3 August 2009 

 

Polo Resources Limited 

("Polo" or "the Company")

Extract Resources provides Rossing South preliminary cost estimates

Study confirms Rossing South's potential to bone oworld's largest uranium mines

Polo Resources (PRL), the AIM listed mining company with uranium and coal interests in Africa, Australia, Europe and Asia, is pleased to provide an update released by Extract Resources Ltd ("Extract" or "the Company"), in which Polo resources holds a 9.06% interest. 

 

Mr.Stephen. R. Dattels, Executive Chairman, said,

"We are very encouraged by Extract's announcement this morning which confirms our view that Rossing South could support a profitable, long life, low cost, low technical risk uranium mine producing 14.8M lbs U3O8 per year, making it one of the world's largest uranium mines. The area has good infrastructure and many other mining projects, including Rio Tinto's Rossing mine are located in the area. 

"We are also very encouraged by the upside potential of the exploration acreage contained within the field and see this as another value diver for Extract and for our significant investment in the business.

"We look forward to further updates from Extract as they progress the Rossing South project."

Contacts:

Polo Resources Limited

Neil HerbertExecutive Deputy Chairman

 27 82 404 36 37 

Canaccord Adams Limited

Mike Jones/Ryan Gaffney

+ 44 (0) 20 7050 6500

Financial Dynamics

Ben Brewerton / Ed Westropp

+ 44 (0) 20 7831 3113

Extract announcement: 

 

STUDY HIGHLIGHTS 

 

* Production rate 15.0 M tpa 

 

* Estimated head grade 487 ppm U3O8 

 

* Mill Recovery 92% 

 

* U3O8 production 14.8 M lbs / year (6.7 K tpa) 

 

* Project capital estimate US $704M 

 

* Production cost estimate US $23.60 /lb U3O8 

 

Australian-based uranium mine development and exploration company, Extract Resources Limited (ASX/TSX: EXT) ("Extract" or "the Company") today released the preliminary capital and operating cost estimates report which confirm the Rossing South project's potential to be one of the world's largest uranium mines. 

 

The report states that preliminary cost estimates on the granite hosted, uranium mineralisation at Rossing South in Namibia indicates that the project can support a viable open pit mining operation developed to feed a 15M tpa agitated tank sulphuric acid leach processing plant. Annual production has been estimated at 14.8M lbs U3O8 with capital costs estimated at US$704M and operating costs of US$23.60 per lb U3O8. 

 

Extract Resources Managing Director, Mr Peter McIntyre, said, "the preliminary cost estimates report indicates a conventional open pit mining operation with an agitated tank leach process plant is expected to support a profitable and sustainable mining operation for +20 years." 

 

"This report represents our base case study and we are continuing with our metallurgical testwork and engineering optimization that will consider other options including a heap-leaching component," he said. 

 

Namibia has outstanding infrastructure which would greatly assist the development of the Rossing South project. The project area is located about 55 kms east of the coastal town Swakopmund and north east of the deep water port of Walvis Bay. Equipment and materials for constructing and running the mine could be brought in through Walvis Bay

 

Mr McIntyre said "the availability of infrastructure combined with the confirmed resource and the outstanding exploration potential still to be tested on the Husab project, should ensure a long and successful mining operation centred on Rossing South." 

 

The Rossing South Feasibility Study, managed by independent consultants GRD Minproc Limited, includes detailed analysis of the Rossing South project parameters with detailed study work ongoing. 

 

Work completed to date has incorporated a preliminary level of design and cost estimation, to establish the general economic viability of a new development. The study has included some key assumptions relevant to the current resource definition program and the metallurgical characteristics of the uranium mineralization, with work on these critical areas continuing.

ENDS

 

About Extract 

 

Extract Resources is an Australian-based uranium mine development and exploration company whose primary focus is in the African nation of Namibia. The Company's principal asset is its 100% owned Husab Uranium Project which contains two known uranium deposit areas: Rossing South; and Ida Dome. Extensive exploration potential also exists for new uranium discoveries, in addition to the already known occurrences. 

