Operating Update

31 Jul 2008 07:00

RNS Number : 2729A
Central Rand Gold Limited
31 July 2008
Β 

ο»Ώ

For immediate releaseΒ  31 JulyΒ 2008

Central Rand Gold Limited ("CRG" or the "Company")

(Incorporated as a company with limited liability under the laws ofΒ Guernsey, Company Number 45108)

(Incorporated as an external company with limited liability under the laws ofΒ South Africa, registration number 2007/0192231/10)

ISIN: GG00B248M601

Share code on LSE: CRND

Share code on JSE: CRD

EXPLORATION AND OPERATIONAL UPDATE

HIGHLIGHTS

Positive results from underground bulk sampling

On track to receive mining rightΒ 

Trial miningΒ scheduledΒ to begin in OctoberΒ 2008

New Mining Order Right

Central RandΒ Gold remains firmly on track to be awarded its New Order Mining Right by the South African Department of Minerals andΒ EnergyΒ (DME). The approval process is well advanced and theΒ Company looks forward to concluding the process in the short term.Β 

TheΒ MiningΒ Right application was accepted by the DME on August 8 2007 and has beenΒ supplementedΒ by theΒ implementation andΒ submission of all other necessaryΒ processes andΒ documentation.

Exploration Update

Considerable exploration activity has taken place resulting in ongoing drilling, assaying and bulk sampling initiatives across theΒ Company's prospecting areas.

Bulk Sampling

Underground bulk sampling has confirmed mineralisation outside of reefsΒ and substantial thicknesses of mineralised grits have been identified.Β 

Significantly, mineralised halos have also been identified in the hangingΒ wall and footΒ wall of conglomerate bands. Underground bulk sampling is currently investigating these mineralised zones.

As part of CRG's exploration programme (surface mapping, diamond drilling, shaft re-access and resource conversion investigations), zones of mineralisation (in the form of pervasive disseminated pyrite and grit bands) have been identified in the hanging wall of the Main Reef Leader and the South Reef on CMR.Β 

CRGΒ has undertakenΒ an extensive bulk sampling exercise to quantify these mineralised zones. These zones of mineralisationΒ have the potential toΒ add to the mineable tonnage and resource estimates.Β This alsoΒ suggestsΒ that mass mining in larger stopes will be viable.Β 

TheΒ Company embarked on its underground sampling process in June 2008. The first samples were obtained through access via East Shaft (Consolidated Main Reef) on 5 level (60 metres below surface).

Approximately 100 metres ofΒ strikeΒ was sampled from the hangingΒ wall of the South Reef utilising a method referred to as "slyping". This involves drilling holes of approximately 200 to 500mm (spaced about 1m apart) into the hangingΒ wall and utilising expanding gas cartridges to "pop" off the sample. The sampling is geologically controlled and a single bulk sample can be made up of 10 to 15 separate entities, depending on the geological feature being analysed. A bulk sample can weigh up to 0.5 ton.

The initial results have become available and are proving to be encouraging (Table 1). This represents a range of 0.5 g/t to 1731 g/t fromΒ eachΒ 0.5 tons of homogenised sample.Β 

Table 1: Initial Results of Bulk Sampling

Sample ID (WBS1)

Values(g/t)

Geology Comments

R_4801

0.5

Gritty Quartzite. Sulphides.

R_4802

0.68

Quartzite

R_4803

28.3

MPC (South reef). Sulphides

R_4804

0.68

Quartzite

R_4805

78.8

Gritty Quartzite. Sulphides. Veining

R_4806

7.48

Gritty Quartzite. Sulphides. Veining

R_4807

2.54

Quartzite

R_4808

0.56

Quartzite

R_4809

12.9

MPC (South reef). Sulphides

R_4810

1 731.0

Quartzite

R_4811

11.5

Quartzite

R_4812

82.7

MPC (South reef). Sulphides

R_4813

25.7

Gritty Quartzite

R_4814

19.4

South Reef. Sulphides

R_4815

1.86

Gritty Quartzite

The implications of these results are significant.Β TheyΒ show that the source of gold is not only confinedΒ toΒ the conglomerate bands,Β but are also present in grit bands, zones of disseminated pyrite and in inter-conglomerate quartzites. This findingΒ would addΒ significantly to the amount of tonnage and resources available for mining.

Bulk sampling isΒ continuing and is currently focusing onΒ Β a cross-cut from the Main Reef to the South Reef (on 5 level, East Shaft) and on 9 level (Β±190m below surface, East Shaft) and will commence in the near future on 5 level, New Unified Shaft (CMR, approximately 3500m to the west of East Shaft).

