foundation offtake agreements are replaced with new offtakes, a period of real price growth is assumed such that the price of POLY4 trends to a level consistent with the sum of its parts.

The Company has to-date signed take or pay offtake agreements for 3.6Mtpa of the initial production for the first 5 to 10 years of production. In addition it has entered into various other commitments that bring the total volume allocated to customers (including customer expansion options) to 7.9Mtpa. The Company is confident that it will be successful in securing further commitments during the construction phase.

High volume

The initial installed capacity of the total Project as defined in the DFS is 10Mtpa. This is consistent across the Project however each component has different embedded capacities from the initial installation, all of which are readily scalable to 20Mtpa.

The Company's intention is to implement three phases of volume growth:

Initial development - initial installation of 10Mtpa of capacity across the Project;

Incremental expansion - expansion to 13Mtpa to utilise the hoisting capacities and to the current approved production level; and

Final capacity expansion - taking all installed capacities to 20Mtpa.

The current approvals for the Project enable the installation of the core infrastructure that delivers the capability of 20Mtpa. Currently there is a limit of 13Mtpa of production imposed by a planning condition on the North York Moors National Park Authority approval. The Company is confident that, given the expansion to 20Mtpa will be largely achieved through utilising the infrastructure constructed for the initial capacity, there will be limited environmental impact arising from the tonnage increase and therefore an application to vary the planning condition to allow for the increased tonnage would be granted as required.

Table 1: Project capacities by Project Area

Project area

Description

Initial Capacity

Final Capacity

Mining

Combination of continuous and drill and blast mining

Mining fleet consists of four high capacity continuous miners operating in two districts

Drill and blast district added in the third year of production

10Mtpa

20Mtpa

Shafts

13.4Mtpa across two winders

Second winder added in the second year of production

Ventilation upgrades for greater than 10Mtpa production rate

Moving to 20Mtpa requires sub-surface connection of the MTS shaft to the mine and installation of a third winder

13Mtpa

20Mtpa

MTS

System capable of 20Mtpa from commissioning

20Mtpa

20Mtpa

MHF

9.5Mtpa of POLY4 granules and 0.5Mtpa of coarse product

Project economics based on expected 80:20 split for production and sales

10Mtpa

20Mtpa

Port

DFS outlines costs of a greenfield development of a new berth with a single ship loader

Option of third party infrastructure supply adopted for base case

10Mtpa

20Mtpa

Long-life, Low cost

The Project is based on a unique asset in the Company's polyhalite resource in North Yorkshire that has key attributes that enable the Company's business strategies to extract the greatest value for shareholders, including:

The largest and highest grade polyhalite resource in the world, reported using the internationally accepted JORC code;

Consistency and thickness of the orebody - low cost high efficiency bulk mining techniques (US$33.1/t at 10Mtpa and US$27.2/t at 20Mtpa); and

High level of purity (grade) - unlocking the low cost direct multi-nutrient product.

The Project has a Joint Ore Reserves Committee ("JORC") compliant Probable Mineral Reserve of 250 million tonnes of 87.8% polyhalite within an area representing just 1% of the Project area of interest. The Reserve sits within a wider resource area of 2.66 billion tonnes of polyhalite at an average grade of 85.7%. The Company expects to complete further resource definition from underground once operations commence, as is required by the business for its future expansion.

The particular characteristics of the resource that make it amenable to a low-cost bulk mining approach are its thickness and grade. The Reserve has an average thickness of 25 metres and areas within the deposit that are up to 70 metres thick. Thickness and consistency enables high efficiency bulk mining methods to be adopted. The effective 1:1 ore to product ratio combined with large scale bulk mining methods means the Project can produce large volumes of its premium multi-nutrient fertilizer product for very low comparative costs - a key sustainable competitive advantage.

Implementation decisions - lower risk and higher quality

During the scoping and design phase of a project such as this, developers are often faced with key decisions about the balance of capital and operating cost. This trade-off analysis usually relates to the quality of installation and design lives of key components. This is not the approach adopted by Sirius. During the development of the DFS the Company has made a conscious decision to opt for higher quality where it could either:

Enhance the sustainable competitive advantage of low cash operating costs; or

Reduce the risk of implementation delays and capital variation risks.

A key example of this approach is the Company's upgrading of the MTS design specification. Initially this system was scoped as a 'mining roadway' in order to reduce capital costs. During the design process and engagement with the tunnelling contractors it became apparent that a fully segmented tunnel would deliver a solution that was more certain in construction schedule and capital cost, be safer and also deliver a lower operating cost solution for the long-term.

