Project Update

27 Feb 2018 08:51

RNS Number : 0631G
Edenville Energy PLC
27 February 2018
 

27 February 2018

EDENVILLE ENERGY PLC

("Edenville" or the "Company")

 

Project Update

 

 

Edenville Energy plc (AIM: EDL), the company developing a coal project in southwest Tanzania, is pleased to provide a further update in relation to the Company's recently established commercial coal production.

 

Highlights

 

· One year contract for a minimum of 2,000 tonnes of coal per month has been signed;

· Further trial orders of several thousand tonnes for other potential customers are being filled;

· All current orders are being sold at commercial market rates, similar to those expected for longer-term contracts;

· Logistical challenges have now been resolved at no cost to the Company; and

· Payments for coal shipped at the end of 2017 are now being received as anticipated.

 

Since the Company Update announcement of 31 January 2018, Edenville has continued to supply coal on a commercial basis and has received further orders. The Company has now signed a one year contract with an East African industrial user for a minimum 2,000 tonnes per month with favourable payment terms.

 

In addition, the Company is pleased to have commenced production on a new order for 4,000 tonnes of coal for use by a Tanzanian customer. If the coal is deemed suitable for the customer's needs having utilised this initial order, the customer has requested another 60,000 tonnes over a period of 6 months (an average of 10,000 tonnes per month). In parallel, trials are underway with a third customer, which if successful is expected to result in future orders on an ongoing basis. 

 

Importantly, the Company believes it has now found solutions to the recent logistical challenges with transporting mined coal, as detailed in the announcement on 31 January 2018, and now has several transport options available at competitive market prices and with no current requirement for capital expenditure by Edenville.

 

The Company is also pleased to report that it has now started receiving payments for the coal shipments made in late 2017, which is in line with the agreed payment terms.

 

With significant demand for the Company's coal and long-term order indications in excess of the amount of coal that the Company can supply in the short to medium-term, the focus is on entering into long-term contracts with those groups that can provide attractive payment terms, maximising the price per tonne and minimising credit terms. Whilst these longer-term contractual negotiations continue, with the goal of ensuring the best long-term economic outcome for the Company, Edenville will continue to supply and be paid commercial rates for significant bulk and trial orders. For the avoidance of doubt the coal subject to these current individual bulk and trial orders is being supplied at a similar price per tonne as is envisaged for longer-term contracts.

 

 

Commenting, Rufus Short, CEO of Edenville said, "As we progress our coal to power project we believe we are in a strong position as a coal producer in Tanzania. Whilst our current production is mainly under one off contracts with potential longer-term customers, we are confident that a sufficient number of these orders will lead to longer-term contracts. This coal is being sold at commercial market rates, similar to those rates we expect for longer-term deals."

 

 

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) 596/2014.

 

 

For further information please contact:

 

 

Edenville Energy Plc

Jeff Malaihollo - Chairman

Rufus Short - CEO

+44 (0) 20 3934 6632

 

Northland Capital Partners Limited

(Nominated Adviser)

David Hignell

Gerry Beaney

Jamie Spotswood

 

+44 (0) 20 3861 6625

 

Optiva Securities Limited

(Broker)

Jeremy King

Graeme Dickson

 

 

+44 (0) 20 3137 1902

IFC Advisory

(Financial PR and IR)

Tim Metcalfe

Graham Herring

Heather Armstrong

 

+44 (0) 20 3934 6630

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
UPDLIFSTFDIDFIT
Date   Source Headline
20th Dec 20167:00 amRNSBulk Sampling Results for Namwele
14th Dec 20167:00 amRNSRukwa Coal to Power Project Update
5th Dec 20167:00 amRNSAdditional Bulk Sampling Results
15th Nov 20167:00 amRNSBulk Sampling Results
3rd Nov 20163:50 pmRNSExercise of Warrants
2nd Nov 20161:53 pmRNSHolding(s) in Company
2nd Nov 20167:00 amRNSDirectorate Change
1st Nov 20167:00 amRNSResource Technical Assessment and Project Update
19th Oct 20163:15 pmRNSIssue of Equity
29th Sep 20167:00 amRNSPlacing to raise £500,000
27th Sep 20167:00 amRNSBulk Sampling Update
21st Sep 20167:00 amRNSUpdated Financial Model
16th Sep 20167:00 amRNSInterim Results for the Six Months to 30 June 2016
1st Sep 20167:00 amRNSNew Investor Presentation
31st Aug 20164:05 pmRNSTotal Voting Rights
30th Aug 201611:19 amRNSResult of General Meeting
24th Aug 20167:00 amRNSAppointment of Chairman
18th Aug 20167:00 amRNSInvestor Evening
15th Aug 20167:00 amRNSAnnouncement by Tanzanian MEM
12th Aug 20167:00 amRNSShare Capital Reorganisation
22nd Jul 20167:00 amRNSMEM and Tanesco Site Visit
13th Jul 20167:00 amRNSRukwa Coal to Power Project Update
14th Jun 20167:00 amRNS£432,500 Subscription
3rd Jun 201612:40 pmRNSResult of AGM
27th May 20167:00 amRNSPower Project Update
25th May 20167:00 amRNSChange of Adviser
18th May 20167:00 amRNSProject Update
11th May 20162:30 pmRNSNotice of AGM
10th May 20167:00 amRNSFull Year Results
27th Apr 20167:00 amRNSProject and Licence Update
8th Apr 20167:00 amRNSResignation of Director
31st Mar 20167:00 amRNSProject Update
3rd Mar 20167:00 amRNSFormal Grant of Mining Licence
2nd Mar 20167:00 amRNS£400,000 Subscription
24th Feb 201610:00 amRNSGranting of Mining Licence
8th Feb 20167:00 amRNSProject Update
11th Jan 20167:00 amRNSRukwa Coal to Power Project update
2nd Dec 20157:00 amRNSCompletion of £250,000 Placing
1st Dec 20157:00 amRNSCollaboration Agreement with EPC Contractor
1st Oct 20157:00 amRNSMining Licence Application Update
23rd Sep 20157:00 amRNSInterim Results
23rd Sep 20157:00 amRNSMining Licence Update
8th Sep 20157:00 amRNSCoal to Power Project Update
27th Aug 20157:01 amRNSExploration Update
26th Aug 201512:50 pmRNSExercise of Warrants
3rd Aug 20157:00 amRNSCompletion of £250,000 Placing
28th Jul 20157:00 amRNSProject Update
21st Jul 201510:30 amRNSCorrection: Exercise of Warrants
16th Jul 201510:14 amRNSExercise of Warrants
15th Jul 20157:00 amRNSPower Plant Feasibility Review Process

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.