(* please refer to the Company's website for a diagram)

OtherΒ explorationΒ achievements:

SevenΒ shaftsΒ have been re-accessedΒ 

Completed reconnaissance sampling and mapping over CMR, Crown Mines and LanglaagteΒ 

Preliminary mapping on City DeepΒ 

Confirmation of un-mined mineralised pillarsΒ andΒ reefs through underground surveying an sampling programme

Reconnaissance drilling on Pyritic Quartzites of Village Main and City DeepΒ Resource upgraded by 1.8Moz in March 2008

Initial production slots/surface targets identified - slots 2,3,4,5,7,8,9 and 14Β Β 

Reconnaissance mapping has identified:

– Un-mined sections of the North and Main Reef
– Un-mined duplicated sections of the Bird and Kimberley Reefs – due to faulting
– Large sections of un-worked Elsburg Reefs located towards the southern boundary of the 3C’s tenement areas

Pyritic Quartzites (Erosional Channels cutting through the North, Main Reefs and Main Reef Leader)

Viable grades in the soils

Un-complicated mineralogy of orebodies increasing the potential for better recoveries

Drilling

Since the start of the drilling programmeΒ in November 2006, CRG has completed 32,247m of reverse circulation drilling, 2,509m of soil sample drilling, 1,456m of geotechnical diamond drilling and 15,831m of diamond drilling.Β 

(* please refer to the company website for a diagram)

DrillingΒ hasΒ provided the following information:

– Geological setting
– Β Mining Targets – Slots
– Presence of mineralised zones
– Presence of zones of low grade mineralisation
– Confirmation of positions of pillars, as reported on old stope plans
– Confirmation of the spatial distribution of values predicted by geostats
– Confirmation of structural information indicated by the regional mapping
– Confirmation of duplication of reef packages – wider surface target areas
– Presence of un-mined reefs (i.e. North Reef, South South Reef)
– Presence of new reefs (i.e. additional conglomerate bands in the Bird Reefs)
– Water table heights and the localities of perched water tables
– Geotechnical controls for mine design
– Additional Resources

Regional mapping first indicated the presence of mineralisation outside the conglomerate bands or 'reefs'. Drilling these occurrences has confirmed zones of mineralisation in disseminated pyrite and grit bands outside the known reefs. Following on from this discovery,Β underground exploration has confirmed its presence. It became apparent that quantifying these additional sources of gold would have to be through bulk sampling. Channel sampling produces a 1 in 12000 representation whereas bulk sampling produces a 1 in 200 representation making the data more reliable.

The results from the underground bulk sampling are significant as they confirm the presence of mineralised material outside the conglomerate bands in zones of disseminated pyrite, grit bands and inter-conglomerate quartzites. This findingΒ wouldΒ also add significantly to the amount ofΒ mineableΒ tonnage.Β Β 

(* please refer to the Company's website for a diagram)

Gold production ramp-up

TheΒ CompanyΒ is on schedule to meet itsΒ initialΒ target of producing gold at an annualised rate of 100,000 ounces by the end of 2009 with trial mining to begin in October 2008.Β 

Trial Mining

The Company has purchasedΒ a plant withΒ theΒ capacity to process ore at a rate ofΒ 20 tons an hourΒ from trial mining.Β The plant,Β acquired from Gekko Systems inΒ AustraliaΒ at a costΒ ofΒ US$5.74Β million,Β comprises a communication circuit, a gravity circuit and a flotation circuit.Β 

It is expected that the plantΒ will be shipped fromΒ MelbourneΒ in AugustΒ 2008Β and isΒ scheduledΒ to arrive inΒ JohannesburgΒ mid September.Β ItΒ will be erected andΒ beΒ suitable for commissioningΒ shortlyΒ Β after its arrival.Β 

The trial mining plant, which will be situated on the surface,Β is expected to beΒ fully commissionedΒ inΒ October andΒ is expected to ramp up in the following months to a target rate ofΒ aroundΒ 12,000 tons of ore per month.Β 

Trial mining willΒ confirmΒ theΒ Company'sΒ mining and metallurgical concepts andΒ determine the final configuration of mining/processing requirements,Β leadingΒ to theΒ commencementΒ of full scale mining from surface deposits by the end of the first quarter of 2009.