 

Extract is listed on the ASX and the TSX under the ticker symbol "EXT". For more information on Extract visit www.extractresources.com   

For further information, please contact 

 

Peter McIntyre Richard Henning 

 

Managing Director Investor Relations 

 

rhenning@extractresources.com 

 

ROSSING SOUTH PRELIMINARY COST ESTIMATE

 

 1. SUMMARY 

 

* Preliminary cost estimates indicate Rossing South could support a long life, low cost, low technical risk uranium mine producing 14.8M lbs U3O8 per year. 

 

* Base case conventional load and haul, open-pit mining operation utilising agitated tank leach processing technology. 

 

* Close proximity to road, rail and port and a pro mining culture adds to the prospects of developing a new uranium mining operation in central west Namibia

 

* Uranium mineralisation on all zones drilled to date is still open at depth and along strike, and supports the expectation that ongoing drilling will increase the Company global resource. 

 

Preliminary cost estimates on the granite hosted, uranium mineralisation at Rossing South indicate that the project can support a viable open pit mining operation developed to feed a 15M tpa agitated tank sulphuric acid leach processing plant. Annual production has been estimated at 14.8M lbs U3O8 with capital costs estimated at US$704M and operating costs of US$23.60 per lb U3O8. 

 

Existing infrastructure and a supportive geopolitical environment make Namibia an outstanding location to develop a new mining project.  

 

The Company now looks forward to working closely with the Namibian Government to obtain the necessary permits to enable the mine to be developed in a timely manner for the benefit of all stakeholders. 

 

 2. INTRODUCTION 

 

The Husab Uranium Project is covered by Exclusive Prospecting License (EPL) 3138 and EPL 3439. The licenses contain two (Rossing South and Ida Dome) of the five currently known occurrences of uraniferous granites (alaskites) within the highly prospective Central Zone of the Damara Orogeny in Central West Namibia (Figure 1). Only one of these occurrences is currently being mined and that is the Rossing Mine which has been processing ore through an agitated tank leach process plant for over 30 years. The Rossing operation currently produces about 7% of the global U3O8 mine production. 

 

The Rossing South deposits (Zone 1 and Zone 2) are the most advanced within the Husab Uranium Project and are the focus of a Feasibility Study which commenced in April 2009. GRD Minproc Limited was appointed lead consulting group because of their knowledge of the uranium industry and their extensive African experience. 

 

The next stage of the Feasibility Study is to complete a Prefeasibility Study to an accuracy level of ± 25%. The final Definitive Feasibility study report will be to an accuracy level of ± 10-15%. Once completed this information would-be sufficient to enable the Company to source finance for developing the project. The Feasibility Study is currently in an early stage with preliminary capital and operating costs defined for the base case processing option of agitated tank leach. Other processing options are also being considered, such as heap leach, with ongoing metallurgical test work aimed at defining the most appropriate option. 

 

 3. RESOURCE 

 

The Rossing South area contains two known zones of uranium mineralisation 

(Figure 1) which host one of the largest known uranium resources in the world.

Significant detail on these resources, generated following JORC Code guidelines, has been previously reported to the market (ASX releases 2nd and 22nd July 2009) with a summary table shown below (Table 1). 

 

The currently defined Inferred and Indicated Resource at Rossing South has formed the basis of the preliminary capital and operating cost estimate. Ongoing resource definition drilling is required to increase resource confidence levels so that reserves can be defined for more detailed project evaluation. 

 

Total resources for Rossing South at 100 ppm U3O8 cut-off is as follows: 

Rossing South Total

Category

Tonnes

(Million)

Grade

(ppm U3O8)

U3O8

(M.lbs)

Zone 1

Indicated

21

527

24

Inferred

126

436

121

Zone 2

Inferred

102

543

122

Total

249

487

267

Table 1: Rossing South Resource Table. Note figures have been rounded. 

 

 4. MINING 

 

The mining study is aimed at assessing the economic viability of an open pit operation at Rossing South. Conventional open-pit bulk mining utilising contract mining services and owner operator are both being considered. 

 

Mining costs have been derived by independent mining consultancy ORElogyMining rates are based on a 15M tpa processing plant. 

 

For this preliminary review an average strip ratio of 5:1 (waste:ore), including the overlying desert sands, has been used with more detailed mine design currently being completed on the most recent Zone 1 and Zone 2 resource models. 

 

 5. METALLURGY AND PROCESSING 

 

The base case process plant is designed to treat 15M tonnes of run of mine ore, on an annual basis, at an average head grade of 487 ppm U3O8 to produce an average of 14.8M lbs U3O8 (6.7K tonnes U3O8). Process plant capacity data is shown in the following table (Table 2). 

