Operational Update re Enhancement Plan

25 Jul 2022 07:00

RNS Number : 5757T
Echo Energy PLC
25 July 2022
 

25 July 2022

 

Echo Energy plc

("Echo" or the "Company")

 

Operational Update on the Production and Infrastructure Enhancement Plan

 

Echo Energy, the Latin American focused energy company, is pleased to provide an operational update regarding progress in the execution of the Santa Cruz Sur assets Production and Infrastructure Enhancement Plan previously announced by the Company on 7 July 2022 (the "Plan").

 

As previously announced, the first operational priority under the Plan is to upgrade the power generation capacity sufficient to sustain the elevated production levels anticipated as possible under the plan, the Company is therefore pleased to announce that a contract for the long-term provision of gas-powered electricity generation units to the Joint Venture for installation across the Cerro Molino Oeste, El Indio Oeste and Oceano fields has now been signed.

 

Accordingly, equipment has now been mobilised to the field in Santa Cruz Sur and installation is anticipated to take a month from commencement. The new generation infrastructure consists of one unit of 1,375 Kilo Volt Amps (KVA) capacity for the Cerro Molino Oeste field, one unit of 375 KVA capacity for the El Indio Oeste field, and one unit of 375 KVA capacity to be installed in the Oceano field. The on-site installation and commission of all three units will begin during the week commencing 25 July 2022, notwithstanding the winter conditions currently being experienced at Santa Cruz Sur. The work will be undertaken by Santa Cruz Sur Joint Venture staff.

 

El Indio Oeste will be installed first, followed by Oceano and then Cerro Molino Oeste. These works will be carried out with the intention of minimising any disruption to existing gas and oil production, although some temporary impact is expected. Following these units' installation, additional power will be available to support existing and future production levels. Although there may be some increase to current production, these infrastructure upgrades are in preparation for the recommissioning of shut-in wells using the Joint Venture rig. Work has also commenced on upgrading this pulling rig in anticipation of this upcoming set of operations.

 

The installation of the additional power generation capacity, alongside the upgrading of the workover rig, represents a critical step in the delivery of the Plan. The Company looks forward to continuing to update shareholders on progress on these plans throughout this year.

 

A second set of planned infrastructure improvements will be focused on the maintenance and optimisation of the compressors at Cerro Norte and Campo Bremen to enable the increased volumes of associated gas to be processed and then sold into the main gas export line. This operation is anticipated to take approximately three months from commencement and will be carried out with the intention of minimising any disruption to existing gas production, although some temporary impact is expected.

 

For further information, please contact:

 

Echo Energy

Martin Hull, Chief Executive Officer

 

via Vigo Communications

Vigo Consulting (IR & PR Advisor)

Patrick d'Ancona

Chris McMahon

 

+44 (0) 20 7390 0230

Cenkos Securities (Nominated Adviser)

Ben Jeynes

Katy Birkin

 

+44 (0) 20 7397 8900

Arden Partners plc (Corporate Broker)

Simon Johnson (Corporate Broking)

John Llewellyn-Lloyd (Corporate Finance)

 

+44 (0) 20 74614 5900

 

Note

 

The assignment of Echo's 70% non-operated participation in the Santa Cruz Sur licences is subject to the authorisation of the Executive Branch of Santa Cruz's Province, which is part of the overall process of title transfer that is proceeding as anticipated. The information contained in this announcement has been reviewed by Echo Energy's Vice President, Exploration, Dr. Julian Bessa Msc, DPhil, MBA ,a Fellow of the Geological Society and President of the Petroleum Exploration Society of Great Britain.

 

Certain of the information contained within this announcement is deemed by the Company to constitute inside information as stipulated under The Market Abuse Regulation (EU 596/2014) pursuant to the Market Abuse (Amendment) (EU Exit) Regulations 2018. Upon the publication of this announcement via a Regulatory Information Service ("RIS"), this inside information is now considered to be in the public domain.

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDSEDSIIEESEEW
Date   Source Headline
7th Dec 20161:12 pmRNSHolding(s) in Company
7th Dec 201611:28 amRNSHolding(s) in Company
7th Dec 20167:00 amRNSPlacing and Conversion of Debt - Update
6th Dec 20167:00 amRNSPlacing and Conversion of Debt
17th Nov 20163:44 pmRNSCommercial Registration
19th Oct 20167:00 amRNSChange of Adviser
18th Oct 201611:52 amRNSHolding(s) in Company
14th Oct 20167:00 amRNSShareholder loan and related party transaction
30th Sep 20163:57 pmRNSUpdate re Loan Facility and Loan Note Settlement
30th Sep 20163:51 pmRNSInterim Report
29th Sep 20167:00 amRNSShareholder loan and related party transaction
28th Sep 20167:00 amRNSSettlement of Loan Note
23rd Aug 20161:18 pmRNSHolding(s) in Company
22nd Aug 20167:00 amRNSHolding(s) in Company
17th Aug 20167:00 amRNSHolding(s) in Company
15th Aug 20167:00 amRNSUpdate on status of Loan Note payable
1st Aug 20167:00 amRNSHolding(s) in Company
25th Jul 20161:19 pmRNSResult of AGM
19th Jul 201611:49 amRNSHolding(s) in Company
15th Jul 20168:01 amRNSHolding(s) in Company
14th Jul 20161:59 pmRNSDirector/PDMR Shareholding & Additional Listing
30th Jun 20163:15 pmRNSHolding(s) in Company
30th Jun 20163:11 pmRNSHolding(s) in Company
30th Jun 20167:01 amRNSAnnual Financial Report & Notice of AGM
30th Jun 20167:00 amRNSFinal Results
24th Jun 20162:42 pmRNSHolding(s) in Company
21st Jun 20167:00 amRNSEast Ghazalat Update
15th Jun 201610:34 amRNSHolding(s) in Company
7th Jun 20169:55 amRNSHolding(s) in Company
6th Jun 20167:00 amRNSHolding(s) in Company
3rd Jun 20168:05 amRNSHolding(s) in Company
27th May 20162:56 pmRNSConversion of convertible loan notes
26th May 20163:32 pmRNSHolding(s) in Company
25th May 20167:00 amRNSFinancial Update
17th May 20167:00 amRNSIssue of Debt
11th May 20167:00 amRNSTunisia: Ksar Hadada Permit CCH Approval Extension
10th May 20163:48 pmRNSHolding(s) in Company
10th May 20167:00 amRNSCreditor and Cost Reductions & Financial Update
25th Apr 201612:23 pmRNSResult of General Meeting
21st Apr 20167:00 amRNSApplication for Ksar Hadada Permit Extension
13th Apr 20162:26 pmRNSHolding(s) in Company
8th Apr 20161:27 pmRNSNotice of GM re Share Capital Reorganisation
7th Apr 20167:00 amRNSKsar Hadada Permit Update
26th Feb 20167:00 amRNSPlacing of 77.98m Ordinary Shares
24th Feb 20167:00 amRNSIssue of Equity & Total Voting Rights
26th Jan 20167:00 amRNSHolding(s) in Company
26th Jan 20167:00 amRNSHolding(s) in Company
25th Jan 20165:06 pmRNSHolding(s) in Company
25th Jan 20162:00 pmRNSUpdate re East Ghazalat concession
20th Jan 20167:00 amRNSTrading Statement

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.