Project Update

28 Jul 2015 07:00

RNS Number : 2283U
Edenville Energy PLC
28 July 2015
 

28 July 2015

Edenville Energy plc

("Edenville" or the "Company")

 

Exploration Update and Detailed Water Monitoring Programme Begins

 

Edenville Energy plc (AIM: EDL) is pleased to provide an update on the status of the Rukwa Coal to Power Project near Sumbawanga, in south western Tanzania.

 

Power Plant EIA Work Update

Following the award of the Environmental Impact Assessment (EIA) for Edenville's proposed coal mining at Rukwa in 2014 and the publication of a positive Power Plant Feasibility Study in March 2015, Edenville are pleased to report the commencement of field activities which will underpin the Power Plant EIA, a key component for development of the Rukwa Coal to Power Project.

The Company has commenced a water survey and sampling programme to provide data for the Power Plant EIA, which will be submitted once the definitive power plant design has been confirmed. This EIA, which will cover power plant, transmission and emissions, requires extensive water level monitoring and water samples to provide baseline data for wet and dry seasons.

Under the supervision of Mark Pryor, COO, Edenville's trained field team are working alongside the Company's environmental consultants to implement and run the water monitoring programme to internationally accepted standards. A dip meter will monitor the water table at a series of selected drill holes covering the 8km strike length of the Mkomolo deposit and a Portable Colorimetric Laboratory for Environmental Water Quality has been purchased in order to establish water quality variations through the seasons.

This test work and data monitoring programme will continue over the life of the project, for both the coal mining and power generation operations, to ensure acceptable standards are maintained.

 

Exploration Work Update

The geophysical survey that was commenced in June is ongoing. Fill-in lines between the Mkomolo and Namwele deposits are now complete with the grid extension moving northwards to cover the western extension of the Mkomolo region. This data is currently being interpreted by Edenville's geologists.

 

Corporate Social Responsibility (CSR) Update

Edenville continues to work closely with the local community to fulfil its CSR responsibilities. School supplies are being organised for delivery to local schools in the area, alongside work to upgrade several school buildings.

 

 

Rufus Short, CEO of Edenville commented, "Edenville continues to advance the Rukwa Coal to Power project and the commencement of water monitoring and data gathering is another important step in collating the information necessary for the Power Plant Environmental Impact Assessment (EIA).

Discussions with Engineering, Procurement and Construction (EPC) partners continue and it is important to note that these negotiations are not dependent on the submission of the Power Plant EIA.

A 12 month data set is required to build an accurate picture of water levels to support the Power Plant EIA, so it important this work is started as soon as possible. We were delighted to receive our EIA for the Rukwa Coal Mine in 2014 and will work closely with the same consultants to move through the Power Plant EIA process.

We will continue to update our shareholders on developments relating to the Rukwa Coal to Power Project as they occur."

 

Contact

 

Edenville Energy Plc

Rufus Short - CEO

+44 (0) 20 7652 9788

Cantor Fitzgerald Europe

(Nominated Advisor and Corporate Broker)

Stewart Dickson

Jeremy Stephenson

 

+44 (0) 20 7894 7000

IFC Advisory

(Financial PR and IR)

Tim Metcalfe

Graham Herring

+44 (0) 20 3053 8671

 

 

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCLLFSDDDIDFIE
Date   Source Headline
18th Jul 20197:00 amRNSMining Update
27th Jun 20197:00 amRNSCommencement of Mining at the Northern Area
21st Jun 20191:37 pmRNSHolding(s) in Company
21st Jun 20197:00 amRNSAnnual Results for the year ended 31 December 2018
13th Jun 20192:09 pmRNSRukwa Coal Project Update
3rd Jun 20192:48 pmRNSHolding(s) in Company
31st May 20197:00 amRNSTotal Voting Rights
29th May 201911:07 amRNSHolding(s) in Company
21st May 20193:42 pmRNSHolding(s) in Company
21st May 20197:00 amRNSHolding(s) in Company
20th May 20196:04 pmRNSHolding(s) in Company
17th May 20191:49 pmRNSResult of General Meeting
16th May 20194:02 pmRNSNew Company Presentation
15th May 20194:36 pmRNSPrice Monitoring Extension
15th May 20199:00 amRNSPrice Monitoring Extension
14th May 20197:00 amRNSRukwa Coal Project - Update
9th May 20194:26 pmRNSHolding(s) in Company
3rd May 20191:11 pmRNSHolding(s) in Company
3rd May 20197:00 amRNSUpdate re: Collateral Shares issued to Lind
2nd May 201911:51 amRNSHolding(s) in Company
29th Apr 20197:00 amRNSPlacing and Notice of GM
1st Apr 20197:00 amRNSCorporate Update
15th Feb 20194:08 pmRNSResult of General Meeting & Open Offer
14th Feb 201911:39 amRNSTanesco Update
12th Feb 20193:59 pmRNSHolding(s) in Company
30th Jan 20197:00 amRNSOpen Offer and Notice of General Meeting
29th Jan 20197:00 amRNSAppointment of Nominated Adviser and Broker
25th Jan 20197:00 amRNSNomad Status Update
14th Jan 20197:00 amRNSProject Update
20th Dec 20187:00 amRNSLamella Plant Operational
17th Dec 20187:00 amRNSProject Update
11th Dec 20187:00 amRNSNomad Status
7th Dec 201810:40 amRNSTanesco Re-submission
8th Nov 20187:00 amRNSLatest Tanesco Announcement
6th Nov 20187:00 amRNSConditional Convertible Loan Facility
2nd Nov 20183:51 pmRNSRecent Tanesco Announcement
22nd Oct 20187:00 amRNSSubmission of RFQ Documentation to Tanesco
9th Oct 20187:00 amRNSCoal supply contract
8th Oct 20187:00 amRNSFurther Coal Supply Contract
24th Sep 20187:00 amRNSInterim Results for the six months to 30 June 2018
22nd Aug 20187:00 amRNSCoal supply contract
14th Aug 201811:00 amRNSPrice Monitoring Extension
14th Aug 20187:00 amRNSCommercial Coal Production Update
18th Jul 20187:00 amRNSBroker Update
28th Jun 20183:55 pmRNSResult of AGM
25th Jun 20181:50 pmRNSExtension of MOU with Sinohydro
22nd Jun 20188:45 amRNSPowerline Financing
12th Jun 20187:00 amRNSInterview with CEO
5th Jun 20189:05 amRNSNotice of AGM
5th Jun 20187:00 amRNSAnnual Results for the year ended 31 December 2017

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.