Project update

23 Nov 2017 07:00

RNS Number : 2817X
Edenville Energy PLC
23 November 2017
 

23 November 2017

 

EDENVILLE ENERGY PLC

("Edenville" or the "Company")

 

Project Update

 

 

Edenville Energy plc (AIM: EDL), the company developing a coal project in southwest Tanzania, is pleased to provide an update on the recently commenced commercial coal production and the Company's coal-to-power project.

 

Coal Production

 

Following the start of washed coal production, announced on 9 October 2017, processed coal is currently being delivered on commercial terms to a number of customers in Tanzania and neighbouring countries.

 

These initial, "test shipments", currently totalling over 1,000 tonnes, are to parties that have expressed interest in placing long-term coal orders with the Company, subject to finalising pricing and quality, that in total could exceed the initial planned output of 10,000 tonnes per month, which is targeted to be achieved by the end of January 2018.

 

In order to deliver product to meet this expected demand, the Company is reviewing options to further optimise the efficiency and therefore the throughput of the wash plant. Pre-screening of coal measures is currently occurring and the option is being reviewed to install a purpose built pre-screening mechanism that reduces the level of fine material that enters the plant providing more capacity for the washing of sized coal, which is our optimum product. Any investment in a pre-screening mechanism is expected to be undertaken using the Company's current financial resources.

 

The Company has been working hard to ensure that all aspects of the project meet the local regulatory requirements. The project now has a fully government certified weighbridge that is being used for measurement of coal tonnages leaving the site. In addition, the project recently underwent a major inspection by 22 Tanzanian Ministry of Energy and Minerals (MEM) officials and the feedback we have had from this visit is positive. It is well supported as a venture which is expected to add both economic and social value to the local area. As previously stated the Company is endeavouring to employ local people wherever possible and the standard and professionalism of our employees is proving to be very high.

 

Coal to Power Project

 

The Company, along with its partner Sinohydro Corporation of China, has recently taken part in senior management meetings with Tanesco, the Tanzanian State Electricity Company, to agree on the route forward for development of the planned mine mouth power plant at the Company's Rukwa Coal Project site in the Sumbawanga Region of Tanzania.

 

Several areas were covered including the size of the project, the proposed structure of a Power Purchase Agreement (PPA), tariff levels, and connectivity into the planned transmission line that will pass through the Sumbawanga Region.

 

Further discussions and clarification between the parties on these and other matters could then lead to a structured agreement between the parties to move the project forward in line with the planned construction by Tanesco of the transmission line and substation infrastructure at Sumbawanga.

 

The Company looks forward to providing further updates as appropriate.

 

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) 596/2014.

 

 

For further information please contact:

 

 

Edenville Energy Plc

Jeff Malaihollo - Chairman

Rufus Short - CEO

+44 (0) 20 7652 9788

 

Northland Capital Partners Limited

(Nominated Adviser)

Gerry Beaney

David Hignell

Jamie Spotswood

 

+44 (0) 20 3861 6625

 

Optiva Securities Limited

(Broker)

Jeremy King

Graeme Dickson

 

 

+44 (0) 20 3137 1902

IFC Advisory

(Financial PR and IR)

Tim Metcalfe

Graham Herring

Heather Armstrong

 

+44 (0) 20 3053 8671

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
UPDLLFERLTLFFID
Date   Source Headline
20th Dec 20167:00 amRNSBulk Sampling Results for Namwele
14th Dec 20167:00 amRNSRukwa Coal to Power Project Update
5th Dec 20167:00 amRNSAdditional Bulk Sampling Results
15th Nov 20167:00 amRNSBulk Sampling Results
3rd Nov 20163:50 pmRNSExercise of Warrants
2nd Nov 20161:53 pmRNSHolding(s) in Company
2nd Nov 20167:00 amRNSDirectorate Change
1st Nov 20167:00 amRNSResource Technical Assessment and Project Update
19th Oct 20163:15 pmRNSIssue of Equity
29th Sep 20167:00 amRNSPlacing to raise £500,000
27th Sep 20167:00 amRNSBulk Sampling Update
21st Sep 20167:00 amRNSUpdated Financial Model
16th Sep 20167:00 amRNSInterim Results for the Six Months to 30 June 2016
1st Sep 20167:00 amRNSNew Investor Presentation
31st Aug 20164:05 pmRNSTotal Voting Rights
30th Aug 201611:19 amRNSResult of General Meeting
24th Aug 20167:00 amRNSAppointment of Chairman
18th Aug 20167:00 amRNSInvestor Evening
15th Aug 20167:00 amRNSAnnouncement by Tanzanian MEM
12th Aug 20167:00 amRNSShare Capital Reorganisation
22nd Jul 20167:00 amRNSMEM and Tanesco Site Visit
13th Jul 20167:00 amRNSRukwa Coal to Power Project Update
14th Jun 20167:00 amRNS£432,500 Subscription
3rd Jun 201612:40 pmRNSResult of AGM
27th May 20167:00 amRNSPower Project Update
25th May 20167:00 amRNSChange of Adviser
18th May 20167:00 amRNSProject Update
11th May 20162:30 pmRNSNotice of AGM
10th May 20167:00 amRNSFull Year Results
27th Apr 20167:00 amRNSProject and Licence Update
8th Apr 20167:00 amRNSResignation of Director
31st Mar 20167:00 amRNSProject Update
3rd Mar 20167:00 amRNSFormal Grant of Mining Licence
2nd Mar 20167:00 amRNS£400,000 Subscription
24th Feb 201610:00 amRNSGranting of Mining Licence
8th Feb 20167:00 amRNSProject Update
11th Jan 20167:00 amRNSRukwa Coal to Power Project update
2nd Dec 20157:00 amRNSCompletion of £250,000 Placing
1st Dec 20157:00 amRNSCollaboration Agreement with EPC Contractor
1st Oct 20157:00 amRNSMining Licence Application Update
23rd Sep 20157:00 amRNSInterim Results
23rd Sep 20157:00 amRNSMining Licence Update
8th Sep 20157:00 amRNSCoal to Power Project Update
27th Aug 20157:01 amRNSExploration Update
26th Aug 201512:50 pmRNSExercise of Warrants
3rd Aug 20157:00 amRNSCompletion of £250,000 Placing
28th Jul 20157:00 amRNSProject Update
21st Jul 201510:30 amRNSCorrection: Exercise of Warrants
16th Jul 201510:14 amRNSExercise of Warrants
15th Jul 20157:00 amRNSPower Plant Feasibility Review Process

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.