The core infrastructure (deep shafts and MTS) design lives in the DFS are over 50 years. These design decisions were taken to underpin the longevity and efficiency of the mining operations but has resulted in a relatively higher capital cost for those elements. This will ultimately deliver a more sustainable long term competitive advantage for the Project.

Project schedule

The Project schedule can be broken into the following key stages:

1. Site preparation and pre-sink activities (22 months).

2. Main shaft sinking activity (36 months).

The aggregate construction schedule equates to 58 months (4.8 years) to first production. As a reference point, if the Company were to commence scheduled activities in April 2016, then first product would be expected in early 2021 and full ramp-up to the 10Mtpa production rate would be reached in late 2023.

Capital funding requirement

The following table outlines the capital funding requirement of the Project for the Company.

Table 2: Capital funding requirement

US$ million

Mine site development

1,219

Mineral transport system

1,106

Materials handling facility and Port

237

Other infrastructure and facilities

125

Project management (including Owner's Costs)

344

Contingency (including escalation)

445

Working capital and other

88

DFS Capital Funding Requirement

3,565

Key attributes of the capital funding requirement estimates are as follows:

Estimate accuracy range of -10% to +10%;

The capital funding requirement is the capital funding required by the Company to the end of the first quarter in which the Project generates positive net cashflow. On the basis of a mid-2016 commencement the capital funding requirement period extends to 30 June 2022;

The capital funding requirement is net of the estimated costs for mobile mining equipment and outsourced port and handling infrastructure. The Company's expectation is for these items to be funded by third parties and paid for through operating costs:

o All mobile mining equipment assumed to be leased (US$12m during the capital funding period);

o All port related infrastructure (including storage and general buildings as defined in the DFS) are assumed to be constructed under a build own operate arrangement (US$515m during the capital funding period based on the DFS estimated cost of greenfield facilities); and

o An aggregate operating charge of US$7.7/t has been included in the operating cost estimates (at 10Mtpa) to account for the cost of mining equipment and greenfield outsourced infrastructure. Should existing infrastructure be utilised then the level of charge related to the port aspects of the Project would be expected to be lower.

Table 3: Capital requirements post capital funding period (funded from operating cashflow)

US$ million

Capital costs incurred after the capital funding period and during ramp-up to 10Mtpa1

176

Incremental capital from 10Mtpa to 13Mtpa1, 2

367

Incremental capital from 13Mtpa to 20Mtpa1, 2

1,175

Note: 1) Expansion capital costs presented on a real 2016 basis. It is expected that all incremental capital will be funded from operating cashflows. 2) Company estimates developed using the DFS scope and estimate as a basis for estimating the expansion cost.

Operating cost estimate

Operating costs are estimated on a free on board ("FOB") basis to be US$33.1/t at 10Mtpa and US$27.2/t at 20Mtpa (real 2016 - life of mine averages). This includes labour, raw material, reagents, operating supply, maintenance supply, utility, lease and other costs. This cost structure positions the Project as the lowest cost multi-nutrient potassium producer and in the bottom quartile of potassium chloride producers.

Table 4: Operating cost breakdown1

By Area

10Mtpa

US$/t

20Mtpa

US$/t

Mining2

11.1

8.2

Transportation

4.7

4.4

Processing

10.0

9.7

Storage and loading2

6.2

4.4

General infrastructure

1.0

0.5

Total

33.1

27.2

Fixed cost percentage

16%

9%

By Expense Category

10Mtpa

US$/t

20Mtpa

US$/t

Labour

4.8

2.3

Raw materials and reagents

4.8

4.8

Maintenance

5.8

5.8

Utility costs (power, gas, water)

7.9

7.9

Lease costs (including Port capital charges)

7.7

4.6

Other costs3

2.1

1.9

Total

33.1

27.2

Notes: 1) Operating costs are real life of mine average Opex per tonne of production and exclude royalties and sustaining capital expenditure. 2) Includes costs relating to mining equipment leasing and outsourced port infrastructure. 3) Includes consumables, fuels and lubricants, G&A, product realisation charges and allowances.