Full scale mining

Full scale mining of already targeted surface deposits (down to 10m below surface) and shallow underground mining (between depths ofΒ 10mΒ toΒ 70m) willΒ beginΒ by the end of Q1 2009.Β The first three mining slots will be accessed for surface mining as well as providing access for the company's ongoing drilling and underground bulk sampling programmes.Β 

Issued on behalf of: Central Rand Gold Limited

Date:Β 31Β JulyΒ 2008

Contact:Β 

Greg James

Ric Vittino

Wayne Epstein

(011) 551 4000

info@centralrandgold.com

Enquiries:

Buchanan Communications Limited +44 (0) 20 7466 5000

Bobby Morse / Ben Willey

Evolution Securities Limited +44 (0) 20 7071 4300

Simon Edwards / Chris Sim / Neil Elliot

Jenni Newman Public Relations (Pty) Ltd +27 (0) 11 772 1033

Jenni Newman /Β Megann Outram

MacquarieΒ First South Corporate Finance +27 (0) 11Β 583Β 2307

Amanda Markman /Β Thato Morojele / Annerie van den Berg

This information is provided by RNS
The company news service from the London Stock Exchange
Β 
END
Β 
Β 
DRLDBGDRIXXGGIG
Date   Source Headline
10th Jan 20179:00 amRNSReplacement: Loan Agreement, Operational Update...
10th Jan 20177:00 amRNSLoan Agreement/Operation Update/Board Change/Nomad
20th Dec 201610:00 amRNSHolding(s) in Company
19th Dec 20167:00 amRNSHolding(s) in Company
7th Dec 201610:30 amRNSAdditional Listing
30th Nov 201610:17 amRNSHolding(s) in Company
30th Nov 201610:14 amRNSHolding(s) in Company
25th Nov 20168:30 amRNSStrategic Investment Update, Shareholder Loan
14th Nov 201611:00 amRNSAdditional Listing
11th Nov 201611:19 amRNSHolding(s) in Company
11th Nov 201611:17 amRNSHolding(s) in Company
31st Oct 20161:00 pmRNSAdditional Listing
25th Oct 201610:00 amRNSIssue of Convertible Security & Operational Update
20th Oct 20168:00 amRNSAdditional Listing
18th Oct 20161:00 pmRNSResults of General Meeting
6th Oct 20167:00 amRNSAcquisition
28th Sep 20167:00 amRNS2016 Interim Report
26th Sep 201611:00 amRNSPosting of Circular and Notice of General Meeting
16th Sep 20162:05 pmRNSSecond Price Monitoring Extn
16th Sep 20162:00 pmRNSPrice Monitoring Extension
14th Sep 20168:45 amRNSHolding(s) in Company
12th Sep 20168:30 amRNSOperational and Board Trading and Market Update
5th Sep 20169:00 amRNSAdditional Listing
24th Aug 20169:00 amRNSAdditional Listing
22nd Aug 201611:20 amRNSExtension of Loan Notes & Financial Update
16th Aug 201610:00 amRNSIssue of Equity
12th Aug 20161:00 pmRNSResult of AGM
10th Aug 20168:27 amRNSHolding(s) in Company
8th Aug 20169:01 amRNSIssue of Equity
2nd Aug 201610:00 amRNSIssue of Equity
29th Jul 20168:00 amRNSTolling Agreement Processing Commencement
28th Jul 20169:00 amRNSIssue of Equity
22nd Jul 20168:00 amRNSTolling Agreement Executed and First Ore Delivery
18th Jul 201611:00 amRNSIssue of Equity
11th Jul 201611:00 amRNSNotice of AGM
30th Jun 20167:00 amRNSAppointment of Company Secretary
30th Jun 20167:00 amRNSFinal Results & Annual Financial Report
23rd Jun 20169:00 amRNSHolding(s) in Company
21st Jun 20167:49 amRNSHolding(s) in Company
7th Jun 20167:00 amRNSBridge Funding Facility with Bergen Global
7th Jun 20167:00 amRNSOperational, Financial, Corporate & Board Update
3rd May 20168:09 amRNSUpdate re Puno
11th Apr 20164:40 pmRNSSecond Price Monitoring Extn
11th Apr 20164:35 pmRNSPrice Monitoring Extension
11th Apr 20167:00 amRNSStatement re Appeal & Registered Address
7th Mar 20161:00 pmRNSResult of EGM
5th Feb 20167:15 amRNSSubscription of 34,999,015 Ordinary Shares
22nd Dec 20158:00 amRNSMisc - Operational Update and Board Changes
8th Oct 20154:40 pmRNSSecond Price Monitoring Extn
8th Oct 20154:35 pmRNSPrice Monitoring Extension

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.