Platanillo - Operations Update

22 Oct 2008 07:00

RNS Number : 3910G
Amerisur Resources PLC
22 October 2008
 



22nd October 2008 

Amerisur Resources Plc ("the Company")

Platanillo - Operations Update

Amerisur Resources Plc, the oil and gas explorer and developer focused on South America is pleased to announce an update of testing operations of wells Alea-1R and Platanillo-2 in the Platanillo Block, PutumayoColombia.

Both wells were tested in natural flow from the Lower U formation through a selection of choke sizes during the period 27th July 2008 to 19th September 2008. Average flow rates from Alea-1R were 39 BOPD and 66 BOPD for Platanillo-2. These data were in line with previously calculated well efficiencies and confirmed regional production characteristics, which indicate that the aquifer support is moderate, and as expected may require some form of artificial lift, like most wells in the region in order to optimise production levels.

On 20th September 2008 a Hydraulic Jet Pump was installed in Platanillo-2 and a similar pump was installed in Alea-1R on 26th September 2008. The wells were then tested individually to ascertain their performance under artificial lift conditions. It should be borne in mind that Hydraulic Lift systems, by their very nature are designed on the basis of theoretical hydrodynamic models which require verification under field conditions. Alea-1R has been tested at the lowest design setting of the pump, i.e. an injection pressure of 500psi, and produced an average of 166 BOPD with 0.5% BS&W. This test confirmed the design of the pump, and indicates that the previously calculated Productivity Index (PI) of the zone is correct at 0.34 BOPD/psi of drawdown.

Platanillo-2 was tested at the same design point (500psi injection) and produced an average of 199 BOPD with 0.2% BS&W. Taking account of the slight design differences between the wells, this confirms the PI of 0.74 BOPD/psi of drawdown for this well. The produced crude oil has an API of approximately 31 degrees.

Having confirmed the pump design and deliverability of the wells at this lowest setting, in the next weeks the company will proceed to test both wells simultaneously at increasing injection pressure. The eventual stable production rate will be selected on the basis of good reservoir management practice and operational considerations. According to the design profile of the lifting system and the results obtained to date, with an injection pressure of 1500psi Alea-1R would deliver 370 Barrels of fluids per day and Platanillo-2 540 Barrels of fluids per dayThe hydraulic pumps installed have an injection pressure design range from 500 to 2000 psi.

The oil produced during these tests is being sold to Ecopetrol S.A. and is delivered to the Mansoya terminal, located 75km from the well location via oil trucking.

The Company is operator of the block and holds a 60 per cent. working interest through its subsidiary, Amerisur Exploración Colombia under the Platanillo Exploration and Production Contract with the ANH. Ecopetrol S.A. holds a 40% interest.

Dr. John Wardle, Amerisur´s Chief Executive Officer commented:

"I am pleased with the results as they stand and am encouraged by the way the wells have reacted to artificial liftThese results, obtained through a careful and technically robust evaluation give grounds for optimism regarding the intended strategy for the third well in the Platanillo field. We foresee continued activity in the block through 2009, which will further reveal the ultimate potential of the project, and will allow us to continue to build on what has become an attractive and flexible position. We are now looking at other attractive opportunities to use our significant cash resources backed by our income stream to further enhance our portfolio. We are looking forward to updating shareholders as the strategy develops over the next months."

Giles Clarke, Chairman commented:

"We have come a long way over the last 18 months and we are now on production testing at two wells, which is due to ramp up significantly in the months ahead. We have a controlling interest in our two main assets and have a clear roadmap to deliver value to shareholders from this powerful position."

Ends

Competent person: Technical information in this announcement has been reviewed by John Wardle Ph.D., the Company's Chief Executive. John Wardle has 24 years experience in the industry, having worked for BP, Britoil, Emerald Energy and Pebercan, and is a trained drilling engineer.

ENQUIRIES:

Billy Clegg/Caroline Stewart

Financial Dynamics

Tel: +44 (0)207 831 3113

Jerry Keen/Andrew Raca,

Blue Oar Securities Plc

Tel: +44 (0)20 7448 4400

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCPUGWWUUPRGMG
Date   Source Headline
22nd Mar 201711:03 amRNSHolding(s) in Company
20th Mar 20172:28 pmRNSNotification of Major Interest in Shares
16th Mar 20177:44 amRNSCaguan-Putumayo Basin Acquisitions
10th Mar 20174:35 pmRNSPrice Monitoring Extension
9th Mar 201712:47 pmRNSPlatanillo Operations Update
9th Mar 20177:00 amRNSMonthly Production and OBA Throughput Update
31st Jan 201711:34 amRNSTotal Voting Rights
27th Jan 20177:00 amRNSHolding(s) in Company
24th Jan 20177:00 amRNSPlatanillo 24 Update
19th Jan 20175:05 pmRNSHolding(s) in Company
9th Jan 20177:24 amRNSPlatanillo-24 Update
3rd Jan 20177:00 amRNSBoard Changes and Remuneration Update
23rd Dec 20167:00 amRNSSpudding of Platanillo 24
22nd Dec 201610:51 amRNSDirector/PDMR Shareholding
20th Dec 20167:00 amRNSColombia Asset Acquisition
16th Dec 20167:00 amRNSColombia Business Update
2nd Dec 20169:51 amRNSBlock listing six monthly return
1st Nov 20167:00 amRNSHolding(s) in Company
27th Oct 20161:12 pmRNSOBA Pipeline Operational
27th Oct 201612:45 pmRNSOBA Pipeline Operational
3rd Oct 20162:55 pmRNSHolding(s) in Company
3rd Oct 20167:00 amRNSOBA Pipeline Update
21st Sep 20167:00 amRNSAnalyst site visit and 2017 guidance
15th Sep 20167:00 amRNSInterim Results
12th Jul 20167:00 amRNSOperations Update
4th Jul 201612:21 pmRNSHolding(s) in Company
27th Jun 20163:59 pmRNSHolding(s) in Company
23rd Jun 20162:35 pmRNSCommencement of Drilling on Platanillo Field
17th Jun 20167:05 amRNSCoati Update
17th Jun 20167:05 amRNSOperations Update
3rd Jun 20167:00 amRNSOperations Update
1st Jun 20169:02 amRNSBLOCK LISTING SIX MONTHLY RETURN
31st May 20167:00 amRNSIndependent Non-executive Director Appointment
23rd May 20163:31 pmRNSLong Term Incentive Plan ("LTIP") Awards
4th May 20163:20 pmRNSResult of AGM
4th May 20169:30 amRNSAGM Statement
22nd Apr 20167:00 amRNSSpudding of Jaguareté-1, Paraguay
8th Apr 20167:00 amRNSNotice of AGM
7th Apr 20167:00 amRNSFinal Results for the year ended 31 December 2015
5th Apr 20169:17 amRNSHolding(s) in Company
29th Mar 20167:00 amRNSReserves Update
16th Mar 20167:00 amRNSIssue of Equity
14th Mar 20164:47 pmRNSHolding(s) in Company
14th Mar 20164:46 pmRNSHolding(s) in Company
14th Mar 20167:00 amRNSHolding(s) in Company
9th Mar 201610:24 amRNSResults of placing
9th Mar 20167:00 amRNSProposed Placing
4th Mar 20161:40 pmRNSHolding(s) in Company
29th Feb 20167:00 amRNSChange of Adviser
18th Feb 20167:00 amRNSEcuador-Colombia Interconnector Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.