Development Update

4 Aug 2009 07:00

RNS Number : 7789W
Polo Resources Limited
04 August 2009
Β 

ο»Ώ

3Β August 2009Β 

Β 

Polo Resources LimitedΒ 

("Polo" orΒ "the Company")

Extract Resources provides Rossing SouthΒ preliminary cost estimates

Study confirms Rossing South's potential to beΒ oneΒ ofΒ world's largest uraniumΒ mines

Polo Resources (PRL), the AIM listed mining company withΒ uraniumΒ andΒ coal interests in Africa,Β Australia, Europe and Asia,Β is pleased to provide an update released by Extract Resources Ltd ("Extract"Β orΒ "the Company"), in whichΒ Polo resourcesΒ holds aΒ 9.06% interest.Β 

Β 

Mr.Stephen. R.Β Dattels, Executive Chairman, said,

"We are very encouraged by Extract's announcement this morning which confirms our viewΒ that Rossing South could support a profitable, long life, low cost, low technical risk uranium mine producing 14.8M lbs U3O8 per year, making it one of the world's largest uranium mines.Β The area has good infrastructure and many other mining projects, including Rio Tinto's Rossing mine are located in the area.Β 

"We are also very encouraged by the upside potential of the exploration acreage contained within the field and see this as another value diver for Extract and for our significant investment in the business.

"We look forward to further updates from Extract as they progress the Rossing South project."

Contacts:

Polo Resources Limited

Neil Herbert,Β Executive Deputy Chairman

Β +Β 27 82 404 36 37Β 

Canaccord Adams Limited

Mike Jones/Ryan Gaffney

+ 44 (0) 20 7050 6500

Financial Dynamics

Ben Brewerton / Ed Westropp

+ 44 (0) 20 7831 3113

Extract announcement:Β 

Β 

STUDY HIGHLIGHTSΒ 

Β 

* Production rate 15.0 M tpaΒ 

Β 

* Estimated head grade 487 ppm U3O8Β 

Β 

* Mill Recovery 92%Β 

Β 

* U3O8 production 14.8 M lbs / year (6.7 K tpa)Β 

Β 

* Project capital estimate US $704MΒ 

Β 

* Production cost estimate US $23.60 /lb U3O8Β 

Β 

Australian-based uranium mine development and exploration company, Extract Resources Limited (ASX/TSX: EXT) ("Extract"Β orΒ "the Company") today released theΒ preliminary capital and operating cost estimates report which confirm the Rossing South project's potential to be one of the world's largest uranium mines.Β 

Β 

The report states that preliminary cost estimates on the granite hosted, uranium mineralisation at Rossing South inΒ NamibiaΒ indicates that the project can support a viable open pit mining operation developed to feed a 15M tpa agitated tank sulphuric acid leach processing plant. Annual production has been estimated at 14.8M lbs U3O8 with capital costs estimated at US$704M and operating costs of US$23.60 per lb U3O8.Β 

Β 

Extract Resources Managing Director, Mr Peter McIntyre, said, "the preliminary cost estimates report indicates a conventional open pit mining operation with an agitated tank leach process plant is expected to support a profitable and sustainable mining operation for +20 years."Β 

Β 

"This report represents our base case study and we are continuing with ourΒ metallurgical testwork and engineering optimization that will consider other options including a heap-leaching component," he said.Β 

Β 

NamibiaΒ has outstanding infrastructure which would greatly assist the development of the Rossing South project. The project area is located about 55 kms east of the coastal town Swakopmund and north east of the deep waterΒ portΒ ofΒ Walvis Bay. Equipment and materials for constructing and running the mine could be brought in throughΒ Walvis Bay.Β 

Β 

Mr McIntyre said "the availability of infrastructure combined with the confirmed resource and the outstanding exploration potential still to be tested on the Husab project, should ensure a long and successful mining operation centred on Rossing South."Β 

Β 

The Rossing South Feasibility Study, managed by independent consultants GRD Minproc Limited, includes detailed analysis of the Rossing South project parameters with detailed study work ongoing.Β 

Β 

Work completed to date has incorporated a preliminary level of design and cost estimation, to establish the general economic viability of a new development. The study has included some key assumptions relevant to the current resource definition program and the metallurgical characteristics of the uranium mineralization, with work on these critical areas continuing.

