Interim Management Statement

12 Nov 2008 07:00

RNS Number : 9545H
Central Rand Gold Limited
12 November 2008
 



Immediate Release
12 November 2008

Central Rand Gold

Interim Management Statement

November 12 2008 - London and Johannesburg listed Central Rand Gold ("CRG") is pleased to provide an operational update on progress being made with the development of CRG's assets in southern Johannesburg. Highlights include:

Award of New Order Mining Right on September 17, 2008, with the formal execution of the right on November 11, 2008.

Commencement of trial mining - Gekko Plant was commissioned on October 1, 2008

Bulk sampling and drilling results

Appointments - geologist and project manager 

CRG remains on track to produce at an annualised rate of 100,000 oz Au by Dec 2009

Publication of feasibility study expected in Q1 2009

Update on water pumping at South West Vertical 1 (SWV1) shaft

Cash at hand as at 30 September 2008 - US$ 105.8 million

First gold pour expected before year end 2008

"After receiving our first New Order Mining Right on September 17, we moved swiftly to commence trial mining on October 1, with our focus now firmly on generating early cash flows, publishing our feasibility study and meeting our initial gold production target," said Greg James, CEO of Central Rand Gold.

"Ongoing exploration and underground bulk sampling continue to be a major priority as we concentrate on building our resource base and upgrading resources to proven reserves."

A copy of the press release with all of the associated maps is available on the web site of Central rand Gold on www.centralrandgold.com.

For further information please contact:
Greg James
(011) 551 4000
Greg.james@centralrandgold.com
Enquiries:
Buchanan Communications Limited +44 (0) 20 7466 5000
Bobby Morse / Ben Willey
 
Evolution Securities Limited +44 (0) 20 7071 4300
Simon Edwards / Chris Sim / Neil Elliot
 
Jenni Newman Public Relations (Pty) Ltd +27 (0) 11 772 1033
Jenni Newman / Megann Outram
 
Macquarie First South Advisers (Pty) Ltd +27 (0) 11 583 2307
Amanda Markman / Thato Morojele / Annerie Britz

Operational Update

New Order Mining Right

Central Rand Gold received its first New Order Mining Right ("the mining right") from the South African Department of Minerals and Energy (DME) on September 17, just 14 months after initial application was made.

The mining right enables the company to now rapidly transform from an explorer to an active miner at its Consolidated Main Reef, Langlaagte and Crown Mines tenements in the Central Rand Goldfield.

The targeted resource for initial operations in the awarded New Order Mining Right has been depicted in the table below:

SITE

MASS-t

GRADE-g/t

CONTENT-oz

8/9

12 930 000

5,76

2 400 000

5

13 000 000

5,54

2 320 000

4

3 790 000

3,61

440 000

7

3 950 000

3,71

940 000

Total

33 670 000

5,19

5 620 000

This is the first mining right in a series of New Order mining rights that will be applied for by CRG. The next two applications will be made in 2009. 

Commencement of Trial Mining

Trial mining commenced as scheduled on October 1, utilising a crushing and concentrating plant acquired from Gekko Systems in Australia. The plant has a capacity of 20 tons/hour or around 12,000 tonnes per month and is expected to produce gold at a rate of 750-1,500 ounces per month.

A major objective of the trial mining process is to convert resources into reserves by affirming mining and metallurgical processes, physically testing mining and backfilling techniques and refining metallurgical processes and equipment.

Ore parcels of between 100 tons and 500 tonnes are being processed through the Gekko plant to test ore grades and recoveries. 

Order placed for concentrate processing plant; board approves purchase of second crusher and concentrator plant

The company has ordered a pilot Carbon In Leach (CIL) concentrate processing plant and has received Board approval to acquire an additional 30 tonnes/hour (18,000 tonnes/month) crusher and concentrator plant to increase its initial gold production rate and enhance its bulk mining opportunities.

The CIL plant is expected to be operational in the first quarter of 2009 while the second processing plant is scheduled to be operational before the end of March or early April 2009.

By processing its own concentrate instead of toll-treating, the company will gain higher gold recoveries and benefit from cost savings. It is estimated the CIL plant will operate initially at a cost of some R90/tonne, reducing to some R60/tonne in October 2009 as capacity is increasingly utilised. This compares with considerably higher toll treatment costs. 