Project economic analysis

The key assumptions underpinning the financial analysis are as follows:

50 year mine life from first production with no terminal value assumed;

Commencement of scheduled activities on 1 April 2016 (adopted as DFS reference point);

Expansion to 13Mtpa in 2024;

Expansion to 20Mtpa in 2026, capital expenditure funded from operations over the 3 year period prior;

80% granulated and 20% coarse POLY4 production and sales split;

Nominal project cashflows (including associated operating expense of outsourced infrastructure and leased mining equipment) with annual inflation of 2% on prices and costs with initial construction capital cost escalation as per the DFS estimates;

NPVs are after-tax applying a 10% nominal discount rate;

Revenues estimated based on expected FOB prices derived from existing offtake contracts and regional sales forecasts. Average real prices for first 10 years of production US$166/t (real 2016) and average mine life equivalent prices of US$186/t (real 2016);

Total royalties 3% of revenue for minerals rights holders and the York Potash Foundation;

Capital and operating costs translated to USD from the currency of underlying estimates which are predominantly USD and GBP (exchange rate assumed GBP 1 = USD 1.42);

Average sustaining capital expenditure of circa US$20m per annum; and

UK Corporation tax rate legislated to reduce to 18% from 1 April 2020.

Table 5: Project cash forecasts: capital funding period (nominal)

US$ millions

2016

2017

2018

2019

2020

2021

H1 2022

Total

Development Capital

(118)

(418)

(698)

(819)

(776)

(519)

(129)

(3,476)

Revenues

-

-

-

-

-

34

72

106

Opex and other costs1

(46)

(15)

(5)

(7)

(28)

(53)

(33)

(188)

Royalties

-

-

-

-

-

(1)

(2)

(3)

Tax /working capital adj.

-

-

-

-

-

(1)

(2)

(3)

Project Net Cashflow2

(164)

(433)

(704)

(827)

(804)

(540)

(94)

3,565

Notes: 1) Other costs include funding of Section 106 security arrangements. 2) Project Net Cashflow includes operating cash flow and investing cash flow. All financing cash flow items including interest are excluded.

Table 6: Project cash forecasts: Production (10Mtpa) (nominal)

US$ millions

2022

2024

2026

2028

2030

POLY4 Production (Mt)

2

10

10

10

10

Revenues

346

1,777

1,821

1,993

2,410

Opex and other costs

(135)

(356)

(368)

(384)

(395)

Royalties

(10)

(53)

(55)

(60)

(72)

EBITDA

201

1,368

1,399

1,549

1,943

Tax and working capital adjustments

3

(90)

(211)

(253)

(332)

Development Capital

(185)

(16)

(19)

-

-

Sustaining Capital

-

(20)

(16)

(18)

(14)

Project Net Cashflow

20

1,243

1,154

1,279

1,597

Table 7: Project cash forecasts: Production (13Mtpa expansion) (nominal)

US$ millions

2022

2024

2026

2028

2030

POLY4 Production (Mt)

2

13

13

13

13

Revenues

346

2,347

2,421

2,670

3,192

Opex and other costs

(135)

(442)

(458)

(479)

(491)

Royalties

(10)

(70)

(73)

(80)

(96)

EBITDA

201

1,835

1,890

2,111

2,604

Tax and working capital adjustments

3

(167)

(294)

(350)

(448)

Development Capital

(190)

(29)

(19)

-

-

Sustaining Capital

-

(28)

(23)

(22)

(17)

Project Net Cashflow

14

1,610

1,554

1,739

2,139

Table 8: Project cash forecasts: Production (20Mtpa expansion) (nominal)

US$ millions

2022

2024

2026

2028

2030

POLY4 Production (Mt)

2

13

18

20

20

Revenues

346

2,347

3,318

4,176

4,945

Opex and other costs

(135)

(442)

(566)

(659)

(678)

Royalties

(10)

(70)

(100)

(125)

(148)

EBITDA

201

1,835

2,653

3,391

4,118

Tax and working capital adjustments

3

(142)

(422)

(568)

(712)

Development Capital

(291)

(525)

(132)

-

-

Sustaining Capital

-

(33)

(27)

(28)

(20)

Project Net Cashflow

(87)

1,135

2,178

2,794

3,386

Table 9: NPV and IRR across expansion scenarios

DFS

Shaft optimization

Full capacity

10Mtpa

13Mtpa

20Mtpa

NPV at start of construction (US$bn)

6.7

9.6

15.1

Project IRR (%)