ENDS

Β 

About ExtractΒ 

Β 

Extract Resources is an Australian-based uranium mine development and exploration company whose primary focus is in the African nation ofΒ Namibia.Β The Company's principal asset is its 100% owned Husab Uranium Project which contains two known uranium deposit areas: Rossing South; and Ida Dome. Extensive exploration potential also exists for new uranium discoveries, in addition to theΒ already known occurrences.Β 

Β 

Extract is listed on the ASX and the TSX under the ticker symbol "EXT". ForΒ more information on Extract visit www.extractresources.comΒ  Β 

For further information, please contactΒ 

Β 

Peter McIntyre Richard HenningΒ 

Β 

Managing Director Investor RelationsΒ 

Β 

rhenning@extractresources.comΒ 

Β 

ROSSING SOUTH PRELIMINARY COST ESTIMATE

Β 

Β 1. SUMMARYΒ 

Β 

* Preliminary cost estimates indicate Rossing South could support a longΒ life, low cost, low technical risk uranium mine producing 14.8M lbs U3O8 per year.Β 

Β 

* Base case conventional load and haul, open-pit mining operation utilising agitated tank leach processing technology.Β 

Β 

* Close proximity to road, rail and port and a pro mining culture adds to theΒ prospects of developing a new uranium mining operation in central westΒ Namibia.Β 

Β 

* Uranium mineralisation on all zones drilled to date is still open at depth and along strike, and supports the expectation that ongoing drilling will increase the CompanyΒ global resource.Β 

Β 

Preliminary cost estimates on the granite hosted, uranium mineralisation atΒ Rossing South indicate that the project can support a viable open pit mining operation developed to feed a 15M tpa agitated tank sulphuric acid leach processing plant. Annual production has been estimated at 14.8M lbs U3O8 with capital costsΒ estimatedΒ at US$704M and operating costs of US$23.60 per lb U3O8.Β 

Β 

Existing infrastructure and a supportive geopolitical environment makeΒ NamibiaΒ an outstanding location to develop a new mining project.Β Β 

Β 

The Company now looks forward to working closely with the Namibian GovernmentΒ to obtain the necessary permits to enable the mine to be developed in a timely manner for the benefit of all stakeholders.Β 

Β 

Β 2. INTRODUCTIONΒ 

Β 

The Husab Uranium Project is covered by Exclusive ProspectingΒ LicenseΒ (EPL)Β 3138 and EPL 3439. The licenses contain two (Rossing South and Ida Dome) of the fiveΒ currently known occurrences of uraniferous granites (alaskites) within the highly prospective Central Zone of the Damara Orogeny in Central West NamibiaΒ (Figure 1). Only one of these occurrences is currently being mined and that is the Rossing Mine which has been processing ore through an agitated tank leach process plant for over 30 years. The Rossing operation currently produces about 7% of the global U3O8 mine production.Β 

Β 

The Rossing South deposits (Zone 1 and Zone 2) are the most advanced within theΒ Husab Uranium Project and are the focus of a Feasibility Study which commencedΒ in April 2009. GRD Minproc Limited was appointed lead consulting group because of their knowledge of the uranium industry and their extensive African experience.Β 

Β 

The next stage of the Feasibility Study is to complete a Prefeasibility Study to an accuracy level of Β± 25%. The final Definitive Feasibility study report will be to an accuracy level of Β± 10-15%. Once completed this informationΒ would-beΒ sufficient to enable the Company to source finance for developing the project. The Feasibility Study is currently in an early stage with preliminary capital and operating costs defined for the base case processing option of agitated tank leach. Other processing options are also being considered, such as heap leach, with ongoing metallurgical test work aimed at defining the most appropriate option.Β 

Β 

Β 3. RESOURCEΒ 

Β 

The Rossing South area contains two known zones of uranium mineralisationΒ 

(Figure 1) which host one of the largest known uranium resources in the world.