The additional crushing and concentrating plant will enable the company to process up to 30,000 tonnes of material per month in total at two different locations and accelerate gold production.

The first crushing and concentrating plant (costing approximately US$ 1.7 million) as well as the CIL plant (costing approximately US$ 2.5 million) have already been paid for and the second crusher and concentrating plant will cost approximately US$ 5.5 million.

Surface drilling and bulk sampling results
·; Surface Drilling:
·; Around 59,000 metres of diamond and RC drilling has been completed
·; Resource has been upgraded by 1.8 million oz to 35.6 million oz as a result of exploration work
·; There has been confirmation of un-mined mineralised pillars and reefs
·; RC drilling has been carried out on pyritic quartzites at Village Main and City Deep
·; Uncomplicated orebodies = potential for better recoveries.
·; Reconnaissance mapping & trenching has identified:
·; Un-mined sections of North and Main Reef
·; Un-mined duplicated sections of Bird & Kimberley Reefs – faulting
·; Large sections of un-worked Elsburg Reefs towards southern boundary of 3Cs
·; Potential additional tonnage - mineralised halos in hanging wall and footwall of conglomerate bands of Main Reef package – leaching potential
·; Bulk Sampling
·; Discovery of gold outside reef horizons indicates a potential increase in mineable tonnes and resources.
·; Underground bulk sampling has been undertaken to quantify mineralized zones in hanging and footwalls and between reef mineralization (it was established that channel/chip sampling was not delivering sufficient representivity)
·; Using an innovative approach CRG has developed a breakthrough in continuous bulk sampling
·; A headgear, winder and hoistroom have been successfully installed on East Shaft to assist with haulage of bulk samples

 

Appointments

Two further senior members to the senior management team have been appointed:

Riccardo Francesco Tonini: Riccardo started his project management career at Bateman  Engineered Technologies 13 years ago, where he has held various positions from Senior Project Manager to his present position as General Manager: Project Execution (a board level position within the company). In this role, he had overall responsibility for management of projects, construction, commercial, safety, health & environment and IT systems development and implementation. 

Keith Matier: Keith started his career as a geologist at a contract geological service provider in 1993, where he was responsible for all geological activities for clients. He specialises in large scale platinum and gold exploration projects. Keith has gained his experience through working at MSA Geoservices.

Water Pumping at SWV1 Shaft

On October 6, 2008, the company received notification of East Rand Proprietary Mines Limited's (ERPM) withdrawal of pumping at the SVW1 shaft. This was in response to the death of two employees owing to asphyxiation while conducting routine water measurements. These pumps are utilised to maintain the water levels in the Central Rand at approximately 900 metres below surface. 

Central Rand Gold has calculated that ERPM's decision to stop pumping at its south-west vertical shaft will have no short or medium term effects on its own mining operations.

Pre-empting that pumping may at some stage cease, CRG five months ago conducted an investigation which showed that it would take at least four years for this underground water to affect or interfere with its own shallow mining operations in the area. ERPM had been pumping water at a rate of 60 megalitres per day.

CRG is confident that it has ample time to address this situation and is examining its various options. 

Cash Position

At at September 31, 2008 the company had US$ 105.8 million in cashThe majority of cash is currently held in British Pounds. Despite the weakening of the Pound against the US$ over the last few weeks, the South African Rand is the currency in which the company has most of its operational cash exposure. The Rand has reported weakening against both the US$ and the Pound over this period. 

The Board is meeting in December where a full review of the 2009 mining plan and budget will be considered in light of the current cash resources available to the company. Further updates to the market will follow in due course.

Following this review the Company will revise, update and upgrade its current draft feasibility study to the level and accuracy appropriate to the reviewed mining plan. This exercise is expected to take four months to complete and will be a significant part of the confirmation and upgrading of mineral resources to reserves.

The current cash spend is in line with budget estimations. 

Overview

CRG has one of the largest gold resources in the world. Its management ream has a strong track record of building large scale mining projects. Through the application of tried and tested mining methods, around four million ounces of gold is expected to be extracted from the CMR, Langlaagte and CMR tenements alone over the next seven years. The company has the necessary political and community backing following a highly inclusive Environmental Impact Study process.