Description

Value

ROM throughput, M tpa

15

ROM grade, ppm U3O8

+/- 487

Annual contained U3O8 (ROM), M lb

16.1

Overall U3O8 recovery, %

92

Annual recovered U3O8, M lb

14.8

Annual recovered U3O8, K tonne

6.7

Table 2: Process Plant Capacity Data. Note figures have been rounded. 

 

Metallurgical test work completed on core samples from Rossing South indicates agitated tank leach recoveries in excess of 90% are consistently being achieved. Agitated tank leach is currently the base case processing option. However, several other options, such as heap leaching, are still being considered with final outcomes to be based on the results from ongoing metallurgical testwork. 

 

 6. INFRASTRUCTURE 

 

This region of Namibia has good infrastructure which would greatly assist the development of the Rossing South project. The project area is located about 55 kilometres east of the coastal town Swakopmund and north east of the deep water port of Walvis Bay. Equipment and materials for constructing and running the mine could be brought in through Walvis Bay. A rail line connecting Walvis Bay to the African network runs within 40 kilometres of Rossing South. 

 

Power is expected to be sourced from Nampower with an expected demand of about 35 MW. Nampower is currently completing an Environmental and Socio Economic Impact Assessment to construct a new coal fired power station in the Walvis Bay area with three capacity scenarios being considered to provide 200, 400 or 800 MW of electricity. 

 

Water for the operation is expected to be sourced from a proposed seawater desalination plant located between Swakopmund and Henties Bay. There have been discussions with several parties regarding the prospect of a collaborative desalination project to meet the needs of multiple industrial customers in the region. Namwater are expected to be the main supplier of this service. 

 

 7. CAPITAL COST ESTIMATE 

 

Capital cost estimates have been prepared by GRD Minproc. The capital cost for 

the project is estimated to be US$704M. 

 

The costs include EPCM and engineering contingency, but do not include the cost of off site water supply capital works (which have been included in the operating cost estimate, process costs), working capital, closure costs and owner's costs. 

 

Mining costs have been omitted from the capital cost estimate, as a total mining cost of US$2.10 per tonne has been defined which includes capital and all material movement during the course of mining (such as overburden prestrip, near surface and at depth within the open pit). 

 

 8. OPERATING COST ESTIMATE 

 

The operating cost estimates have been prepared by GRD Minproc Limited, with

the exception of the mining costs generated by ORElogy. 

 

The estimated annual operating costs for the project are US$351M when full production has been reached. The operating costs estimated for the mining operation and process plant, as at July 2009, are shown in the following table (Table 3). 

Annual Operating Cost

Million US$ pa

US $/t* of ore

US$ / lb U3O8

Mining Cost (includes capital) 

189

12.6

12.7

Process Cost

162

10.8

10.9

Total Operating Cost

351

23.4

23.6

Table 3: Summary of the annual operating cost estimate. Note figures have been rounded. 

 

*Cost per tonne for mining is based on total (ore + waste) tonnes moved to get ore to the ROM pad, using a strip ratio of 5:1 (waste:ore). Processing costs are based on a 15M tpa processing plant. 

 

Sulphuric acid is the single largest reagent cost item within the process plant with the assumption that it would be imported through the Walvis Bay Port. However, there are opportunities for significant cost savings if acid is produced in Namibia. This option will be investigated in more detail during the course of the Feasibility Study. 

 

The information in this report that relates to Exploration Results, MineraResources or Ore Reserves is based on information reviewed or compiled by Mr Martin Spivey, who is a Member of The Australasian Institute of Mining and Metallurgy and Mr Andrew Penkethman who is a Member of the Australian Institute of Geoscientists. Mr Spivey and Mr Penkethman are both full time employees of the Company. Mr Spivey and Mr Penkethman have sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which they are undertaking to qualify as a Competent Person as defined in the 2004 Edition of the `Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves'. Mr Spivey and Mr Penkethman consent to the inclusion in this report of the matters based on their information in the form and context in which it appears. 