Significant detail on these resources, generated following JORC Code guidelines, has been previously reported to the market (ASX releases 2nd and 22nd July 2009) with a summary table shown below (Table 1).Β 

Β 

The currently defined Inferred and Indicated Resource at Rossing South has formed the basis of the preliminary capital and operating cost estimate. Ongoing resource definition drilling is required to increase resource confidence levels so that reserves can be defined for more detailed project evaluation.Β 

Β 

Total resources for Rossing South at 100 ppm U3O8 cut-off is as follows:Β 

Rossing South Total

Category

Tonnes

(Million)

Grade

(ppm U3O8)

U3O8

(M.lbs)

Zone 1

Indicated

21

527

24

Inferred

126

436

121

Zone 2

Inferred

102

543

122

Total

249

487

267

Table 1: Rossing South Resource Table. Note figures have been rounded.Β 

Β 

Β 4. MININGΒ 

Β 

The mining study is aimed at assessing the economic viability of an open pitΒ operation at Rossing South. Conventional open-pit bulk mining utilisingΒ contract mining services and owner operator are both being considered.Β 

Β 

Mining costs have been derived by independent mining consultancy ORElogy.Β Mining rates are based on a 15M tpa processing plant.Β 

Β 

For this preliminary review an average strip ratio of 5:1 (waste:ore), including the overlying desert sands, has been used with more detailed mine design currently being completed on the most recent Zone 1 and Zone 2 resourceΒ models.Β 

Β 

Β 5. METALLURGY AND PROCESSINGΒ 

Β 

The base case process plant is designed to treat 15M tonnes of run of mine ore, on an annual basis, at an average head grade of 487 ppm U3O8 to produce an average of 14.8M lbs U3O8 (6.7K tonnes U3O8). Process plant capacity data is shown in the following table (Table 2).Β 

Description

Value

ROM throughput, M tpa

15

ROM grade, ppm U3O8

+/- 487

Annual contained U3O8 (ROM), M lb

16.1

Overall U3O8 recovery, %

92

Annual recovered U3O8, M lb

14.8

Annual recovered U3O8, K tonne

6.7

Table 2: Process Plant Capacity Data. Note figures have been rounded.Β 

Β 

Metallurgical test work completed on core samples from Rossing South indicates agitated tank leach recoveries in excess of 90% are consistently being achieved. Agitated tank leach is currently the base case processing option. However, several other options, such as heap leaching, are still being considered with final outcomes to be based on the results from ongoing metallurgical testwork.Β 

Β 

Β 6. INFRASTRUCTUREΒ 

Β 

This region ofΒ NamibiaΒ has good infrastructure which would greatly assist theΒ development of the Rossing South project. The project area is located about 55Β kilometresΒ east of the coastal town Swakopmund and north east of the deep waterΒ portΒ ofΒ Walvis Bay. Equipment and materials for constructing and running the mine could be brought in throughΒ Walvis Bay. A rail line connectingΒ Walvis BayΒ to the African network runs within 40 kilometres of Rossing South.Β 

Β 

Power is expected to be sourced from Nampower with an expected demand of aboutΒ 35 MW. Nampower is currently completing an Environmental and Socio EconomicΒ Impact Assessment to construct a new coal fired power station in theΒ Walvis BayΒ area with three capacity scenarios being considered to provide 200, 400 or 800Β MW of electricity.Β 