20.7%

23.2%

25.7%

Table 10: NPV (US$bn) sensitivity to Capex and Price at 10mtpa

Capex sensitivity

Long-term POLY4 price sensitivity

-20%

-10%

Base

+10%

+20%

-20%

5.1

6.2

7.3

8.3

9.4

-10%

4.9

5.9

7.0

8.0

9.1

Base

4.6

5.7

6.7

7.8

8.8

+10%

4.3

5.4

6.5

7.5

8.5

+20%

4.0

5.1

6.2

7.2

8.3

Table 11: IRR sensitivity to Capex and Price at 10mtpa

Capex sensitivity

Long-term POLY4 price sensitivity

-20%

-10%

Base

+10%

+20%

-20%

21%

22%

24%

25%

26%

-10%

20%

21%

22%

24%

25%

Base

18%

20%

21%

22%

24%

+10%

17%

19%

20%

21%

22%

+20%

17%

18%

19%

20%

21%

Table 12: NPV (US$bn) sensitivity to Capex and Price at full capacity (20mtpa)

Capex sensitivity

Long-term POLY4 price sensitivity

-20%

-10%

Base

+10%

+20%

-20%

11.6

13.7

15.8

17.8

19.9

-10%

11.2

13.3

15.4

17.5

19.6

Base

10.9

13.0

15.1

17.2

19.2

+10%

10.5

12.6

14.7

16.8

18.9

+20%

10.2

12.3

14.4

16.4

18.5

Table 13: IRR sensitivity to Capex and Price at full capacity (20mtpa)

Capex sensitivity

Long-term POLY4 price sensitivity

-20%

-10%

Base

+10%

+20%

-20%

25%

27%

29%

30%

31%

-10%

24%

25%

27%

28%

30%

Base

23%

24%

26%

27%

28%

+10%

21%

23%

24%

26%

27%

+20%

20%

22%

23%

25%

26%

Procurement

The Company has been conducting a tendering exercise for the site preparation, the mine site development scope and the MTS scope in parallel with completing the DFS. This exercise has involved recognised major industry shaft and tunnelling contractors and the designs provide a scheme that is both buildable and cost effective. The tender processes are well advanced and the Company is close to selecting preferred bidders for over 50% of the DFS value. The Company expects there will be further optimisations available as this process moves forward.

Financing plan

It is the Company's stated intention to undertake a staged financing of the Project as the best method to deliver the lowest overall cost of funding for the development. This will be achieved by aligning perceived risks with the most appropriate cost of capital in the various phases of the Project.

Stage 1 Financing - US$1.63bn

Stage 1 financing will cover the entire direct costs of all site preparation, shaft excavations, tunnel caverns and a proportion of the indirect costs, project management and owner's costs and contingency - representing approximately 46% of the capital funding requirement. It is proposed that this will be a combination of equity, either from strategic partners or ordinary equity plus structured debt.

It is the intention of the Company to seek conditional commitments from the structured debt providers first and then to complete the required equity component to satisfy the conditions of the debt commitments. The Company is working closely with its corporate brokers and advisers in relation to the components of the Stage 1 financing.

The Company's goal is to secure this funding as soon as possible to enable construction to commence. Discussions have been underway for a significant period of time with providers of the structured debt and also potential equity investors. Following the release of the DFS the Company will engage in a more detailed formal due diligence process with these key parties to seek to move to binding commitments as quickly as possible.

Stage 2 Financing - US$1.93bn

The Stage 2 financing will fund the remaining capital components of the Project that are lower risk and amenable to lump-sum pricing and defined procurement. It is likely to be a project finance facility or a high-yield senior bond. This financing may or may not include an Infrastructure UK guarantee, for which the Company pre-qualified in September 2015.

Sirius has been working with Societe Generale as financial advisor in relation to the structuring of the Stage 2 financing as a project financing facility. This has included due diligence of the financial model, undertaking debt sizing analysis and production of associated credit metrics. This work has identified that the Project could secure a project debt finance facility with the following indicative terms for the Stage 2 financing (subject to market sounding):

US$2.6bn facility value;

14 year debt facility with amortisation commencing in year seven;

Require the Company to secure sufficient offtake to support the credit analysis; and

Secure lump-sum Engineering Procurement and Construction ("EPC") contractors for substantially all of the remaining Project construction.

The opportunity for export credit agencies and/or Infrastructure UK guarantee scheme participation remains a key part of the Company's financing plan and these options will be explored in further detail as part of the market sounding exercise.

In addition to the work on traditional project finance the Company has also been in discussions with various advisers in relation to the potential for a high yield bond to finance the second stage of the Project. This work has identified that a high yield bond of US$2.5 to 3bn could be raised by the Company to fund the Stage 2 capital requirements.

The Company's cash balance as at 28 February 2016 was 拢25 million.