 

A full announcement with diagrams is available on www.extractresources.com 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCBXGDISXGGGCX
Date   Source Headline
29th Sep 20205:30 pmRNSPolo Resources
29th Sep 20209:05 amRNSAIM Delisting
28th Sep 20201:30 pmRNSHolding(s) in Company
11th Sep 202012:51 pmRNSCelamin Holdings Ltd - Investment Update
9th Sep 202012:24 pmRNSPortfolio Update
3rd Sep 20203:18 pmRNSHibiscus Petroleum - Investment Update
1st Sep 20207:30 amRNSSuspension - Polo Resources Limited
1st Sep 20207:00 amRNSResignation of Nominated Adviser and Broker
26th Aug 20207:00 amRNSANDINA GOLD - INVESTMENT UPDATE
24th Aug 20204:31 pmRNSHIBISCUS PETROLEUM - INVESTMENT UPDATE
21st Aug 20207:30 amRNSResult of Adjourned AGM
17th Aug 20204:40 pmRNSSecond Price Monitoring Extn
17th Aug 20204:35 pmRNSPrice Monitoring Extension
31st Jul 20205:26 pmRNSNotice Reconvening Adjourned AGM
31st Jul 20205:25 pmRNSResignation of Nominated Adviser
4th May 20202:20 pmRNSHIBISCUS PETROLEUM – INVESTMENT UPDATE
16th Apr 202011:40 amRNSHolding(s) in Company
16th Apr 202011:35 amRNSHolding(s) in Company
16th Apr 202011:30 amRNSHolding(s) in Company
15th Apr 202010:20 amRNSHolding(s) in Company
7th Apr 20205:30 pmRNSUpdate re GCM and other matters
30th Mar 202010:30 amRNSInterim Results for the Six Months Ended 31 Dec 19
11th Mar 20208:00 amRNSHIBISCUS PETROLEUM – INVESTMENT UPDATE
26th Feb 20207:00 amRNSHIBISCUS PETROLEUM – INVESTMENT UPDATE
21st Feb 20204:01 pmRNSUpdate re admission of GCM Consideration Shares
21st Feb 20204:00 pmRNSAdjourned AGM, Phronimos Capital and other matters
12th Feb 20207:45 amRNSUpdate re Admission of GCM Consideration Shares
6th Feb 20208:53 amRNSPOLO INCREASES INTEREST IN GCM
30th Jan 20203:00 pmRNSHolding(s) in Company
21st Jan 20205:14 pmRNSResult of AGM
31st Dec 20197:00 amRNSNotice of AGM
30th Dec 20193:15 pmRNSHolding(s) in Company
20th Dec 20194:07 pmRNSRESULTS FOR THE YEAR ENDED 30 JUNE 2019
19th Dec 201912:35 pmRNSCELAMIN HOLDINGS LTD - INVESTMENT UPDATE
12th Dec 20193:02 pmRNSHibiscus Petroleum - Investment Update
21st Nov 20194:38 pmRNSHIBISCUS PETROLEUM - INVESTMENT UPDATE
7th Oct 20192:51 pmRNSHIBISCUS PETROLEUM - INVESTMENT UPDATE
23rd Sep 20198:15 amRNSCELAMIN HOLDINGS LTD - INVESTMENT UPDATE
16th Sep 20197:00 amRNSNIMINI GOLD HOLDINGS - INVESTMENT UPDATE
20th Aug 20194:45 pmRNSHIBISCUS PETROLEUM - INVESTMENT UPDATE
20th Aug 201910:14 amRNSHIBISCUS PETROLEUM - INVESTMENT UPDATE
24th Jul 20191:08 pmRNSHIBISCUS PETROLEUM - INVESTMENT UPDATE
17th Jul 20192:13 pmRNSHIBISCUS PETROLEUM - INVESTMENT UPDATE
19th Jun 20195:30 pmRNSCELAMIN HOLDINGS LTD - INVESTMENT UPDATE
7th May 20197:00 amRNSHIBISCUS PETROLEUM - INVESTMENT UPDATE
10th Apr 20197:35 amRNSCELAMIN HOLDINGS LTD - INVESTMENT UPDATE
5th Apr 20199:06 amRNSCELAMIN HOLDINGS LTD - INVESTMENT UPDATE
29th Mar 20198:39 amRNSInterim Results for the Six Months Ended Dec 2018
15th Mar 20198:13 amRNSGCM Resources PLC - Investment Update
7th Mar 20197:34 amRNSCelamin Holdings NL - Investment Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.