Β 

Water for the operation is expected to be sourced from a proposed seawaterΒ desalination plant located between Swakopmund andΒ HentiesΒ Bay. There have beenΒ discussions with several parties regarding the prospect of a collaborativeΒ desalination project to meet the needs of multiple industrial customers in theΒ region. Namwater are expected to be the main supplier of this service.Β 

Β 

Β 7. CAPITAL COST ESTIMATEΒ 

Β 

Capital cost estimates have been prepared by GRD Minproc. The capital cost forΒ 

the project is estimated to be US$704M.Β 

Β 

The costs include EPCM and engineering contingency, but do not include the costΒ of off site water supply capital works (which have been included in theΒ operating cost estimate, process costs), working capital, closure costs and owner's costs.Β 

Β 

Mining costs have been omitted from the capital cost estimate, as a totalΒ mining cost of US$2.10 per tonne has been defined which includes capital and all material movement during the course of mining (such as overburden prestrip,Β near surface and at depth within the open pit).Β 

Β 

Β 8. OPERATING COST ESTIMATEΒ 

Β 

The operating cost estimates have been prepared by GRD Minproc Limited, with

the exception of the mining costs generated by ORElogy.Β 

Β 

The estimated annual operating costs for the project are US$351M when fullΒ production has been reached. The operating costs estimated for the miningΒ operation and process plant, as at July 2009, are shown in the following tableΒ (Table 3).Β 

Annual Operating Cost

MillionΒ US$ pa

USΒ $/t* of ore

US$ / lb U3O8

Mining Cost (includes capital)Β 

189

12.6

12.7

Process Cost

162

10.8

10.9

Total Operating Cost

351

23.4

23.6

Table 3: Summary of the annual operating cost estimate. Note figures have beenΒ rounded.Β 

Β 

*Cost per tonne for mining is based on total (ore + waste) tonnes moved to get ore to the ROM pad, using a strip ratio of 5:1 (waste:ore). Processing costs are based on a 15M tpa processing plant.Β 

Β 

Sulphuric acid is the single largest reagent cost item within the process plant with the assumption that it would be imported through theΒ Walvis BayΒ Port.Β However, there are opportunities for significant cost savings if acid is produced inΒ Namibia. This option will be investigated in more detail during the course of the Feasibility Study.Β 

Β 

The information in this report that relates to Exploration Results, MineralΒ Resources or Ore Reserves is based on information reviewed or compiled by Mr Martin Spivey, who is a Member of The AustralasianΒ InstituteΒ ofΒ MiningΒ and Metallurgy and Mr Andrew Penkethman who is a Member of the Australian InstituteΒ of Geoscientists. Mr Spivey and Mr Penkethman are both full time employees of the Company. Mr Spivey and Mr Penkethman have sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which they are undertaking to qualify as a Competent Person as defined in the 2004 Edition of the `Australasian Code for Reporting of Exploration Results, Mineral Resources andΒ OreΒ Reserves'. Mr Spivey and Mr Penkethman consent to the inclusion in this report of the matters based on their information in the form and context in which it appears.Β 