For further information, please contact:

Sirius Minerals Plc

Investor Relations

Email: ir@siriusminerals.com

Tel: +44 845 524 0247

Joint Brokers

Liberum Capital Limited (NOMAD)

Neil Elliot, Clayton Bush, Jill Li

Tel: +44 20 3100 2222

J.P. Morgan Cazenove

Ben Davies, Jamie Riddell

Tel: +44 20 7742 4000

WH Ireland

Adrian Hadden

Tel: +44 20 7220 1666

Media Enquiries

Tavistock

Jos Simson, Mike Bartlett,

Emily Fenton

Tel: +44 20 7920 3150

About Sirius Minerals Plc

Sirius Minerals is the fertilizer development company focused on the development of its polyhalite project in North Yorkshire, the United Kingdom. It has the world's largest and highest grade deposit of polyhalite, a multi-nutrient form of potash containing potassium, sulphur, magnesium and calcium. Incorporated in 2003, Sirius Minerals' shares are traded on the London Stock Exchange's AIM market. Its shares are also traded in the United States on the OTCQX through a sponsored ADR facility. Further information on the Company can be found at: www.siriusminerals.com.

Sirius Minerals' consultants

SRK

SRK is a mining consultancy that provides professional technical services to the mining and metals sector, encompassing multi-disciplinary technical studies and due diligence for mineral assets including exploration through to development, operation and mine closure. Established in 1974, SRK employs more than 1,400 professionals internationally in over 45 offices on 6 continents. SRK provides a truly comprehensive range of consulting services to the resource industry including geological modelling, resource estimation, mine design and scheduling, geotechnics, water management, tailings disposal, metallurgy, environmental management, geochemistry and technical-economic modelling.

Worley Parsons

Worley Parsons provides expertise in engineering, procurement and construction and offers a wide range of consulting and advisory services. The company covers the full lifecycle, from creating new assets to sustaining and enhancing operating assets, in the hydrocarbons, mineral, metals, chemicals and infrastructure sectors. It was established in 1976 as a Wholohan Grill and Partners - a small Australian engineering consultancy, and is now a company with global reach, listed on the Australian Stock Exchange.

Arup

Arup is an independent firm of designers, planners, engineers, consultants and technical specialists offering a broad range of professional services. Founded in 1946, Arup now has more than 12,000 people working in 92 offices in 40 countries and its projects have taken it to more than 160 countries. Arup provide engineering and related consultancy services necessary to every stage of a project, from inception to completion and after. Throughout the world Arup aim to provide a consistently excellent multi-disciplinary service, which also incorporates its concern for the environment. Arup operates as five Regions: Americas, Australasia, East Asia, Europe, and UK, Middle East and Africa (UKMEA).

K Home International

K Home International provides comprehensive engineering design solutions to developers and operators of world-class installations, a portfolio which ranges from innovative industrial process plants to major infrastructure projects. The company was founded in North East England in 1973 with the aim of providing an engineering design, project and construction management services that delivers the most appropriate and effective solutions for its clients. The company, which is privately-owned, operates around the world and works within a broad range of industrial sectors. Throughout its years of service K Home International has gained an enviable record of delivering safe, compliant and consistently productive capital projects.

Royal HaskoningDHV

Royal HaskoningDHV is an independent, international engineering and project management consultancy with over 130 years of experience. The company's professionals deliver services in the fields of aviation, buildings, energy, industry, infrastructure, maritime, mining, transport, urban and rural planning and water. Backed by expertise and experience of nearly 7,000 colleagues across the world, Royal HaskoningDHV works for public and private clients in more than 130 countries. Company's roots are in the Netherlands, the United Kingdom and South Africa. In addition, it is established in Asia and the Middle East, Africa and the Americas.

Bechtel

Bechtel is one of the most respected global engineering, construction, and project management companies. Together with its customers, the company delivers landmark projects that create long-term progress and economic growth. Since 1898, Bechtel has completed more than 25,000 extraordinary projects across 160 countries on all seven continents. It operates through four global businesses: infrastructure; nuclear, security and environmental; oil, gas and chemicals; and mining and metals.

