Trial Mining Commences

12 Jan 2017 10:30

RNS Number : 0173U
Edenville Energy PLC
12 January 2017
 

12 January 2017

 

 

 

EDENVILLE ENERGY PLC

("Edenville" or the "Company")

 

 

Trial Mining Commences

 

Edenville Energy plc (AIM: EDL) the company developing an integrated coal to power project in south western Tanzania, is pleased to announce that it has started trial mining at the Rukwa Coal Project near Sumbawanga in western Tanzania.

 

Key Points

 

· Trial mining commenced

 

· Initial mine production planned to start in Q1 2017

 

· Significant interest from several groups for the coal from Rukwa

 

 

Over the past several months Edenville has received significant formal interest from several companies for long-term coal supply. As a result, trial shipments of run of mine ("ROM") coal have been transported to customers in order to determine appropriate logistical, quality and quantity parameters. Commercial rates are being paid for the delivery of this coal.

 

Consequentially, the Company has taken the decision to move the project to the next stage of development, which focuses on the commencement of commercial mining operations and the acquisition of a coal processing facility. It is planned that initial mining will commence in Q1 2017. This will focus on stripping the overburden and the production of a ROM coal stockpile. In parallel, a suitable coal wash plant is planned to be established on site.

 

Whilst some coal will be delivered unprocessed, as per customer requirements, it is envisaged that the majority of coal will undergo a degree of treatment through the wash plant to optimise the product for different customers and maximise the potential returns to Edenville. Initial mining operations will be under the control of Edenville and the Company is well advanced in selection of a suitable wash plant facility. The wash plant facility will also be configured so as to be able to process coal for the planned future power plant. More details on the above points and other areas of the operation will be announced as appropriate.

 

Rufus Short CEO of Edenville Energy commented: "I am very pleased we have been able to reach the stage where we are confident there is a long-term market for the coal from Rukwa. Our goal is to move our asset into generating positive cash flow in the near-term and to become a key supplier of coal in the East Africa region. Production will take place alongside the continued advancement of the planned coal to power project."

 

 

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) 596/2014.

 

 

For further information please contact:

 

 

 

Edenville Energy Plc

Jeff Malaihollo - Chairman

Rufus Short - CEO

+44 (0) 20 7652 9788

 

Northland Capital Partners Limited

(Nominated Adviser)

Gerry Beaney

David Hignell

 

 

+44 (0) 20 3861 6625

 

Optiva Securities Limited

(Broker)

Jeremy King

Graeme Dickson

 

 

+44 (0) 20 3137 1902

IFC Advisory

(Financial PR and IR)

Tim Metcalfe

Graham Herring

Heather Armstrong

 

+44 (0) 20 3053 8671

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCOKBDBKBKDCDD
Date   Source Headline
8th Jul 20157:00 amRNSRecent Meetings in Tanzania
2nd Jul 20153:05 pmRNSExercise of Warrants
1st Jul 201510:07 amRNSSubmission of Mining Licence
1st Jul 20157:00 amRNSExercise of Warrants
23rd Jun 201512:00 pmRNSResult of AGM
23rd Jun 20157:00 amRNSMining Licence Application
9th Jun 20157:00 amRNSExercise of Warrants
3rd Jun 20157:00 amRNSBoard Reorganisation
29th May 20154:28 pmRNSNotice of AGM
27th May 20157:01 amRNSProject Update
27th May 20157:00 amRNSFull Year Results
12th May 20157:01 amRNSExploration Programme and Project Update
12th May 20157:01 amRNSTermination of Darwin Facility
23rd Apr 20157:00 amRNSCompletion of £250,000 Placing
15th Apr 20157:00 amRNSProject and Company Update
2nd Mar 20157:00 amRNSPOWER PLANT FEASIBILITY STUDY
21st Jan 201512:01 pmRNSCorrection: Mkomolo and Muze Test Pit Results
21st Jan 20157:00 amRNSMkomolo and Muze Test Pit Results
16th Dec 20147:00 amRNSMkomolo Test Pit Results
1st Dec 20147:00 amRNSStrategy Update
24th Nov 20147:00 amRNSNamwele Test Pit Results
18th Nov 20144:40 pmRNSHolding(s) in Company
11th Nov 20147:00 amRNSDirectorate Change
10th Nov 20147:00 amRNSHolding(s) in Company
5th Nov 20147:00 amRNSFeasibility Study and Working Capital Placing
19th Sep 20147:00 amRNSInterim Results
1st Jul 20147:00 amRNSEnvironmental Impact Assessment Certificate
27th Jun 201411:10 amRNSResult of AGM
19th Jun 20147:00 amRNSPlacing & Issue of Equity
17th Jun 20144:40 pmRNSSecond Price Monitoring Extn
17th Jun 20144:35 pmRNSPrice Monitoring Extension
11th Jun 20147:00 amRNSExpression of Interest signed
4th Jun 20149:00 amRNSNotice of AGM
3rd Jun 20147:00 amRNSResults for the Year Ended 31 December 2013
3rd Apr 201410:30 amRNSEdenville at UK Ivestor Show
26th Mar 20147:00 amRNSOperational Update
24th Jan 20145:31 pmRNSHolding(s) in Company
24th Jan 201411:31 amRNSTR-1 Disclosure Form
22nd Jan 201410:40 amRNSHolding(s) in Company
21st Jan 20144:35 pmRNSPrice Monitoring Extension
21st Jan 20142:27 pmRNSTR-1 Disclosure Form
20th Jan 20145:32 pmRNSHolding(s) in Company
20th Jan 20141:05 pmRNSHolding(s) in Company
17th Jan 20147:00 amRNSChange of Adviser
17th Jan 20147:00 amRNSCompletion of £1 million Placing
16th Jan 20144:40 pmRNSSecond Price Monitoring Extn
16th Jan 20144:35 pmRNSPrice Monitoring Extension
3rd Jan 20149:43 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES
9th Dec 20133:27 pmRNSTR-1 Notification of Major Interest in Shares
3rd Dec 201311:08 amRNSTR-1: NOTIFICATION OF MAJOR INTEREST IN SHARES

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.