Β 

A full announcement with diagrams is available on www.extractresources.comΒ 

This information is provided by RNS
The company news service from the London Stock Exchange
Β 
END
Β 
Β 
MSCBXGDISXGGGCX
Date   Source Headline
5th Feb 20183:40 pmRNSWEATHERLY INTERNATIONAL PLC - INVESTMENT UPDATE
2nd Feb 20184:58 pmRNSWEATHERLY INTERNATIONAL PLC - INVESTMENT UPDATE
22nd Jan 20187:00 amRNSWeatherly International Plc - Investment Update
16th Jan 20187:48 amRNSRESULT OF ANNUAL GENERAL MEETING
11th Jan 201810:38 amRNSCELAMIN HOLDINGS NL - INVESTMENT UPDATE
29th Dec 201711:29 amRNSNOTICE OF ANNUAL GENERAL MEETING
20th Dec 20172:01 pmRNSRESULTS FOR THE YEAR ENDED 30 JUNE 2017
1st Dec 20177:37 amRNSCELAMIN HOLDINGS NL - INVESTMENT UPDATE
20th Nov 20177:30 amRNSRestoration - Polo Resources Limited
20th Nov 20177:00 amRNSAppointment of Nominated Adviser and Joint Broker
19th Oct 20177:00 amRNSSuspension - Polo Resources Limited
18th Oct 20176:02 pmRNSSUSPENSION OF TRADING-STATUS OF NOMINATED ADVISER
11th Oct 20178:22 amRNSSTATUS OF NOMINATED ADVISER
10th Oct 20176:15 pmRNSNomad Register Change - ZAI Corporate Finance Ltd
25th Sep 20174:50 pmRNSTR-1
30th Jun 201711:05 amRNSHolding(s) in Company
30th May 20177:09 amRNSCELAMIN HOLDINGS NL - INVESTMENT UPDATE
19th May 20175:14 pmRNSHolding(s) in Company
19th May 20178:49 amRNSGCM RESOURCES plc - INVESTMENT UPDATE
6th Apr 20171:15 pmRNSCELAMIN HOLDINGS NL - INVESTMENT UPDATE
6th Apr 20179:27 amRNSWEATHERLY INTERNATIONAL - INVESTMENT UPDATE
3rd Apr 20177:00 amRNSBLACKHAM RESOURCES - INVESTMENT UPDATE
29th Mar 20172:31 pmRNSInterim Results
23rd Mar 20177:00 amRNSBlackham Resources - Investment Update
1st Mar 20174:35 pmRNSPrice Monitoring Extension
15th Feb 201711:06 amRNSIRONSTONE RESOURCES - INVESTMENT UPDATE
10th Feb 20177:00 amRNSBLACKHAM RESOURCES - INVESTMENT UPDATE
25th Jan 20177:00 amRNSResult of Annual General Meeting
30th Dec 20167:00 amRNSNOTICE OF ANNUAL GENERAL MEETING
20th Dec 20163:22 pmRNSRESULTS FOR THE YEAR ENDED 30 JUNE 2016
11th Nov 20162:40 pmRNSGCM RESOURCES PLC - INVESTMENT UPDATE
21st Oct 201611:49 amRNSNOTIFICATION OF MAJOR INTEREST IN SHARES
20th Oct 20167:00 amRNSCELAMIN HOLDINGS NL - INVESTMENT UPDATE
18th Oct 201612:31 pmRNSBLACKHAM RESOURCES LIMITED - INVESTMENT UPDATE
13th Oct 20167:00 amRNSHIBISCUS PETROLEUM - INVESTMENT UPDATE
12th Oct 201612:04 pmRNSMATILDA GOLD PRODUCTION COMMENCES
11th Oct 20164:35 pmRNSPrice Monitoring Extension
7th Oct 20164:21 pmRNSMAJOR SHAREHOLDERS
19th Aug 20167:00 amRNSBLACKHAM RESOURCES - UPDATE
3rd Aug 20165:09 pmRNSTotal Voting Rights
21st Jul 20164:40 pmRNSSecond Price Monitoring Extn
21st Jul 20164:35 pmRNSPrice Monitoring Extension
21st Jul 20167:00 amRNSBlackham Resources - Matilda Mining Commences
15th Jul 20165:08 pmRNSEQUUS PETROLEUM PLC - DISPOSAL
15th Jul 20167:00 amRNSPolo increases stake in Blackham Resources
12th Jul 201611:37 amRNSPolo Second Largest Shareholder in Hibiscus
10th Jun 20164:35 pmRNSPrice Monitoring Extension
9th Jun 20167:00 amRNSPolo Increases Interests in Blackham Resources
31st May 20167:00 amRNSPolo Invests in Universal Coal Resources
14th Apr 201612:21 pmRNSCelamin Holdings - Investment Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.