Ends

Issued on behalf of: Central Rand Gold Limited

Date: November 12, 2008

About CRG

Central Rand Gold is engaged in gold mining and exploration in southern Johannesburg, South Africa. With JORC and SAMREC-compliant resources of over 35.6m oz of gold, CRG has a primary listing on the London Stock Exchange and a secondary listing on the JSE Limited. CRG's operating subsidiary Central Rand Gold South Africa is currently involved in prospecting an area south of the Johannesburg Central Business District, known as the 3C's (Consolidated Main Reef, Crown Mines and City Deep) as well as Langlaagte, the farm where gold was first discovered in the Witwatersrand in 1886 by Australian prospector George Harrison.

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
IMSGUGGUGUPRGMG
Date   Source Headline
1st Feb 20107:00 amRNSTotal Voting Rights
1st Feb 20107:00 amRNSInvestor and Analyst Site Visit Presentation
29th Jan 20103:31 pmRNSNOTIFICATION OF MAJOR INTEREST IN SHARES
22nd Jan 20107:00 amRNSPlacing and operational update
25th Nov 20093:00 pmRNSNotice of Change of Auditor
25th Nov 20097:00 amRNSPuno Gold Investments complaint rejected by FSB
20th Nov 20097:00 amRNSPuno Gold Investments applies for leave to appeal
17th Nov 20097:00 amRNSInterim Management Statement
5th Nov 20092:30 pmRNSCourt Case Update
14th Oct 200911:30 amRNSPDMR's Dealings
13th Oct 200910:44 amRNSPuno Gold Investments Court Case Date Postponed
14th Sep 200912:30 pmRNSSeptember 2009 Investor and Analyst Presentation
9th Sep 20097:00 amRNSPuno Update
27th Aug 200910:00 amRNSMain Reef Package Intersection
25th Aug 20097:30 amRNSINITIAL RESERVE STATEMENT FOR CENTRAL RAND GOLD
25th Aug 20097:30 amRNSInterim Results
28th Jul 20097:00 amRNSFirst Gold Smelt
21st Jul 200911:00 amRNSBoard Subcommittee Reconstitutions
16th Jul 20094:40 pmRNSSecond Price Monitoring Extn
16th Jul 20094:35 pmRNSPrice Monitoring Extension
8th Jul 20097:00 amRNSOperations Update
26th Jun 20092:00 pmRNSBoard Appointments to CRGSA
4th Jun 20097:00 amRNSSenior Management Appointment
21st May 20092:30 pmRNSResult of AGM
21st May 20097:00 amRNSAnnual General Meeting - Webcast & Conference Call
19th May 200911:54 amRNSInterim Management Statement
19th May 200911:47 amRNSBoard and Senior Management Changes
14th May 20092:00 pmRNSBEE Update
9th Apr 20097:00 amRNSBEE Update
3rd Apr 20097:00 amRNSReserve Statement Update
1st Apr 200910:00 amRNSAGM Notice
31st Mar 200911:30 amRNSToll Treatment Arrangement
25th Mar 20099:00 amRNSAnnual Results
9th Mar 200911:30 amRNSAustralian Investor Meetings
5th Mar 200912:52 pmRNSAppointment of Company Secretary
4th Mar 20099:00 amRNSCOMMENCEMENT OF DECLINE DEVELOPMENT
26th Feb 20092:00 pmRNSNew Order Mining and Prospecting Rights Granted
16th Feb 200910:02 amRNSBEE Developments
5th Feb 20097:00 amRNSAnalyst Site Visit
29th Jan 20097:00 amRNSOperational Update
16th Jan 200912:13 pmRNSDirector/PDMR Shareholding
5th Dec 20089:00 amRNSCENTRAL RAND GOLD LIMITED APPOINTS NEW CEO
4th Dec 200812:25 pmRNSFirst Gold Pour
2nd Dec 20087:00 amRNSHolding(s) in Company
12th Nov 20081:30 pmRNSHolding(s) in Company
12th Nov 20087:00 amRNSInterim Management Statement
7th Nov 200811:00 amRNSResignation of Company Secretary
6th Nov 20084:43 pmRNSSecond Price Monitoring Extn
6th Nov 20084:41 pmRNSPrice Monitoring Extension
13th Oct 200812:00 pmRNSHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.