This information is provided by RNS
The company news service from the London Stock Exchange
END
MSCAKADPDBKBQND
Date   Source Headline
16th Mar 20204:29 pmRNSAn open letter from Russell Scrimshaw
16th Mar 20204:18 pmRNSForm 8.5 (EPT/RI)-Replacement of Sirius Minerals
16th Mar 20204:15 pmRNSForm 8.5 (EPT/RI)-Replacement of Sirius Minerals
16th Mar 20203:51 pmRNSForm 8.5 (EPT/RI) - Replacement of Sirius Mineral
16th Mar 20203:20 pmRNSForm 8.3 - Sirius Minerals plc
16th Mar 20203:15 pmBUSForm 8.3 - Sirius Minerals plc
16th Mar 20203:00 pmRNSForm 8.3 - Sirius Minerals Plc
16th Mar 20203:00 pmRNSForm 8.3 - Sirius Minerals plc
16th Mar 20202:24 pmEQSForm 8.3 - The Vanguard Group, Inc.: Sirius Minerals plc
16th Mar 20201:04 pmRNSForm 8.3 - Sirius Minerals plc
16th Mar 202011:37 amRNSForm 8.5 (EPT/RI)
16th Mar 202011:28 amBUSForm 8.3 - SIRIUS MINERALS PLC
16th Mar 202011:25 amRNSForm 8.5 (EPT/RI)
16th Mar 202011:12 amRNSForm 8.5 (EPT/RI) - Sirius Minerals plc
16th Mar 202011:11 amRNSForm 8.5 (EPT/RI)- Sirius Minerals plc
16th Mar 202010:44 amRNSForm 8.3 - Sirius Minerals PLC
16th Mar 20208:14 amBUSForm 8.3 - Sirius Minerals plc
16th Mar 20207:50 amRNSSuspension of trading
16th Mar 20207:30 amRNSSuspension Sirius Minerals Plc
13th Mar 20204:41 pmRNSCourt sanction of the Scheme
13th Mar 20203:51 pmRNSForm 8.5 (EPT/RI)-Replacement of Sirius Minerals
13th Mar 20203:20 pmRNSForm 8.3 - Sirius Minerals plc
13th Mar 20203:00 pmRNSForm 8.3 - Sirius Minerals plc
13th Mar 20203:00 pmRNSForm 8.3 - Sirius Minerals Plc
13th Mar 20201:19 pmEQSForm 8.3 - The Vanguard Group, Inc.: Sirius Minerals plc
13th Mar 202012:24 pmRNSForm 8.3 - Sirius Minerals plc
13th Mar 202012:01 pmRNSForm 8.5 (EPT/RI) - Sirius Minerals plc amendment
13th Mar 202011:40 amRNSForm 8.5 (EPT/RI)
13th Mar 202010:50 amRNSForm 8.5 (EPT/RI)
13th Mar 202010:36 amRNSForm 8.5 (EPT/RI)- Sirius Minerals plc
13th Mar 202010:33 amRNSForm 8.3 - Sirius Minerals plc
13th Mar 20209:51 amRNSNotification of Major Holdings
13th Mar 20209:44 amRNSForm 8.5 (EPT/RI)- Sirius Minerals plc
12th Mar 20204:45 pmRNSForm 8.5 (EPT/RI)- Sirius Minerals plc AMENDMENT
12th Mar 20204:44 pmRNSForm 8.5 (EPT/RI)- Sirius Minerals plc AMENDMENT
12th Mar 20203:20 pmRNSForm 8.3 - Sirius Minerals plc
12th Mar 20203:15 pmBUSForm 8.3 - Sirius Minerals plc
12th Mar 20203:00 pmRNSForm 8.3 - Sirius Minerals Plc
12th Mar 20203:00 pmRNSForm 8.3 - Sirius Minerals plc
12th Mar 20202:00 pmRNSForm 8.3 - Sirius Minerals Plc
12th Mar 20201:52 pmGNWForm 8.3 - Sirius Minerals Plc
12th Mar 20201:12 pmEQSForm 8.3 - The Vanguard Group, Inc.: Sirius Minerals plc
12th Mar 202012:59 pmBUSForm 8.3 - Sirius Minerals plc
12th Mar 202012:42 pmRNSForm 8.3 - Sirius Minerals plc
12th Mar 202011:42 amRNSSirius Minerals plc 8.6 Public
12th Mar 202011:22 amRNSForm 8.5 (EPT/RI)- Sirius Minerals plc
12th Mar 202011:12 amRNSForm 8.5 (EPT/RI)
12th Mar 202010:20 amRNSForm 8.5 (EPT/RI)
12th Mar 202010:16 amRNSForm 8.5 (EPT/RI) - Sirius Minerals plc
12th Mar 20209:24 amRNSNotification of Major Holdings

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.